129
This is an extract from Dr. Sam's forthcoming book “Contract Administration in the
Middle East under FIDIC — 4° Edition (copy right pending) -
Clauses 51 and 52 are the Clauses most misunderstood by many
Engineers and other Contract Administrators. The root cause of many a
claim in the industry is either the inadequate valuation of a variation or
the questionable validity’ of a variation. Through proper understanding
of Clauses 51 and 52 and their application in the intended manner,
many disputes could be avoided
Contract Administrators should note that, what is varied is not the
Contract but the Works and therefore, expressions such as “Variation of
the Contract’, “Variation to the Contract”, ‘Contract Amendment” eto.
should not be used when referring to a variation of the Works, under the
Contract
It is incorrect to construe the expression “No such variation shall in any
way vitiate or invalidate the Contract ......” stated in Sub-Clause 51.1, to
mean that the Contractor is obliged to carry out any variation, instructed
by the Engineer. The expression “...... the Contractor shall do ......"has
already imposed this obligation on the Contractor. It is the Engineer who
shall not “vitiate or invalidate the Contract’ by instructing variations
‘Changes onginated by the Contractor and executed in the absence of an instruction from the:
Engineer, do not constitute variations pursuant to Clause 51, though many Contractors claim
them to be variations. There afe many instructions issued by the Engineer during the
‘execution of @ project (such as instructions to change an unacceptable method of working or,
to clarify the scope of work) which do not constitute variations, either. Employers often
question the authority of the Engineer to issue a variation or, the necessity for a variation
{contending that the work is already included in the original scope of work, and as such shall
‘not constitute a variation)130
which are neither “necessary” nor “appropriate”. He should also not
instruct those changes stated in page 81 of the table given in Section
26,
Contractors often claim that changes initiated and carried out by them
should be considered as variations pursuant to Sub-Clause 51.1. Their
Contract Administrators should note that the first sentence? of Sub-
Clause 51.2 prohibits them to make any variation without an instruction
of the Engineer.
Contractors often argue that the proviso in Sub-Clause 51.2 implies that
the differences between the quantities of the Works and those stated in
the Bill of Quantities, are variations pursuant to Sub-Clause 51.1 (a)
The discussion on page 177 is applicable to this scenario too. The
expression “..... quantity of any work .....” in Sub-Clause 51.1 (a)
refers to actual quantities and not to estimated quantities. Therefore the
changes in estimated quantities do not constitute variations.
Some Engineers refuse to accept the valuation of variations submitted
by Contractors and/or to certify payment in respect thereof, where
notice has not been given pursuant to Sub-Clauses 52.2 (a) of 52.2 (b)
The opening sentence of Sub-Clause $1.1 restricts the Engineer's authority to make
variations which are only “necessary” or “appropriate”.
* The Contractor shall not make any such Variation without an instruction of the Engineer.431
They offer the literal meaning of the second paragraph’ of Sub-Clause
62.2 as the reason for such refusal. This is one instance where a Sub-
Clause in FIDIC ~ 4" Edition needs to be construed to produce an
acceptable and intended meaning, by departing from its literal meaning
Engineers should apply the following tests in this instance :~
- Was it the intention of the parties that the Employer should have the
varied work executed at the Contractor's cost (e.g. :- a valid variation
for additional work) ?
- Should the Contractor receive payment for work not executed by him
(e.g. = an omission instructed as a variation under a lump sum
contract) ?
If the first variation is not valued. it would not be acceptable to the
Contractor whilst the second would not be acceptable to the Employer,
if not valued. To be fair to both parties, variations need to be valued
even in the absence of a notice pursuant to Sub-Clause 52.2.
Therefore the requirement of notice in Sub-Clause 52.2 should be
construed as a prerequisite to only claims for extra payments or varied
rates or prices, (i. the effect of the variations) and not for the purpose
of valuing the variations,
770 varied work instructed to be done by the Engineer pursuant to Clause 51 shail be
valued under Sub-Clause 52.1 or under this Sub-Clause unless notice shail have been
given