Chapter 8: Interim Conclusions and Recommendations
Chapter 8: Interim Conclusions and Recommendations
RECOMMENDATIONS
After careful review of traffic demand forecast made in Phase 1 Study, the traffic demand
forecast on MRT Line 6 is carried out more precisely taking into account the stage construction
plan mentioned in 8.2. The results of traffic demand forecast are shown in Figure 8.1-1.
700 656
637
Estimated Volume (Stage3) 619
600
582
600 563*
544
526
507
489 491
500 Estimeted Volume (Stage2) 475
458
442
426
410*
397
383
400
200
/d
y
)p
0m
rV
u
(1lP
g
n
e
s o
T
ta
100
0
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Open
Year
The proposed Mass Rapid Transit Railway (MRT) System Line 6 starts form UTTARA North and
terminates to Saidabad, total length of 20.8 km. Total number of stations is 18 stations.
The Study Team proposes to construct MRT Line 6 by following three (3) stages as;
Ga
uge
Minimum Radius
The Safety is the most important Mission of Transport Entities. The following transport policy is
After careful study of alternative route study, the proposed route illustrated in Figure 5.1-1 in
The Study Team examines three major structure types such as 1) at-grade structure, 2) elevated
25m Standard Span length of Precast Box Girder is recommended for Guideway Structure
30m & 40m Span of Precast Box Girder are is recommended at road intersections.
60m Span Cantilever Type of Precast Box Girder is recommended at Mirpur 10 and
Sonargaon intersections.
Large Size Single Bored Pile Foundation is recommended to minimize the influence to the
According to the Seismic Zoning Map of Bangladesh, proposed MRT Line 6 is located in
1) Depot Location
The location in Uttara area which is far from Pallabi station to the northern direction approx. 1
km, is recommended for construction a depot. It is better to locate the depot parallel to an
alignment of MRT Line 6 stage 3. Because, this location is not so far from a main line, cause least
resettlement and effects on environmental and development plan in the future. However, further
discussions with RAJUK, NHA, BWDB and MOD is strongly recommended in design stage for
2) Depot Foundation
The earth filling method is recommended for low land and swampy land which will cause no
effect on the flow of water after filling. While the artificial foundation method is recommended for
an area in water retention pond which any obstruction to water flow in prohibited.
It is strongly recommended to carry out more geotechnical and hydrological surveys at the depot
area in design stage. The consolidation settlement should be calculated carefully in advance for
After careful examination of the operation of the MRT Line 6, it is proposed the following
operation plan;
6:00 ~ 170 Trains 6 Cars 10:00 3:20 Min. 6:00 Min. 4:00 Min 10:00
8.2.3 Station and Equipment, Signal and Telecommunication, Electrification and Depot Plan
Elevated Type of Station is proposed along the existing road or alignment route.
Concourse is proposed at 2nd floor level and Platform is proposed at 3rd floor level.
Lateral type platform is recommended for intermediate stations and Island type platform is
recommended for terminal stations such as Pallabi Sta., Sonargaon Sta. and Saidabad Sta.
Basically it is proposed that one ticket barrier for one station to minimize the related facilities
such as ticket bending machine, automatic gate, ticketand ticket reader and so on.
Barrier free design shall be adopted. Elevator and stairs are proposed between ground floor
and concourse level. Elevator, escalator and stairs are proposed between concourse level and
platform level.
Prayer room and toilet are proposed for passenger and station staff.
Based on the preliminary investigation made, the following station equipment is proposed for
Equi Proposal
pme
nt
Tick
Automatic Fare Collection System is proposed for MRT Line 6
Syst
・Automatic Gate(Capacity:Maximum about 60 pax / min)
of Line 6
Tick
et
lator station.
Elev
Elevator is proposed to be installed between concourse and platform.
ator
Main specification is as follows
Barrier-free function
Since it is the first electric railway in Dhaka, Bangladesh, the following facilities, which are
required for the safety and enable operation and maintenance, shall be recommended as the plan
Items Recommendations
As the plan for MRT Line 6, the following facilities shall be recommended for the safety
Items Recommendations
System(LCX)
Monitoring System
System
In order to operate MRT Line 6, it is essential to provide electric power for train operation and
pertained facilities such as signal & telecommunication, lighting, ventilation and air condition,
etc. At the first step, the electric power requirement is calculated and location of substation is
proposed as follows;
Based on the electric power requirement, the Study Team together with DTCB will discuss the
As for centenary electric wire, it is recommended for the MRT Line 6 to employ 2 types of electric
It is recommended to design the depot with sufficient space and facilities for the maximum
capacity of all 3 stages i.e. 28×6 car trains. The necessary area for a depot is approximate 222,000
The preliminary design of depot layout in this report is used for planning and preliminary budget
costing purposes and should be reviewed in details during the design stage. The depot layout
should be adjusted by discussions with RAJUK, NHB, BWDB, MOD and other relative
The implementation schedule has been tentatively prepared as realistic by reference to past
The Station square plan is examined on the basis of location of MRT station, number of
passengers used to the station, bus routes, etc. The following table shows the category of station
square.
Station
Uttara Nor
Notes; Type 1: Station square with other mass transit transportation connection, connection
Type 2: Station square for Bus bay, CNG bay and Rickshaw bay
Uttara Cen
Type 3: Traffic line for Bus, CNG and Rickshaw for getting on and off
DTCB as a project proponent is highly recommended to take the following actions from
N o.
L iaiso n to
and M inis
obtain appr
The Draft Final Report will be submitted and discussed at the end of January 2011. At around
time, JICA appraisal mission would be dispatched here when the Government of Bangladesh
2010 2011
9 10 11 12 1 2 3 4 ・・・・・
DHUTS Phase 2 Study, Feasibility
Study of MRT Line 6
Reports
ITR DFR FR
Remarks
Appraisal Misssion will be disptached when GOB reuestsfinancial
assistant to GOJ