Earth Work in Excavation: Date Description Nos Length Width Depth Quantity Cumulative in RM Inrminrmincum Quantity in CUM

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 35

EARTH WORK IN EXCAVATION

Date Description Nos Length Width Depth Quantity Cumulative


In RM In RM In RM In CUM Quantity in CUM

28.10.2018. For footing P1 :- C240, C241. 2 2.300 1.450 1.500 10.005

For footing P2 :- C238 & C239. 1 2.750 1.450 1.500 5.981

29.10.2018. For footing P1 :- C242, C243.


C244,C247,C248,C249. 6 2.300 1.450 1.500 30.015

For footing P2 :- C245 & C246. 1 2.750 1.450 1.500 5.981

30.10.2018. For footing P1 :- C250, C253. 2 2.300 1.450 1.500 10.005

31.10.2018. For footing P1 :- C254, C257,C258. 3 2.300 1.450 1.500 15.008

For footing P2 :- C255 & C256. 1 2.750 1.450 1.500 5.981

04.11.2018. For footing P1 :- C259. 1 2.300 1.450 1.500 5.003

05.11.2018. For footing P1 :- C304,C305,


C306,C309,C310,C313. 6 2.300 1.450 1.500 30.015

For footing P2 :- C307 & C308. 1 2.750 1.450 1.500 5.981

06.11.2018. For footing P1 :- C314,C315,


C316,C317. 4 2.300 1.450 1.500 20.010

07.11.2018. For footing P1 :- C320,C321,C322. 3 2.300 1.450 1.500 15.008

For footing P2 :- C318 & C319. 1 2.750 1.450 1.500 5.981


32
08.11.2018. For footing P1 :- C323,C3327,C328,
C329,C330. 5 2.300 1.450 1.500 25.013

For footing P2 :- C325 & C326. 1 2.750 1.450 1.500 5.981 195.968
Contd…..P/2
Page No.-2
EARTH WORK IN EXCAVATION
Date Description Nos Length Width Depth Quantity Cumulative
In RM In RM In RM In CUM Quantity in CUM
B/F…… 195.968
10.11.2018. For footing P1 :- C331,C334,C335. 3 2.300 1.450 1.500 15.008

For footing P2 :- C332 & C333. 1 2.750 1.450 1.500 5.981

15.11.2018. For footing P1 :- C340,C341,C342,


C343,C346. 5 2.300 1.450 1.500 25.013

For footing P2 :- C344 & C345. 1 2.750 1.450 1.500 5.981

Contd…..P/3
SAND FILLING
Date Description Noes Length Width Depth Quentity Cumulative
In RM In RM In RM In CUM Quentity in CUM

29.10.2018. For footing P1 :- C240, C241. 2 2.300 1.450 0.300 2.001

For footing P2 :- C238 & C239. 1 2.750 1.450 0.300 1.196

30.10.2018. For footing P1 :- C242, C243.


C244,C247,C248,C249. 6 2.300 1.450 0.300 6.003

For footing P2 :- C245 & C246. 1 2.750 1.450 0.300 1.196

31.10.2018. For footing P1 :- C250, C253. 2 2.300 1.450 0.300 2.001

01.11.2018. For footing P1 :- C254, C257.


C258. 3 2.300 1.450 0.300 3.0015

For footing P2 :- C255 & C256. 1 2.750 1.450 0.300 1.196

05.11.2018. For footing P1 :- C259. 1 2.300 1.450 0.300 1.001

06.11.2018. For footing P1 :- C304,C305,


C306,C309,C310,C313. 6 2.300 1.450 0.300 6.003

For footing P2 :- C307 & C308. 1 2.750 1.450 0.300 1.196

07.11.2018. For footing P1 :- C314,C315,


C316,C317. 4 2.300 1.450 0.300 4.002

08.11.2018. For footing P1 :- C320,C321,


C322. 3 2.300 1.450 0.300 3.0015

For footing P2 :- C318 & C319. 1 2.750 1.450 0.300 1.196 32.995

09.11.2018. For footing P1 :- C323,C327,


C328,C329,C330. 5 2.300 1.450 0.300 5.0025

For footing P2 :- C318 & C319. 1 2.750 1.450 0.300 1.196

For footing P2 :- C325 & C326. 1 2.750 1.450 0.300 1.196


Contd…..P/2
Page No.-2
SAND FILLING

Date Description Noes Length Width Depth Quentity Cumulative


In RM In RM In RM In CUM Quentity in CUM
B/F…… Contd…..P/2

11.11.2018. For footing P1 :- C331,C334,


C335. 3 2.300 1.450 0.300 3.002

For footing P2 :- C332 & C333. 1 2.750 1.450 0.300 1.196

16.11.2018. For footing P1 :- C340,C341,C342,


C343,C346. 5 2.300 1.450 0.300 5.003

For footing P2 :- C344 & C345. 1 2.750 1.450 0.300 1.196


Contd…..P/3
POLYTHENE SHEET
Date Description Nos Length Width Quantity Cumulative
In RM In RM In SQM Quantity in SQM

29.10.2018. For footing P1 :- C240, C241, 2 2.300 1.450 6.670

For footing P2 :- C238 & C239. 1 2.750 1.450 3.988

30.10.2018. For footing P1 :- C242, C243,C244,


C247,C248,C249. 6 2.300 1.450 20.010

For footing P2 :- C245 & C246. 1 2.750 1.450 3.988

31.10.2018. For footing P1 :- C250,C253. 2 2.300 1.450 6.670

01.11.2018. For footing P1 :- C254, C257,C258. 3 2.300 1.450 10.005

For footing P2 :- C255 & C256. 1 2.750 1.450 3.988

05.11.2018. For footing P1 :- C259. 1 2.300 1.450 3.335

06.11.2018. For footing P1 :- C304,C305,


C306,C309,C310,C313. 6 2.300 1.450 20.010

For footing P2 :- C307 & C308. 1 2.750 1.450 3.988

07.11.2018. For footing P1 :- C314,C315,


C316,C317. 4 2.300 1.450 13.340

08.10.2018. For footing P1 :- C320,C321,C322. 3 2.300 1.450 10.005

For footing P2 :- C318 & C319. 1 2.750 1.450 3.988

09.10.2018. For footing P1 :- C323,C327,


C328,C329,C330. 5 2.300 1.450 16.675

For footing P2 :- C325 & C326. 1 2.750 1.450 3.988

11.10.2018. For footing P1 :- C331,C334.


C335. 3 2.300 1.450 10.005
For footing P2 :- C332 & C333. 1 2.750 1.450 3.988
Contd…..P/2
Page No.-2
POLYTHENE SHEET

Date Description Nos Length Width Quantity Cumulative


In RM In RM In SQM Quantity in SQM
B/F……

Contd…..P/3
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM

20.09.2018. Shuttering for P.C.C. 16 1.500 0.100 2.400

21.09.2018. Shuttering for P.C.C. 16 1.500 0.100 2.400

22.09.2018. Shuttering for P.C.C. 4 1.500 0.100 0.600

Shuttering for R.C.C. 8 1.500 0.450 5.400 10.800

27.09.2018. Shuttering for P.C.C.


For footing P1 :- C104, C105. 4 2.300 0.100 0.920
4 1.450 0.100 0.580

For footing P2 :- C106 & C107. 2 2.750 0.100 0.550


2 1.450 0.100 0.290

28.09.2018. Shuttering for P.C.C.


For footing P1 :- C102, C103. 4 2.300 0.100 0.920
4 1.450 0.100 0.580

Shuttering for R.C.C.


For footing P1 :- C 105. 2 2.100 0.450 1.890
2 1.250 0.450 1.125

For footing P2 :- C106 & C107. 2 2.550 0.450 2.295


2 1.250 0.450 1.125

29.09.2018. Shuttering for P.C.C.


For footing P1 :- C101 2 2.300 0.100 0.460
2 1.450 0.100 0.290

For footing P2 :- C99 & C100. 2 2.750 0.100 0.550


2 1.450 0.100 0.290

Shuttering for R.C.C.


For footing P1 :- C 102, 103. 4 2.100 0.450 3.780
4 1.250 0.450 2.250

30.09.2018. Shuttering for P.C.C.


For footing P1 :- C95, C96,C97, 8 2.300 0.100 1.840
C98. 8 1.450 0.100 1.160 20.895
Contd…..P/2
Page No.-2
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM
B / F…… 20.895
01.10.2018. Shuttering for P.C.C.
For footing P1 :- C90, C91, C94. 6 2.300 0.100 1.380
6 1.450 0.100 0.870

For footing P2 :- C92 & C93. 2 2.750 0.100 0.550


2 1.450 0.100 0.290

Shuttering for Column under


Tie Beam
For Column No:- C105, C106. 8 0.400 0.750 2.400

02.10.2018. Shuttering for R.C.C.


For footing P1 :- C96,C97,C98, 10 2.100 0.450 9.450
C101, C104. 10 1.250 0.450 5.625

For footing P2 :- C99 & C100. 2 2.550 0.450 2.295


2 1.250 0.450 1.125

Shuttering for Column under


Tie Beam
For Column No:- C102, C103. 8 0.400 0.750 2.400

03.10.2018. Shuttering for R.C.C.


For footing P1 :- C90,C91,C94, 8 2.100 0.450 7.560
C95. 8 1.250 0.450 4.500

For footing P2 :- C92 & C93. 2 2.550 0.450 2.295


2 1.250 0.450 1.125

04.10.018. Shuttering for P.C.C.


For footing P1 :- C87, C88, C89. 6 2.300 0.100 1.380
6 1.450 0.100 0.870

For footing P2 :- C85 & C86. 2 2.750 0.100 0.550


2 1.450 0.100 0.290

Shuttering for Column under


Tie Beam
For Column No:- C96, C97,C98,
C100,C101,C104,C107. 28 0.400 0.750 8.400 74.250

Contd…..P/3
Page No.-3
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM
B / F…… 74.250
05.10.018. Shuttering for P.C.C.
For footing P1 :- C80, C81, C82, 10 2.300 0.100 2.300
C83,C84. 10 1.450 0.100 1.450

06.10.018. Shuttering for P.C.C.


For footing P1 :- C69, C70, C73, 10 2.300 0.100 2.300
C77,C108. 10 1.450 0.100 1.450

For footing P2 :- C78 & C79. 2 2.750 0.100 0.550


2 1.450 0.100 0.290

Shuttering for R.C.C.


For footing P1 :- C88,C89. 4 2.100 0.450 3.780
4 1.250 0.450 2.250

Shuttering for Column under


Tie Beam
For Column No:- C90, C91,C93,
C94,C95,C99. 24 0.400 0.750 7.200

Shuttering for Tie Beam


Column C104 To C106. 4 4.100 0.600 9.840
7 0.400 0.600 1.680
8 0.075 0.600 0.360

Shuttering for Column above


Tie Beam
For Column No:- C104, C105,
C106. 12 0.400 2.250 10.800

07.10.018. Shuttering for Tie Beam


Column C104 To C106. 8 4.100 0.600 19.680
9 0.400 0.600 2.160
16 0.075 0.600 0.720

08.10.018. Shuttering for P.C.C.


For footing P1 :- C74, C75. 4 2.300 0.100 0.920
4 1.450 0.100 0.580

For footing P2 :- C71 & C72. 2 2.750 0.100 0.550


2 1.450 0.100 0.290 143.400
Contd…..P/4
Page No.-4
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM
B / F…… 143.400
08.10.018. Shuttering for R.C.C.
For footing P1 :- C81,C82,C83, 10 2.100 0.450 9.450
C84,C87. 10 1.250 0.450 5.625

For footing P2 :- C85 & C86. 2 2.550 0.450 2.295


2 1.250 0.450 1.125

09.10.018. Shuttering for R.C.C.


For footing P1 :- C73,C74,C75, 10 2.100 0.450 9.450
C77,C80. 10 1.250 0.450 5.625

For footing P2 :- C78 & C79. 2 2.550 0.450 2.295


2 1.250 0.450 1.125

10.10.018. Shuttering for R.C.C.


For footing P1 :- C108 2 2.100 0.450 1.890
2 1.250 0.450 1.125

Shuttering for Column above


Tie Beam
For Column No:- C100, C101,
C102,C103. 16 0.400 2.250 14.400

Shuttering for Coping


Column C105 To C106. 2 4.100 0.075 0.615
2 4.900 0.150 1.470
1 0.400 0.150 0.060

11.10.018. Shuttering for P.C.C.


For footing P1 :- C62, C63, C66, 10 2.300 0.100 2.300
C67,C68. 10 1.450 0.100 1.450

For footing P2 :- C64 & C65. 2 2.750 0.100 0.550


2 1.450 0.100 0.290
Shuttering for R.C.C.
For footing P1 :- C70 2 2.100 0.450 1.890
2 1.250 0.450 1.125

For footing P2 :- C71 & C72. 2 2.550 0.450 2.295


2 1.250 0.450 1.125 210.975
Contd…..P/5
Page No.-5
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM
B / F…… 210.975
12.10.018. Shuttering for P.C.C.
For footing P1 :- C59, C60, C61, 8 2.300 0.100 1.840
C76. 8 1.450 0.100 1.160

Shuttering for Column under


Tie Beam
For Column No:- C108. 4 0.400 1.050 1.680

Shuttering for Coping


Column C103 To C105. 4 4.100 0.075 1.230
2 9.000 0.150 2.700

13.10.018. Shuttering for Column under


Tie Beam
For Column No:- C107. 4 0.400 0.300 0.480 220.065
Contd…..P/6
Page No.-6
SHUTTERING WORK

Date Description Noes Length Height Quentity Cumulative


In RM In RM In SQM Quentity in SQM
B / F……
P.C.C. (1:2:4)
Date Description Noes Length Width Depth Quentity Cumulative
In RM In RM In RM In CUM Quentity in CUM

29.10.2018. For footing P1 :- C240, C241. 2 2.300 1.450 0.100 0.667

For footing P2 :- C238 & C239. 1 2.750 1.450 0.100 0.399

30.10.2018. For footing P1 :- C242, C243.


C244,C247,C248,C249. 6 2.300 1.450 0.100 2.001

For footing P2 :- C245 & C246. 1 2.750 1.450 0.100 0.399

31.10.2018. For footing P1 :- C250, C253. 2 2.300 1.450 0.100 0.667

01.11.2018. For footing P1 :- C254, C257.


C258. 3 2.300 1.450 0.100 1.0005

For footing P2 :- C255 & C256. 1 2.750 1.450 0.100 0.399

05.11.2018. For footing P1 :- C259. 1 2.300 1.450 0.100 0.334

06.11.2018. For footing P1 :- C304,C305,


C306,C309,C310,C313. 6 2.300 1.450 0.100 2.001

For footing P2 :- C307 & C308. 1 2.750 1.450 0.100 0.399

07.11.2018. For footing P1 :- C314,C315,


C316,C317. 4 2.300 1.450 0.100 1.334

08.11.2018. For footing P1 :- C320,C321,


C322. 3 2.300 1.450 0.100 1.0005

For footing P2 :- C318 & C319. 1 2.750 1.450 0.100 0.399 10.998

09.10.2018. For footing P1 :- C323,C327,


C328,C329,C330. 5 2.300 1.450 0.100 1.668

For footing P2 :- C325 & C326. 1 2.750 1.450 0.100 0.399


Contd…..P/2
Page No.-2
P.C.C. (1:2:4)
Date Description Noes Length Width Depth Quentity Cumulative
In RM In RM In RM In CUM Quentity in CUM
B/F…… 0
11.11.2018. For footing P1 :- C331,C334.
C335. 5 2.300 1.450 0.100 1.668

For footing P2 :- C332 & C333. 1 2.750 1.450 0.100 0.399

Contd…..P/3
REINFORCEMENT WORK

Date Description Noes Quentity TotalQuentity Cumulative


In KG In KG Quentity in KG

22.09.2018. 2

28.09.2018. For footing P1 :- C105. 1 87.005 87.005

For footing P2 :- C106 & C107. 1 126.722 126.722

29.09.2018. For footing P1 :- C102,C103.. 2 87.005 174.01

01.10.2018. R.C.C. for Column under


Tie Beam
For Column No. C105, C106. 2 5.056 10.112

02.10.2018. For footing P1 :- C96,C97,C98,


C101,C104. 5 87.005 435.025

For footing P2 :- C99 & C100. 1 126.722 126.722

R.C.C. for Column under


Tie Beam
For Column No. C102, C103. 2 5.056 10.112

03.10.2018. For footing P1 :- C90,C91,C94,


C95. 4 87.005 348.02

For footing P2 :- C99 & C100. 1 126.722 126.722

04.10.2018. R.C.C. for Column under


Tie Beam
For Column No. C96, C97,C98,
C100,C101,C104,C107. 7 5.056 35.392

06.10.2018. For footing P1 :- C88,C89. 2 87.005 174.010

R.C.C. for Column under


Tie Beam
For Column No. C90,C91,C93,C94,
C95,C99. 6 5.056 30.336 1684.188
Contd…..P/2
Page No.-2
REINFORCEMENT WORK

Date Description Noes Quentity TotalQuentity Cumulative


In KG In KG Quentity in KG
B / F…… 1684.188

06.10.2018. R.C.C. for Tie Beam 1684.188


From Column C100 To C107 1 152.022 152.022

08.10.2018. For footing P1 :- C81,C82,C83,C84,


C87. 5 87.005 435.025

For footing P2 :- C85 & C86. 1 126.722 126.722

09.10.2018. For footing P1 :- C73,C74,C75,C77,


C80. 5 87.005 435.025

For footing P2 :- C78 & C79. 1 126.722 126.722 2959.704


2959.704
Contd…..P/3
R.R.C. (1:1.5:3)

Date Description Nos Length Width Depth Quantity Cumulative


In RM In RM In RM In CUM Quntity in CUM

31.10.2018. For footing P2 :- C238 & C239. 1 2.550 1.250 0.450 1.434

01.11.2018. For footing P1 :- C240, C241.


C242,C243. 4 2.100 1.250 0.450 4.725

For footing P2 :- C245 & C246. 1 2.550 1.250 0.450 1.434

02.11.2018. For footing P1 :- C244, C247,


C248. 3 2.100 1.250 0.450 3.544

03.11.2018. R.C.C. for Column under


Tie Beam
For Column No :- C239, C240,
C241,C242,C243. 5 0.400 0.400 1.050 0.840

04.11.2018. For footing P1 :- C249. 1 2.100 1.250 0.450 1.181

R.C.C. for Column under


Tie Beam
For Column No :- C244, C245,
C247,C248. 4 0.400 0.400 1.050 0.672

05.11.2018. For footing P1 :- C250, C253,


C254,C257. 4 2.100 1.250 0.450 4.725

For footing P2 :- C255 & C256. 1 2.550 1.250 0.450 1.434

R.C.C. for Column under


Tie Beam
For Column No :- C238. 1 0.400 0.400 1.050 0.168

06.11.2018. For footing P1 :- C258,C259. 2 2.100 1.250 0.450 2.363

R.C.C. for Column under


Tie Beam
For Column No :- C246, C249,
C250. 3 0.400 0.400 1.050 0.504 23.025
23.025 Contd…..P/2
Page No:-2
R.R.C. (1:1.5:3)

Date Description Noes Length Width Depth Quentity Cumulative


In RM In RM In RM In CUM Quentity in CUM
B/F…… 23.025
07.11.2018. For footing P1 :- C304, C305,
C306,C309,C310. 5 2.100 1.250 0.450 5.906

For footing P2 :- C307 & C308. 1 2.550 1.250 0.450 1.434

08.11.2018. For footing P1 :- C313, C314,


C315,C316,C317. 5 2.100 1.250 0.450 5.906

09.11.2018.

10.11.2018. For footing P1 :- C320,C321,


C322,C323,C327. 5 2.100 1.250 0.450 5.906

For footing P2 :- C325 & C326. 1 2.550 1.250 0.450 1.434

R.C.C. for Column under


Tie Beam
For Column No :- C253, C254,
C255,C257,C258. 5 0.400 0.400 1.050 0.840

11.11.2018. For footing P1 :- C328,C329. 2 2.100 1.250 0.450 2.363

R.C.C. for Column under


Tie Beam
For Column No :- C256, C259. 2 0.400 0.400 1.050 0.336

12.11.2018. For footing P1 :- C330,C334,


C335. 3 2.100 1.250 0.450 3.544

13.11.2018. For footing P1 :- C331. 1 2.100 1.250 0.450 1.181

For footing P2 :- C332 & C333. 1 2.550 1.250 0.450 1.434


Contd…..P/3
Page No:-3
Page No:-4

Date Description Noes Length Width Depth Quentity Cumulative


In RM In RM In RM In CUM Quentity in CUM
B/F…… #REF!
13.11.2018. R.C.C. for Column under
Tie Beam
For Column No :- C304,C305,
C306,C307,C309. 5 0.400 0.400 1.050 0.840
Contd…..P/4
Page No:-4
EARTH WORK IN EXCAVATION
Date Description Noes Length Width Depth Quentity Cumulative
In RM In RM In RM In CUM Quentity in CUM

28.10.2018. For footing P1 :- C240, C241. 2 2.300 1.450 0.700 4.669

For footing P2 :- C238 & C239. 1 2.750 1.450 0.700 2.791

29.10.2018. For footing P1 :- C242, C243.


C244,C247,C248,C249. 6 2.300 1.450 0.700 14.007

For footing P2 :- C245 & C246. 1 2.750 1.450 0.700 2.791

30.10.2018. For footing P1 :- C250, C253. 2 2.300 1.450 0.700 4.669

31.10.2018. For footing P1 :- C254, C257.


C258. 3 2.300 1.450 0.700 7.0035

For footing P2 :- C255 & C256. 1 2.750 1.450 0.700 2.791

04.11.2018. For footing P1 :- C259. 1 2.300 1.450 0.700 2.335

05.11.2018. For footing P1 :- C304,C305,


C306,C309,C310,C313. 6 2.300 1.450 0.700 14.007

For footing P2 :- C307 & C308. 1 2.750 1.450 0.700 2.791

06.11.2018. For footing P1 :- C314,C315,


C316,C317. 4 2.300 1.450 0.700 9.338

07.11.2018. For footing P1 :- C320,C321,


C322. 3 2.300 1.450 0.700 7.0035

For footing P2 :- C318 & C319. 1 2.750 1.450 0.700 2.791

08.11.2018. For footing P1 :- C323,C3327,C328,


C329,C330. 5 2.300 1.450 0.700 11.673

For footing P2 :- C325 & C326. 1 2.750 1.450 0.700 2.791 91.452
Contd…..P/2
Page No.-2
EARTH WORK IN EXCAVATION
Date Description Noes Length Width Depth Quentity Cumulative
In RM In RM In RM In CUM Quentity in CUM
B/F….. 91.452
10.11.2018. For footing P1 :- C331,C334,C335. 3 2.300 1.450 0.700 7.004

For footing P2 :- C332 & C333. 1 2.750 1.450 0.700 2.791

15.11.2018. For footing P1 :- C340,C341,C342,


C343,C346. 5 2.300 1.450 0.700 11.673

For footing P2 :- C344 & C345. 1 2.750 1.450 0.700 2.791

Contd…..P/3
REINFORCEMENT WORK

Description Dia of Spacing of Cutting No. of Total Length Unit Weight Total Weight Total Weight
Bar Bar Length Im Meter Bars in Meter in Kg. / Meter in Kg. in MT.

FOOTING 10mm 125 C/C 1.650 17 28.050 0.620 17.391


P1 10mm 125 C/C 2.500 10 25.000 0.620 15.500
10mm 250 C/C 1.650 9 14.850 0.620 9.207
10mm 250 C/C 2.500 6 15.000 0.620 9.300
8mm Binder 3.570 2 7.140 0.390 2.785
10mm Chair 1.640 6 9.840 0.620 6.101
Total 60.284

FOOTING 10mm 125 C/C 1.650 21 34.650 0.620 21.483


P2 10mm 125 C/C 2.950 10 29.500 0.620 18.290
10mm 250 C/C 1.650 11 18.150 0.620 11.253
10mm 250 C/C 2.950 6 17.700 0.620 10.974
8mm Binder 4.020 2 8.040 0.390 3.136
10mm Chair 1.640 8 13.120 0.620 8.134
Total 73.270

COLUAM 10mm 8 Nos 0.690 8 5.520 0.620 3.422


AT FOOTING 8mm 150C/C 1.430 3 4.290 0.390 1.673
450 8mm 150C/C 1.130 3 3.390 0.390 1.322
Total 6.417
REINFORCEMENT WORK

Description Dia of Spacing of Cutting No. of Total Length Unit Weight Total Weight Total Weight
Bar Bar Length Im Meter Bars in Meter in Kg. / Meter in Kg. in MT.

COLUAM 10mm 8 Nos 0.750 8 6.000 0.620 3.720


750 8mm 150C/C 1.430 5 7.150 0.390 2.789
8mm 150C/C 1.130 5 5.650 0.390 2.204
Total 8.713

COLUAM 10mm 8 Nos 1.050 8 8.400 0.620 5.208


1050 8mm 150C/C 1.430 7 10.010 0.390 3.904
8mm 150C/C 1.130 7 7.910 0.390 3.085
Total 12.197
TIE BEAM 12mm 4 Nos 28.020 4 112.080 0.890 99.751
Lap 57D 12mm 4 Nos 0.690 8 5.520 0.890 4.913
10mm 2 Nos 27.820 2 55.640 0.620 34.497
Lap 57D 10mm 2 Nos 0.570 4 2.280 0.620 1.414
For Tie Beam 8mm 200C/C 1.610 12 19.320 0.390 7.535
For Tie Beam 8mm 300C/C 1.610 6 9.660 0.390 3.767
For Coluam 10mm 8 Nos 0.600 8 4.800 0.620 2.976
For Coluam 8mm 150C/C 1.430 4 5.720 0.390 2.231
8mm 150C/C 1.130 4 4.520 0.390 1.763
Total 158.847

COLUAM 10mm 8 Nos 2.685 8 21.480 0.620 13.318


2400 8mm 150C/C 1.430 16 22.880 0.390 8.923
8mm 150C/C 1.130 16 18.080 0.390 7.051
Total 29.292
REINFORCEMENT WORK

Description Dia of Spacing of Cutting No. of Total Length Unit Weight Total Weight Total Weight
Bar Bar Length Im Meter Bars in Meter in Kg. / Meter in Kg. in MT.

COLUAM 10mm 8 Nos 2.385 8 19.080 0.620 11.830


2100 8mm 150C/C 1.430 14 20.020 0.390 7.808
8mm 150C/C 1.130 14 15.820 0.390 6.170
Total 25.808

COPPING 8mm 6 Nos 27.520 6 165.120 0.390 64.397


Lap 57D 8mm 12 Nos 0.460 12 5.520 0.390 2.153
8mm 150C/C 1.050 28 29.400 0.390 11.466
Total 78.016
BRICK WORK

Date Description Noes Length Width Depth Quentity Cumulative


In RM In RM In RM In CUM Quentity in CUM

07.10.2018. Brick WORK


08.10.2018. Column C105 To C106. 1 4.100 0.250 2.250 2.306

11.10.2018. Brick WORK


Column C103 To C105. 2 4.100 0.250 2.250 4.613 6.919
Contd…..P/2
Page No.-2
BRICK WORK

Date Description Noes Length Width Depth Quentity Cumulative


In RM In RM In RM In CUM Quentity in CUM

07.10.2018. Brick WORK


08.10.2018. Column C105 To C106. 1 4.100 0.250 2.250 2.306

11.10.2018. Brick WORK


Column C103 To C105. 2 4.100 0.250 2.250 4.613 6.919
Contd…..P/3
Item Description of items Nos Length Width Depth Qaentity
No In RM In RM In RM In CUM
1 Earth work in excavation
depth upto 1500 mm.

For footing P1 :- 14 2.300 1.450 1.500 70.035

For footing P2 :- 3 2.750 1.450 1.500 17.944


TOTAL 87.979

2 Earth work in excavation


depth 1500 mm to 3000 mm.

For footing P1 :- 14 2.300 1.450 0.600 28.014

For footing P2 :- 3 2.750 1.450 0.600 7.178


TOTAL 35.192

4 Silver sand filling.

For footing P1 :- 14 2.300 1.450 0.300 14.007

For footing P2 :- 3 2.750 1.450 0.300 3.589


TOTAL 17.596

5 Single brick flat soling.

For tie beam :- 15 4.100 0.250 15.375

6 Ordinary cement concrete (1:2:4) (P.C.C.)

For footing P1 :- 14 2.300 1.450 0.100 4.669


For footing P2 :- 3 2.750 1.450 0.100 1.196
TOTAL 5.865

7 Reinforced cement concrete (1:1.5:3)


(a) For footing base :-
For footing P1 :- 14 2.100 1.250 0.450 16.538
For footing P2 :- 3 2.550 1.250 0.450 4.303
(b) for Column under tie beam :-
For column :- 20 0.400 0.400 1.050 3.360

(c) for tie beam :- 15 4.100 0.250 0.600 9.225


19 0.400 0.400 0.600 1.824
C/O…… 35.250
3 Earth work in filling. B/F…… 35.250
(d) for Column above tie beam :-
For column :- 19 0.400 0.400 1.950 5.928
TOTAL 41.178

15 Cover block making.


50 mm
For footing P1 :- 14 16 224
For footing P2 :- 3 18 54
40 mm
For column :- 20 8 160
19 8 152
19 8 152
30 mm
For tie beam :- 15 20 300
TOTAL 1042
39 Shuttering work.
For P.C.C.
For footing P1 :- 28 2.300 0.100 6.440
28 1.450 0.100 4.060

For footing P2 :- 6 2.750 0.100 1.650


6 1.450 0.100 0.870
For R.C.C.
(a) For footing base :-
For footing P1 :- 28 2.100 0.450 26.460
28 1.250 0.450 15.750

For footing P2 :- 6 2.550 0.450 6.885


6 1.250 0.450 3.375
(b) for Column under tie beam :-
For column :- 80 0.400 1.050 33.600

(c) for tie beam :- 30 4.100 0.600 73.800


43 0.400 0.600 10.320
66 0.075 0.600 2.970
(d) for Column above tie beam :-
For column :- 76 0.400 1.950 59.280
TOTAL 245.460

Extra Labour charges for Laying


of polythene sheet.
For footing P1 :- 14 2.300 1.450 46.690
For footing P2 :- 3 2.750 1.450 11.963
TOTAL 58.653

14 Labour charges for chipping.


For column :- 32 0.400 1.950 24.960
For tie beam :- 15 4.100 0.250 15.375
TOTAL 40.335

17 250mm thick Brick work in


superstrucure. (1:6) 15 4.100 0.250 1.950 29.981

35 Reinforcement work.

41 Shuttering board making.

Labour charges for Laying of polythene sheet.

You might also like