How to Do the Power test for 3G

1. Deactivate the Cell HSDPA at RNC side:----Please inform to NOC


BSS Team and tell to deactivate
DEA UCELLHSDPA:CELLID=54321;
DEA UCELLHSDPA:CELLID=54322;
DEA UCELLHSDPA:CELLID=54323;
2. Login the NodeB via LMT or webLMT:------Start the Download test
STR DLSIM: LR=99;
3. Open the output power monitoring:
Please get the RRU Subrack No. by using LST RRU command;
Save for all 3 sectors. ----wait for 5mins;

4. STOP the DL test by using following command at NodeB side.

STP DLSIM:;
5. Finally activate the Cell HSDAP at RNC side.(ACT UCELLHSDPA)