Installation of 110 KV D/C Ohtl From 380/110 KV Khulais BSP To 110/13.8Kv S/S Gulf Salman Jeddah, Saudi Arabia Foundation Setting Plan

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

INSTALLATION OF 110 KV D/C OHTL FROM 380/110 KV KHULAIS BSP TO 110/13.

8KV S/S GULF SALMAN JEDDAH, 
SAUDI ARABIA
FOUNDATION SETTING PLAN          
TOWER TYPE "TT" (PAD & CHIMNEY) FD = 4.0M
(REF. WE ‐ 294348 R.0 SHT. 01 OF 01)
Hv 1293.6 793.6 + 500 (Ref. WE‐294347 SHT. 1 R.0) yb 42.4 Neutral axis

Hf 3700 Chimney height + structure pad (=3400 + 300) Hs 950 Stub height Bottom of GL      (Ref. 


WE‐294347 SHT. 1 R.0))
Hv + Hf 4993.6 Hv + Hs 2243.6

A C Tan (theta) Theta P L R H
NO. EXTENSION Actual b/b  Projected b/b 
(See Ref.)     (See Ref.)   Radian Degrees c/c  dist. c/c diag. dist.
stub dist. stub dist.
1 BB+L2       6,630.00         6,905.00  0.1063 6.067          7,106.96            7,691.56            7,607.24           10,758.26 

2 BB+L4       7,053.00         7,328.00  0.1063 6.067          7,529.96            8,114.56            8,030.24           11,356.47 


3 BB+L6       7,475.00         7,750.00  0.1063 6.067          7,951.96            8,536.56            8,452.24           11,953.27 
4 BB+L8       7,898.00         8,173.00  0.1063 6.067          8,374.96            8,959.56            8,875.24           12,551.48 
5 BB+L10       8,321.00         8,596.00  0.1063 6.067          8,797.96            9,382.56            9,298.24           13,149.70 
6 BB+6BE+L2       7,898.00         8,173.00  0.1063 6.067          8,374.96            8,959.56            8,875.24           12,551.48 
7 BB+6BE+L4       8,321.00         8,596.00  0.1063 6.067          8,797.96            9,382.56            9,298.24           13,149.70 
8 BB+6BE+L6       8,744.00         9,019.00  0.1063 6.067          9,220.96            9,805.56            9,721.24           13,747.91 
9 BB+6BE+L8       9,167.00         9,442.00  0.1063 6.067          9,643.96         10,228.56          10,144.24           14,346.12 
10 BB+6BE+L10       9,590.00         9,865.00  0.1063 6.067        10,066.96         10,651.56          10,567.24           14,944.33 
11 BB+12BE+L2       9,167.00         9,442.00  0.1063 6.067          9,643.96         10,228.56          10,144.24           14,346.12 
12 BB+12BE+L4       9,590.00         9,865.00  0.1063 6.067        10,066.96         10,651.56          10,567.24           14,944.33 
13 BB+12BE+L6     10,012.00       10,287.00  0.1063 6.067        10,488.96         11,073.56          10,989.24           15,541.13 
14 BB+12BE+L8     10,435.00       10,710.00  0.1063 6.067        10,911.96         11,496.56          11,412.24           16,139.34 
15 BB+12BE+L10     10,858.00       11,133.00  0.1063 6.067        11,334.96         11,919.56          11,835.24           16,737.56 

NOTES:
THETA = ATAN ((C ‐ A) / (2 * Hv)
P = A +2 * ( Hv + Hs ) * TAN (teta)
L = A +2 * ( Hv + Hf ) * TAN (teta)
R = L ‐ 2 * yb * COS (teta)
Hv = STUB VERTICAL HEIGHT
Hf = CHIMNEY VERTICAL HEIGHT TO G.L
Yb = STUB NEUTRAL AXIS