Professional Documents
Culture Documents
MGO 634 作業8
MGO 634 作業8
1.
Events typically designate the start or completion of an activity and do not consume
resources.
A path traces the predecessor-successor relationship that exist among activities and events
Dummy activity are nothing and are simply used to maintain predecessor-successor
relationships.
management would give us a brief schedule and a diagram which includes all relationship
with our clients or subcontractors for our project. Those documents could let us know what
we should do right now and who we should find when we need help or ask. If we wanted
The most common approach to project scheduling is the use of network techniques such as
PERT and CPM. The Program evaluation and review technique was developed by the US
navy in cooperation with Booz Allen Hamilton and the Lockheed Corporation for the
Polaris missile/submarine project in 1958. And the Critical path method was developed by
the DuPont.
PERT is commonly used for R&D projects whereas CPM is used in construction industry.
Use of PERT has been decreased in the recent years and a large majority of Project
Originally, PERT used to determine the probability of the project completion date. CPM
used to control both the time and cost aspects of the project. Both techniques identified the
critical path with activities that could not be delayed without lengthening the project
completion time.
In 2005, the project management institute renamed PERT as ADM i.e “Arrow diagram
method” and CPM as PDM i.e “Precedence diagram method”. In general, they are referred
to either as a “network,” but if we refer specifically to a PERT network where the activities
are shown as arrows on the network, then they are called as AOA (activity-on-arrow)
network, and if we refer to a CPM network where the activities are shown as nodes then
It always begins with a node called “Start”. Activities ‘a’ and ‘b’ have no predecessors
The arrowheads show the direction of precedence. Activity ‘c’ follows ‘a’, activity ‘d’
Now, activity ‘f’ follows both ‘c’ and ‘d’. The WBS does not indicate any further activity
is required to complete the task, so we have reached the end of this particular plan. We thus
draw arrows from activities ‘e’ and ‘f’ to the node END,
Constructing the Network, AOA Version
Again begin with the node called “Start”. Activities ‘a’ and ‘b’ have no predecessors
so we draw arrows labeled ‘a’ and ‘b’ from Start and terminating in circle shaped nodes
numbered 1 and 2.
Activity ‘c’ follows ‘a’, activity ‘d’ follows ‘b’, and activity ‘e’ also follows ‘b’. Let’s add
these arrows to our AOA network, labeling the arrows and nodes sequentially.
Activity ‘f’ must follow both ‘c’ and ‘d’, but any given activity must have its source in one
and only one node. Therefore, ‘c’ and ‘d’ must terminate at the same node. So we need to
erase activity ‘d’ and its node and redraw ‘d’ to end at the same node that terminates ‘c’.
Then we need to add activity ‘e’ following ‘b’, and ‘f’ following ‘c’ and ‘d’. Because ‘e’
and ‘f’ have no successors, they will terminate at the END node.
The choice between Activity on Arrow and Activity on node is largely a matter of personal
preference. AON is used in PC based commercially available computer software and AON
networks are easier to draw than the AOA because they sometimes require use of dummy
activity to aid in indicating a particular precedence via a dashed arc. A dummy activity has
I only saw them once or twice when I got into a task force meeting room. Rarely team
members could get into the meeting room, so that's why I only saw them once or twice.
For our company, this diagram is not essential and not useful. We usually use Gantt