Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Insein GTI ( 204 ' x 72' ) Up to ( 3.12.

2018) JOB Progress

No Particular Quantity Units Amount workdone amount Progress

1 Site Clearing 16800 sq.ft 273000 218400 0.29%

2 Staking Work 14688 sq.ft 880490 880490 1.17%

3 Earthwork 45300.5 cu.ft 5889065 4711252 6.28%

4 1:3:6 Lean concrete work 1617.88 cuft 3914777 3131821.6 4.18%

5 1:2:4 R.C. C concrete work 6835.3 cu.ft 22324222 14510744.3 19.36%

6 Formwork 5509.72 sq.ft 11073765.4 7197947.51 9.60%

7 Mild Steel Reinforcement 21.42 t0ns 21008500 16806800 22.43%

8 Overhead & Contingency 5987979.5 5987979.5 7.99%

9 Commercial tax 3567571.43 3567571.43 4.76%

74919370.33 57013006.34 76.06%

You might also like