Professional Documents
Culture Documents
9.1 Snagging and De-Snagging Process
9.1 Snagging and De-Snagging Process
Snagging refers to a process that takes place prior to practical completion when an area
is considered complete by a contractor and is offered ready for inspection.
A snagging list (occasionally referred to as a punch list) is prepared and issued by the
appropriate certifying authority, typically this will be the employer and client
representative. The faults that are identified should be rectified prior to a certificate of
practical completion being issued.
Snagging in such circumstances might begin months before overall project completion.
It may also mean that some areas are physically complete but without the services
having been commissioned. This should be noted on the snagging sheet and the snags
should be closed prior to get FAC (Final Acceptance Certificate) from the client.
Contractor will adopt a testing that rigorously tests each element of the system
throughout the construction to ensure faults are identified and rectified, and future is
optimized wherever applicable. The aim of the testing shall be to ensure a robust
construction that meets the intended designed requirement.
o To verify that the performance of the installed equipment/systems meet with the
specified design intent through a series of tests and adjustments.
o To capture and record performance data of the whole installation as the baseline
for future operation and maintenance.
A spare part, spare, service part, repair part, or replacement part, is an interchangeable
part that is kept in an inventory and used for the repair or replacement of failed units.
According to the Project, BOQ Volume 4 only street lighting spare parts will be
provided to end user. The spare parts list are below:
According to the BOQ of the project there is no status of material for any scope of work
that client will provide the materials? Not Applicable for this project.
Testing and commissioning is one the important element of the project, Similarly that
will following throughout the project from initial testing and site installation and
execution till handing over to the end user for the final testing. Record should be
documented under the surveillance off supervision consultant. e.g.
ADDC- Power substation testing and commissioning
ADDC-water flushing and disinfection etc.
With regards of mandatory approvals is the base expected prior to signing the contract
and there one stand application to be followed by all parties from the date of award till
effect and liability period. Record is the backbone of any contract. Contract even the
mandatory contract inform and contract settlement this record including the following
but not limited.