Professional Documents
Culture Documents
Cut Fill Analysis-Final Bid
Cut Fill Analysis-Final Bid
Negative is fill
Burm,2m
distance from O Elvn Diff H:V Elvn (1:25) diff Adjus ele Req'd adj Final elev.
17.83 15.00 2.00
0.00 0.00 0.00 0.00 0.00 0.00 2.00 -2.00
33.99 33.99 2.00 17.00 1.91 0.09 2.27 1.73 0.27
33.60 67.59 4.00 17.00 3.79 0.21 4.51 1.49 2.51
26.04 93.63 6.00 13.00 5.25 0.75 6.24 1.76 4.24
55.32 148.95 8.00 28.00 8.35 -0.35 9.93 0.07 7.93
25.91 174.86 10.00 13.00 9.81 0.19 11.66 0.34 9.66
37.96 212.82 12.00 19.00 11.93 0.07 14.19 -0.19 12.19
Slope change 11.13 14.00 0.00 0.00
47.06 259.88 14.00 24.00 16.23 -2.23 15.55 -1.55 15.55
30.68 290.56 16.00 15.00 18.99 -2.99 17.74 -1.74 17.74
17.00 307.56 18.00 9.00 20.52 -2.52 18.96 -0.96 18.96
18.39 325.95 20.00 9.00 22.17 -2.17 20.27 -0.27 20.27
10.32 336.27 22.00 5.00 23.10 -1.10 21.01 0.99 21.01
22.06 358.33 24.00 11.00 25.08 -1.08 22.58 1.42 22.58
15.21 373.54 26.00 8.00 26.45 -0.45 23.67 2.33 23.67
15.76 389.30 28.00 8.00 27.86 0.14 24.80 3.20 24.80
389.30
0.00
2.00
4.00
6.00
Actual elevation obtained at the end of 1:15 slope 8.00
12.19 10.00
12.00
14.00
16.00
18.00
20.00
22.00
24.00
26.00
28.00
-0.27
0.73
1.87 DIST ELVN MGL DIFF
2.87 0.00 0.00 7.28 0.00
6.00 1.67 8.95 0.00
15.00 4.17 11.45 0.55
22.00 6.11 13.39 0.61
29.00 8.06 15.34 0.66
38.00 10.56 17.84 0.16
43.00 11.94 19.23 0.77
53.00 14.72 22.00 0.00
61.00 16.94 24.23 -0.23
Slope change= 5.10
94.00 18.43 25.71 0.29
109.00 21.37 28.65 -0.65
0.00 0.00
34.00 2.00
49.00 4.00
62.00 6.00
77.00 8.00
83.00 10.00
92.00 12.00
99.00 14.00
106.00 16.00
115.00 18.00
120.00 20.00
130.00 22.00
138.00 24.00
171.00 26.00
186.00 28.00
DIS FROM SLOPE AVG 4.20
0.00 0.00 0.00 0.00 MGL DIFF
0.00 0.00 0.00 2.00 -2.00
2.00 5.00 5.00 2.50 -0.81 2.81
4.00 12.00 17.00 4.25 2.05 1.95
6.00 10.00 27.00 4.50 4.43 1.57
8.00 9.00 36.00 4.50 6.57 1.43
10.00 4.00 40.00 4.00 7.52 2.48
12.00 3.00 43.00 3.58 8.24 3.76
14.00 15.00 58.00 4.14 11.81 2.19
16.00 15.00 73.00 4.56 15.38 0.62
18.00 8.00 81.00 4.50 17.29 0.71
20.00 3.00 84.00 4.20 18.00 2.00
22.00 7.00 91.00 4.14 19.67 2.33
24.00 17.00 108.00 4.50 23.71 0.29
26.00 13.00 121.00 4.65 26.81 -0.81
Total
Height
Control Total No. (Lift Avilable
interval Area of Lifts Ht=4m) Volume
0
27731 4 31 859661
4
24739 6 24 593736
8
17334 5 20 346680
12
6508 4 16 104128
16
6662.9 3 12 79954.8
20
5755.5 2 8 46044
24
88730.4 1 4 354921.6
28
Total 2385125.4
Total Site Capacity=1363416m 3
Elevation Area bn eleAverage exiLandfill area within th Finised ga Cut depth Cut volume
0 2063
2 2065
6 2069 2065
10 2073 2069
14 2077 2073
16 2079 14452 2077 17379 2075 2 34758
18 2081 2077
22 2085 2081
26 2089 2085
zone1
zone2
zone3
zone4
zone5
zone6
zone7
Front recess
D 28.00 zone base area
BP 1,177.64 14,969.00 4 59,876.00
TP 913.08 23,535.00 8 188,280.00
VOLUME 3,703.73 17,379.00 12 208,548.00
6,817.00 16 109,072.00
6,596.00 20 131,920.00
Prism V 5,734.00 24 137,616.00
Tot A 82,052.71 835,312.00
D 28.00 Filling volume
VOLUME 2,297,475.88 V+ 1,458,460.15
2 2065
6 2069
10 2073
14 2077
18 2081
22 2085
26 2089
Excavation Phase 1
No of cell Top width Top Length B width B length
Land Fill 4 140.768991512 167.2427898 124.36899151 150.842789814
Common Exca 1
4 6508 874.7
5 6662.9 2012.7
6 5755.5
88730.4
4 6508 874.7
5 6662.9
6 5755.5
88730.4
Height of stock pile 5
Stock pile area 27,145.00
Volume to stockpile 90,483.33
2028 2029
Daily Cover 243,076.69 1139615 1235381.9
Waste volume Capacity = 1,215,383.46
Finished
grade Cut depth Cut volume
189658
359256
2063 2 12,236.00
470700
2065
278064
2067 2 29,938.00
81804
2069
52768
2071 2 47,070.00
22936
2073
1455186
2075 2 34,758.00
2077
2079 2 13,634.00
2081
2083 2 13,192.00
2085
2087 2 11,468.00
162,296.00
Depth Free B B Area T Area Volume Slope Zx
2 0.1 18760.1656 23542.59885968 44417.9027 2 8.44037914
Cumil A Lift H Cap Capacity with out Capacity with Avg. depthExcavation
27731 4 110,924.00 110924 92,436.67 2.00 55,462.00
- -
64801 4 259,204.00 259204 216,003.33 2.00 49,478.00
- -
98043.93 4 392,175.72 392175.72 326,813.10 2.00 34,668.00
- -
120418.83 4 481,675.32 481675.32 401,396.10 2.00 13,016.00
- -
133046.83 4 532,187.32 532187.32 443,489.43 2.00 13,325.80
- -
141900.43 4 567,601.72 567601.72 473,001.43 2.00 11,511.00
177,460.80
-
64801 4 259,204.00
120418.83 4 481,675.32
141900.43 4 567,601.72
me at landfill
Cut Volume Fill Volume Reusable Hauling soil Imported fill
Zy slope area 0.5 0.2 0.97
8.4403791384 2461.314 22208.9514 4441.79027 10230.9236 7536.2375 0
Cumlative excaslope length Slope area Total area to Cumill. ReusaHauling soil
55,462.00 168.00 1,502.64 27,889.64 22,184.80 33,277.2
- - - 0.0
104,940.00 217.3 1,943.59 24,944.19 51,840.80 53,099.2
- - - - 0.0
139,608.00 495.8 4,434.57 17,802.17 78,435.14 61,172.9
- - - - 0.0
152,624.00 326 2,915.83 6,815.83 96,335.06 56,288.9
- - - - 0.0
165,949.80 284.6 2,545.54 6,931.64 106,437.46 59,512.3
- - - - 0.0
177,460.80 198 1,770.97 5,942.47 113,520.34 63,940.5
90,325.94
SUMMARY SHEET
TOTAL
VAT(15%)
GRAND TOTAL
2.2 Supply and lay DN 200 PVC pipe for leachet collection. m 1,550.00
2.3 Trench excavation m³ 279.00
2.4 Masonry Work m³ 372.00
2.5 one meter diameter pipe Culverts m 14.00
2.6 Reinforced Concrete Work C-30 (Pond and manhole) m³ 146.00
2.7 Form Work (pond and manhole) m2 660.00
Sub-Total……………………………………………………………………………………
option 1
1 Sanitary Landfill -
2 Leachet collection & Treatment 0
3 Access road 0
4 Fence work 58560
5 Building blocks 153,101.00
211,661.00
243,410.15
deduction 4,726,540.34
appraisal?
option 2
1 Sanitary Landfill -
2 Leachet collection & Treatment 0
-
With VAT -
deduction 4,969,950.49
-
-
Six zones
No. Description Unit Quantity Rate Total Amount
ETB ETB
Bill No Solid waste
1 Sanitary Land fill
1.2 20 cm thick Clearing and Grubbing m² 69,804 0 -
1.3 Common excavation m³ 113,082 0 -
1.4 Excavation of soft rock m³ 12,565 0 -
Hauling excavated surplus material, hauling
1.5 distance up to 1 km m³ 61,173 0 -
1.6 Disposal off material to stockpile for reuse m³ 78,435 0 -
21.15
372
Grand Total 6193135.593525
Three zones
Quantity Rate Total Amount
ETB ETB
61,173 5 305,864.28
78,435 2 156,870.29
28,254 58 1,638,755.15
2,215.00 12 26,580.00
1,550.00 11 17,050.00
279.00 15 4,185.00
372.00 220 81,840.00
14.00 60 840.00
146.00 700 102,200.00
660.00 40 26,400.00
10% 25,909.50 -
285,004.50
Grand Total 4,878,087.75 -
4.6
1.84 46 230
ZONE TOTAL AREA TOTAL CUT VOLUME
ONE 93129.00 33975.77
TWO 46903.00 23904.75
THREE 19533.00 31651.26
FOUR 6535.00 3672.90 Stock pile area 27Ha.
Volume (m3)
GRAND T 166100.00 93204.69
assuming cover to SW 1:6 and 4.0m lift height lift base area
19972.43 ele
Available site capacity= 553666.666666667 m3 1 82052
2 59940
volume of cover= 92277.7777777778 3 44137
4 28758
5 17283
6 8957
TOTAL AVAILABLE SITE CAPACITY= 646871.35 7 2992
8 0
The landfill is sufficent till 2018[i.e. for 14 years]
2
23301.171896418 2 2
5825.293
D 28 Zone
BP 1177.635 14969 4 59876 1
TP 913.083 23535 4 94140 2
VOLUME 3703.728 17379 4 69516 3
6817 4 27268 4
6596 4 26384 5
5734 4 22936 6
Tot A 82052.71 300120
D 28
VOLUME 2297475.88 V+ 1993652 0
8
Hehight(m) 4
Stock pile area 27Ha. 27
Volume (m3) 720000
2
Added area on previous ones as next zone filling begins
Area 2nd 3rd 4th 5th 6th Cumil A Lift H Cap
27731 12331 1819.33 27731 4 110,924.00
24739 14089.6 6547 1674.9 64801 4 259,204.00
17334 9319.9 3415.5 1085.4 98043.93 4 392,175.72
6508 874.7 120418.8 4 481,675.32
6662.9 2012.7 133046.8 4 532,187.32
5755.5 141900.4 4 567,601.72
88730.4