96
Struktur Beton Jembatan
1. Pembebanan
B. Lap.aspal = 0,15 m x 22 KN/m³ x 1m x 2 = 6,6 kN/m
B. Lap.perkerasan = 0,20 m x 22 KN/m³ x 1 m x 2 = 8,8 kN/m
B. Plat injak = 0,25 m x 24 KN/m³ x 1 m x 1,3 = 7,8 kN/m
B. Kendaraan = 0,6 m x 17,2 KN/m x 1 m x 1,8 = 18,58 kN/m
41,78 kN/m
97
Struktur Beton Jembatan
C=0
Φ = 25˚
γm = 17,2 KN/m3
KN KN
(75,371 .2,2 m)+(68,263 .1,466 m)
m m
𝑦= = 1,851 m
143,634 KN/m
Wu = Pa = 143,634 KN/m
98
Struktur Beton Jembatan
fc’ = 32 MPa
fy = 400 MPa
Cek H minimum
hmin ≥ 200 mm
99
Struktur Beton Jembatan
fc′ 𝑀𝑢
𝜌𝑑𝑒𝑠𝑎𝑖𝑛 = 1,7 . ( ) . (0,5 − √0,25 − )
fy 1,36. b. d2 . fc′
32 263,817 .106
= 1,7 . ( ) . (0,5 − √0,25 − )
280 1,36. 1000 .2522 .32
= 0,0207
b 1000
As pakai = 1⁄4 𝜋𝑑2 . 𝑠 = 1⁄4 𝜋. 162 . 35
= 5744,626 mm²
As pakai > As perlu
100
Struktur Beton Jembatan
Sedangkan untuk tulangan susut di ambil nilai 50% dari tulangan pokok
As = 50% As = 50% x 5744,626 mm2 = 2872,313 mm2
101