Professional Documents
Culture Documents
Made Easy Book
Made Easy Book
Date (mm/dd/yy)
of Preparation of Estimate 17-Apr-15
Details Amount Leads
Embankment Earth 51.67 3.00
HMP 250.61 21.00
Crusher 250.61 21.00
Metal/ Stone Qry 250.61 21.00
Gravel 51.67 3.00
Sand 359.30 31.00
Varies with pipe
Hume Pipes dia. 67.00
BITUMEN Rates
LEAD 798.00
Grade 80/100 VG 10 31590.00
Grade 60/70 VG 30 32390.00
RS 25590.00
Emulsion SS 26920.00
CEMENT / STEEL Rates
CEMENT 6300.00
HYSD Steel 40000.00
6 mm Mild Steel 42000.00
MS STEEL 40000.00
ALLOWANCES
Place ITEM Name Value
DATA Labour Municipal Area Allowance %
RMR Metal %
RMR Gravel %
RMR Sand %
Overhead Charges ( R) 5.00 %
Overhead Charges ( B) 5.00 %
Contractors Profit 10.00 %
VAT 5.00 %
Centering Charges Local Entry %
GOVERNMENT OF TELANGANA
ROADS AND BUILDINGS DEPARTMENT.
From To
Chaitanya Projects Consultancy Pvt.Ltd The Superintending Engineer
(R&B) Circle ,
Warangal
Warangal Dist.
Sir,
Sub :- "Widening of existing Single lane /Intermediate lane to Double lane for the road (1)
pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal. Km.0/0 to 27/5 ,
(2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in karimnagar district
I request the Superintending Engineer (R&B) Rural Circle, Warangal dist to kindly
obtain necessary approval from the competent authority and communicate.
Yours faithfully
Enclosures ::
1 Plan and Profile
2 Detailed Cost estimate (Chitanya Projects Consultancy )
3 Managing Director
SPECIFICATION REPORT
"Widening of existing Single lane /Intermediate lane to Double lane for
the road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet
Name of Work :
Mandal. Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0
to 32/6" in karimnagar district
Amount of Estimate : Rs. 3550
Sulthanabad to Kalvasrirampur road is an important road in Warangal district .The existing single
lane Bituminous road is damaged, carriageway edges reduced and the berms are not sufficient also the
C.D. works are narrow. All these bad conditions are creating problems to the road user and the
existing width is not catering to many fold increased traffic. The surface is no at all suitable for fast
moving vehicles.
In view of the above mentioned conditions of the Road and as per the instructions of Higher
officials a detailed "& estimate for the Road is prepared to widen from existing single lane to Double
lane and bringing the total road to traffic worthy by strengthening , with the following provisions."
The estimate is prepared based on common SSR 2014-15 . The quarries and their leads are
taken from approved Quarry and Lead Charts. The work will be carried out as per specifications and
codal guide lines and relevant circular instructions issued time - to -time.
0
0
Asst. Executive Engineer Dy. Executive Engineer Executive Engineer,
R&B Section, ___ ___ ___ R&B Sub-Division___ _____ (R&B) Division, ___ ____ _____
GOVERNMENT OF
TELANGANA
D. P. R.
AMOUNT OF ESTIMATE
Rs 3550.0 Lakhs
Amount
S.No Description Remarks
(Rs.)
1 2 3 4
C C Drain
267458319
8 Segniorage 11064170
Amount in Cr 29.82
GENERAL ABSTRACT
Amount
S.No Description Remarks
(Rs.)
1 2 3 4
304496710
10 Segniorage 11064170
354846880
RR Masonry in CM(1:3)
37 1 cum 1.158 0.00 0.347 0.00
substructure
Ref:- For Emulsion (Bulk):-IOCL Price List With Effect From Dt.1-7-2015
For Bulk VG10 grade & VG30 grade:-IOCL Price List With Effect From Dt.16-7-15
Bulk Bulk
RS Emulsion
TYPE OF BITUMEN (80/100) (60/70)
Emulsion (M.S)
VG 10 VG 30
Machine Crushing
(-) Stacking Charges
Conveyance rate (-)
unloading charges
Stacking Charges
Blasting Charges
Average Lead
Initial Rate
Conveyance
Charges
Seigniorage
Loading &
of Material
Charging
Weighted
Charges
Stacking
TOTAL RATE
0
rate
S.No Nature of Metal
Machine Crushing
(-) Stacking Charges
Conveyance rate (-)
unloading charges
Stacking Charges
Blasting Charges
Average Lead
Initial Rate
Conveyance
Charges
Seigniorage
Loading &
of Material
Charging
Weighted
Charges
Stacking
TOTAL RATE
0
rate
S.No Nature of Metal
Machine Crushing
(-) Stacking Charges
Conveyance rate (-)
unloading charges
Stacking Charges
Blasting Charges
Average Lead
Initial Rate
Conveyance
Charges
Seigniorage
Loading &
of Material
Charging
Weighted
Charges
Stacking
TOTAL RATE
0
rate
S.No Nature of Metal
2 Sand for Mortar 31.00 359.30 0.00 68.40 606.00 359.30 606.00 -- -- 0.00 0.0 0.00 965.30
3 Sand for Concrete 31.00 359.30 0.00 68.40 462.00 359.30 462.00 -- -- 0.00 0.0 0.00 821.30
4 Sand for Filling 31.00 359.30 0.00 68.40 342.00 359.30 342.00 -- -- 0.00 0.0 0.00 701.30
(F ) Seigniorage charges
10.00 Lm TOTAL Cost for 10 Lm = (A+B+C+D+E+F) 33070.97
3307.10
Rate per 1 Lm 3307.00
Name of the Work:: "Widening of existing Single lane /Intermediate
lane to Double lane for the road (1)
pwd(Chandrampet) road to Marrimadla (via)
Konaraopet Mandal. Km.0/0 to 27/5 , (2)
Vemulawada -Sirikonda road from km.28/0 to
32/6" that
Certified in karimnagar district
I have inspected the above road personally on
……………. …… ……. and the provisions made in the estimate are essential
and adequate.
Superintending Engineer,
(R&B) Circle, ____________
Name of the Work:: "Widening of existing Single lane /Intermediate lane to
Double lane for the road (1) pwd(Chandrampet) road to
Marrimadla (via) Konaraopet Mandal. Km.0/0 to 27/5 , (2)
Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
1) Certified that the Leads provided in the lead statement are the shortest.
2) Certified that the Distances noted herein are correct.
3) Certified that the quarries are nearest and are having sufficient yield.
4) Certified that the routs shown are nearest.
5) Certified that the description of the variety of materials noted are correct to the
best of my knowledge.
6) Certified that the Land available for the road formation is sufficient and no land
acquisition is required
7) Certified that the Hard Blasted Trap is obtained by Blasting, Hence Blasting
charges are allowed on Trap metal.
8) Certified that the reach in the Estimate is not proposed in any other schemes.
9) Certified that the side earth is not available for formation, hence Barrowed soils
with 1000 m lead is provided in the estimate.
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
BILL 01 : SITE CLEARANCE AND DISMANTLING
1.01
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto
300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150
mm in thickness as per Technical Specification Clause 201 MoRT&H.
2.04 Removal of unserviceable soils up to SDR including excavation, loading and disposal up to 1000 m etc., complete
including (excluding seigniorage) charges for finished item of work as per MoRT&H specification 301(5th Revision) and
as directed by the Engineer-in-Charge
8420.00 65.40 550668
2.02 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material with all
leads and lifts up to 1000 m as per MoRT&H (5th Revision) Specn. No.305.4.3
from KM.0/0-0/8,1/2-4/2,5/2-6/6,7/0-
27/5,28/0-30/4,31/4-32/25,32/450-
101010 7.50 757575
32/6 (deducting retained structure
length 240m & ECC road length)
2.03
Road Way excavation by mechanical means up to SDR and utilising the exavated earth for embankment including pre-
watering of soil , removal of top soil, excavation of soils , depositing the soils on the embankment, spreading soil, breaking
clods, sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of
table 300-2 of MoRT&H, including all hire and operational charges of T&P and (excluding seigniorage) charges, complete
for finished item of work as per MoRT&H specification 305 (5th revision) (Payment will be made based on levels for
finished item of work).
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
2.05 Construction sub Grade withroad way excavated useful earth by mechanical means upto SDR with all leads and lifts
including pre-watering of soil, removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the
soil on the embankment, spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes
Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges
of T&P and excluding seigniorage charges, complete for finished item of work as per MoRT&H specification 305 (5th
Revision)
as per qty sheet CP&VS Road Cum 2.00 28860.00 91557+11839 103396.00
103396
from KM.0/0-0/8,1/2-4/2,5/2-6/6,7/0-
27/5,28/0-30/4,31/4-32/25,32/450-
Cum 2.00 28860.00 1.85 0.20 21356.40
32/6 (deducting retained structure
length 240m & ECC road length)
38101.40
Total 38102 1662.00 63325524
3.02 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macadem specification
including cost of all materials and including premixing the material with water at OMC in Mechanical mix plant carriage of
mixed material by tipper to site , laying in uniform layers with Hydrostatic Sensor paver in base courses on well
prepared surface and compacting with Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-
Charge and as per MoRT&H specification.406 (5th revision) for finished item of work. (Payment will be made based on
level for finished item of work).
from KM.0/0-0/8,1/2-4/2,5/2-6/6,7/0-
27/5,28/0-30/4,31/4-32/25,32/450-
2.00 28860.00 1.85 0.25 26695.50
32/6 (deducting retained structure
length 240m & ECC road length)
52396.50
Total 52397 1909.00 100025873
Sub Total 163351397
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
BILL.NO:4 BITUMINOUS COURSE ( FLEXIBLE PAVEMENT )
4.01 Providing and applying Prime Coat with bitumen emulsion (Slow Setting - I) bulk using emulsion pressure distributor on
prepared surface of Granular base including cleaning of road surface and spraying emulsion at the rate of 0.70 Kg/sqm
using emulsion pressure distributor for finished item of work etc., complete for finished item of work as per MoRT&H
Specification 502 (5th Revision) and as directed by the Engineer-in-charge.
from KM.0/0-0/8,1/2-4/2,5/2-6/6,7/0-
27/5,28/0-30/4,31/4-32/25,32/450-
Sqm 1.00 28860 7.00 0.030 6060.60
32/6 (deducting retained structure
length 240m & ECC road length)
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
6.02 Supplying of hot applied thermoplastic road marking compound, 2.5mm thick including reflectorising glass beads @
250gms with Reflectorising Glass Beads on Bituminous Surface at 250 gms per sqm area, thickness of 2.5mm is exclusive of
surface applied glass bead as per IRC: 35, the material should be of BERGER Company/ BERGER Equivalent/ Equivalent
brand and must comply with the following: a) White index for the product should be in the range of 60-70 when measured
against standard reference. The applied panel 7/8 number must be submitted for checking up the white index in the
department lab. In case the department approves the white index of any vendor, the department engineer may carryout
random checking of the applied products at site against the approved panel. In case of any major deviation, beyond
acceptance limit, department reserve the right to cancel or reject the total supplied consignment of the said material and
will compell the vendor has to replace the full consignment by the desired material as per approved panel at his own cost
and additional demurrages may be claimed due to loss of man days (as per the rules of the department). b) Luminance factor
of the material should be in the range of 80-85% at 45 degree centigrade as per AASTHOM 249. c) Crack resistance: The
applied panel cured for 7 days under ambient condition and then should be tested as per BS3262, Part-1, 1989 and should
pass at the range of '0' degree centigrade to '-10' degree centigrade D) Adhesion : Strong E) Softening point: 102 degree
centigrade F) Dried film finish : Smooth and uniform G) Night Vision: High as directed by the Engineer-in-Charge and
confirming to IS: 164-1961 (1st revision reaffirmed in 1986) and clause conforming to IRC 35-1997
6.03 Providing and fixing Village name board size 900x450 mm made out of Type – IV of ASTMD 4956-09 High Intensity
Prismatic Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of Green Colour & White
Letters and fixed over 3MM Alluminium Composite Material sheet having minimum 0.30 mm thick Aluminium skin on
both sides with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and
fixing with 35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from
the ground level to the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of
synthetic enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS
base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and
conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading charges necessary for
satisfactory completion of the work as directed by Engineer -in-Charge.
Providing and fixing Mandatory / Regulatory sign boards size 600 mm equilateral Triangle made out of Type – IV of
ASTMD 4956-09 High Intensity Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of
White colour and letters/logos done by screen printing in Black colour, boarders by screen printing in Red colour and fixed
over 3MM Alluminium Composite Material ( ACM ) sheet having minimum 0.30 mm thick Aluminium skin on both sides
with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with
35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground
level the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic
enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle
35x35x4 mm in to the ground by M15 Concrete foundation of size 450x450x600mm including cost and conveyance of all
materials ,equipment, machinery and labour with all leads and lift, loading changes necessary for satisfactory completion of
the work as directed by Engineer -in-Charge.
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
6.04 Providing and fixing Mandatory / Regulatory sign boards size 600 mm circle made out of Type – IVof ASTMD 4956-09
High Intensity Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of White colour and
letters/logos done by screen printing in Black colour, boarders by screen printing in Red colour and fixed over 3MM
Alluminium Composite Material sheet having minimum 0.30 mm thick Aluminium skin on both sides with back side
painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and
mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the
bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint
Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4 mm
in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and conveyance of all materials
,equipment, machinery and labour with all leads and lift, loading charges necessary for satisfactory completion of the work
as directed by Engineer -in-Charge.
Providing and fixing Village name board size 450x750 mm made out of Type – IV of ASTMD 4956-09 High Intensity
Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of Green Colour & White Letters
and fixed over 3MM Alluminium Composite Material sheet having minimum 0.30 mm thick Aluminium skin on both sides
with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with
35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground
level to the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic
enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle
35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and conveyance of all
materials equipment, machinery and labour with all leads and lift, loading charges necessary for satisfactory completion of
the work as directed by Engineer –in-Charge
Cum 122.62
Cum 123 27.00 3321
7.02
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H (50% natuaral sand & 50% sand dust) including cost, (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including
all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for levelling course
Cum 11.87
Cum 12 4268.00 51216
7.03 Vibrated cement concrete M 25 Grade Concrete using 20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) (50% natural sand & 50% stone dust)
including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,centering, machine
mixing, laying in position, Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th Revision) for footings and Raft
foundation in Substructure .
Cum 78.24
Package III CPC pvt Ltd
Detailed Estimate
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
79 6165.00 487035
7.04 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2)(50% natural sand & 50% stone dust) including
cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2300 (5th revision ) and as directed by the Engineer-in-Charge for
Superstructure
Cum 18.96
19 7079.00 134501
7.05 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods,
tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges
and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished
item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification
1600 & 2200, 2300 (5th revision) and as per I.S.1786 of 1985 for Super structure of R.C.C items.
MT 11.00
11 53253.00 585783
7.06 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG metal satisfying the
requirements laid down in clause 2504.2.2 of MoRT&H specifications to a thickness of not less than 600mm with smaller
size towards the soil and bigger size towards the wall and provided over the entire surface behind the abutment, wing wall
and return wall to the full height compacted to a firm condition including cost and conveyance of all metal (excluding
seigniorage) charges ,and all labour charges as directed by the departmental officers as per drawing and Technical
specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
Cum 42.24
43 1215.00 52245.00
7.07 Providing and laying filter material with Gravel underneath pitching in slopes including cost, (excluding seigniorage)
charges and conveyance of materials to site including labour charges etc., complete for finished item of work as per
MoRT&H Specification 2504 (5th Revision) and as directed by the Engineer-in-Charge
Cum 11.76
12 678.00 8136.00
7.08 Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm size including cost, (excluding
seigniorage) charges and conveyance of materials to site and including labour charges for packing the stones for revetment
etc., complete for finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-
in-Charge for Pitching of slopes
Cum 23.52
24 1044.00 25056
7.09
Providing and laying Boulder's apron on River Bed for protection against scour with stone boulders weighing not less than
40 k.g each complete as per drawing and technical specification 300 mm thick with HBG stone of not less than 300 mm size
including cost, (excluding seigniorage) charges and conveyance of materials to site and including labour charges for
packing the stones for apron etc., complete for finished item of work as per MoRT&H specification 2503 ( 5th revision ) and
as directed by the Engineer-in-Charge for Bed Protection.
Cum 4.77
5 1044.00 5220.00
7.10 Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe extending through the
full width of the structure at 1.00m C/C in both horizontal and vertical direction so that the weep holes in each horizontal
direction is staggered from the weep holes laying above and below lines as shown in drawing including cost and
conveyance of the A.C pipes and labour charges for cutting to required length, placing the pipe with a slope of about 1V :
20H towards stream side face etc., complete for finished item of work for weep holes as per MoRT&H specification 2706 &
2200 (5th Revision)
54.00
Package III CPC pvt Ltd
Detailed Estimate
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
RM 54 71.60 3866.4
7.11 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including
all other incidental and operational charges of all T&P etc., complete for finished item of work as per drawing BD/1-69( A)
but including cost of steel and its fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2702 (5th
Revision) and as directed by the Engineer-in-Charge for Wearing coat over Deck slab.
Cum 6.30
7 4268.00 29876
7.13
Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) (50% natural sand &50% stone dust) including
cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing including cost of steel and its fabrication charges as per MoRT&H specification 1500,
1600,1700, & 2704 (5th Revision) and as directed by the Engineer-in-Charge for Approach slab.
Cum 19.74
20 6047.00 120940
7.14 Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as
per dimensions in the approved drawing and at locations directed by the Engineer, all as specified 809 MORTH
Rm 9.48
10 3307.00 33070
Total 1564373
8 BILL NO.8: HUME PIPE CULVERT
Reconstruction: 52Nos + 23Nos Widening = 75No's
8.01 Earthwork excavation in soils up to SDR by mechanical means for foundations of structures as per drawing and technical
specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
dressing sides of bottom, back filling the excavation earth to the extent required etc., complete including (excluding
seigniorage) charges for finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge
3022.00
Cum 3022 27.00 81594
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
8.02 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H including cost,(50% natural sand & 50% stone dust) (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including
all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for foundations.
440.00
Cum 440 4268.00 1877920
8.03 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) (50% natural sand & 50% stone dust)
including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges , centering, machine
mixing, laying in position, Compacting, Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision) for Sub structure .
2002.00
Cum 2002 5907.00 11825814
8.04
Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia., NP-4 class for pipe culverts including cost and
conveyance of Pipes etc.,(50% natural sand & 50% stone dust) complete and Labour charges for laying, jointing of 1000mm
dia. R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per
MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the
Engineer-in-Charge for finished item of work.
654.75
Cum 655 481.50 315383
8.06
Providing and laying Boulder's apron on River Bed for protection against scour with stone boulders weighing not less than
40 k.g each complete as per drawing and technical specification 300 mm thick with HBG stone of not less than 300 mm size
including cost, (excluding seigniorage) charges and conveyance of materials to site and including labour charges for
packing the stones for apron etc., complete for finished item of work as per MoRT&H specification 2503 ( 5th revision ) and
as directed by the Engineer-in-Charge for Bed Protection.
607.50
Cum 608 1044.00 634752
8.07
Providing and laying filter material with Gravel underneath pitching in slopes including cost, (excluding seigniorage)
charges and conveyance of materials to site including labour charges etc., complete for finished item of work as per
MoRT&H Specification 2504 (5th Revision) and as directed by the Engineer-in-Charge
51.68
Cum 52 678.00 35256
8.08
Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm size including cost, (excluding
seigniorage) charges and conveyance of materials to site and including labour charges for packing the stones for revetment
etc., complete for finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-
in-Charge for Pitching of slopes
103.35
Cum 104 1044.00 108576
Total 27050769
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
1103.58
Cum 1104 27.00 29808
9.2
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine aggregate
conforming to table 1000-2 of MoRT&H including cost,(50% natural sand & 50% stone dust) (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including
all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for foundations.
61.34
Cum 62 4268.00 264616
9.3
Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) (50% natural sand & 50% stone dust)
including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges , centering, machine
mixing, laying in position, Compacting, Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision) for Sub structure .
1032.15
Cum 1033 5907.00 6101931
9.4
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2)(50% natural sand & 50% stone dust) including
cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2300 (5th revision ) and as directed by the Engineer-in-Charge for
Superstructure
128.96
Cum 129 7079.00 913191
9.5
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost and
conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods,
tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges
and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished
item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification
1600 & 2200, 2300 (5th revision) and as per I.S.1786 of 1985 for Super structure of R.C.C items.
10.32
MT 11 53253.00 585783
9.6
Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG metal satisfying the
requirements laid down in clause 2504.2.2 of MoRT&H specifications to a thickness of not less than 600mm with smaller
size towards the soil and bigger size towards the wall and provided over the entire surface behind the abutment, wing wall
and return wall to the full height compacted to a firm condition including cost and conveyance of all metal (excluding
seigniorage) charges ,and all labour charges as directed by the departmental officers as per drawing and Technical
specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
111.132
Package III CPC pvt Ltd
Detailed Estimate
"Widening of existing Single lane /Intermediate lane to Double lane for the
road (1) pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal.
Name of Work :
Km.0/0 to 27/5 , (2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in
karimnagar district
Length In
32100
m
DETAILED COST ESTIMATE
S NO DESCRIPTION UNIT NO LENGTH WIDTHDEPTH QTY RATE AMOUNT
Cum 112 1215.00 136080
9.7
Providing and laying filter material with Gravel underneath pitching in slopes including cost, (excluding seigniorage)
charges and conveyance of materials to site including labour charges etc., complete for finished item of work as per
MoRT&H Specification 2504 (5th Revision) and as directed by the Engineer-in-Charge
110.18
Cum 111 678.00 75258
9.8
Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm size including cost, (excluding
seigniorage) charges and conveyance of materials to site and including labour charges for packing the stones for revetment
etc., complete for finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-
in-Charge for Pitching of slopes
265.33
Cum 266 1044.00 277704
9.9
Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe extending through the
full width of the structure at 1.00m C/C in both horizontal and vertical direction so that the weep holes in each horizontal
direction is staggered from the weep holes laying above and below lines as shown in drawing including cost and
conveyance of the A.C pipes and labour charges for cutting to required length, placing the pipe with a slope of about 1V :
20H towards stream side face etc., complete for finished item of work for weep holes as per MoRT&H specification 2706 &
2200 (5th Revision)
MAINTENANCE
Part-I (B) Routine MAINTENANCE WORK within the Defects liability period i.e. 2 Years
Routine Maintenance for Jungle Clearance /tree and shrub trimming and culvert repairs / vents
maintenance / parapet wall repairs / retaining wall repairs etc within DLP i.e., 2 years.
28.86 Km for Double Lane DL 2 28.86 3600 207792
per Km per
years Kms
Year
Part-I (C) Routine MAINTENANCE WORK after completion of DLP for 3 years
Routine Maintenance comprising of B.T. Pot Hole filling, BT edge repairs (and other items on B.T.
carriageway such as crack sealing, minor surface repair etc., and unpaved shoulder repair (Berms)/Surface
drains maintenance/ including gravelling berms and jungle clearance/tree and shrub trimming and culvert
repairs/Vent maintenance/parapet wall repairs / retaining wall repairs etc., Ordinary repairs to bridges and
sign maintenance/guard stones maintenance / painting Km/Hm stones and others for 3 years from the end
of DLP.
The data for the Routine Maintenance items to be covered will be prepared with SSR with which the
PLAN work estimate is sanctioned and the items of Rouine Maintenance will be carried out at these rates
duly operating the quoted percentage. Payment shall be made for the items to be recorded in M. book. The
overall amount shall be for Routine Maintenance for 3 years after DLP and for Routine Maintenance of
culverts and jungle clearance for 2 years after completion of PM work shall be limited maximum to
amounts indicated at Part I(B) and Part I(C)
DESIGN SYNOPSIS
SITE Clearing and grubbing road land including uprooting wild vegetation, grass
CLEARAN bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps
such trees cut earlier and disposal of unserviceable materials and stacking o
CE serviceable material to be used or auctioned, upto a lead of 1000 m includin
removal and disposal of top organic soil not exceeding 150 mm in thickness
complete
Page.No.2by mechanical as per Technical Specification Clause 201 MoRT&
2 of
Sr No MORT&H
2.1 Unit =
Hectare
Taking
output =
1 Hectare
(i) By
Manual
Means:-
A In area of
light
jungle
a)
Labour
Mate day 0.160 0.00
Mazd day 4.000 0.00
oor
b)
Machiner
y
c) (10-VAT) 5.000
Overhead
charges
@ on
(a+b)
d)
Contract
or's profit
@ on
(a+b+c)
Rate per
Hectare =
a+b+c+d
2.1 say
b) Machinery
Tractor-trolley hour 0.300 422.00 126.60
b) Machinery
Tractor-trolley hour 0.400 422.00 168.80
b) Machinery
Tractor-trolley hour 0.600 422.00 253.20
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 345.00 690.00
Mazdoor day 50.000 295.00 14750.00
b) Overhead charges @ on (a) 5.000 772.00
c) Contractor's profit @ on (a+b) 10.000 1621.20
Rate per Hectare = a+b+c 17833.20
say 17833.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not
exceeding 150 mm in thickness as per Technical Specification Clause 201 MoRT&H.
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 345.00 2070.00
Mazdoor day 150.000 295.00 44250.00
b) Machinery
Tractor-trolley hour 1.000 422.00 422.00
a) Labour
Mate day 8.000 300.00 2400.00
Mazdoor day 200.000 200.00 40000.00
b) Machinery
Tractor-trolley hour 2.000 200.00 400.00
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10
and below
a) Labour
Mate day 0.040 300.00 12.00
Mazdoor for dismantling and loading day 1.000 200.00 200.00
b) Machinery
Tractor-trolley hour 0.270 300.00 81.00
a) Labour
Mate day 0.050 300.00 15.00
Mazdoor for dismantling and loading day 1.250 200.00 250.00
b) Machinery
Tractor-trolley hour 0.270 300.00 81.00
a) Labour
Mate day 0.020 300.00 6.00
Mazdoor for dismantling, loading and day 0.500 200.00 100.00
unloading
b) Machinery
Tractor-trolley hour 0.270 300.00 81.00
a) Labour
Mate day 0.060 300.00 18.00
Carpenter day 0.500 350.00 175.00
Mazdoor for dismantling, loading and day 1.000 200.00 200.00
unloading.
b) Machinery
Tractor-trolley hour 0.270 300.00 81.00
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 300.00 42.00
Blacksmith day 1.000 300.00 300.00
Mazdoor for dismantling, loading and day 2.500 200.00 500.00
unloading
Add 2.5 per cent of cost of labour for gas cutting, 21.05
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 300.00 51.00
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 300.00 6.00
Mazdoor day 0.520 200.00 104.00
b) Overhead charges @ on (a) 11.00
c) Contractor's profit @ on (a+b) 12.10
Rate per metre = a+b+c 133.10
say 133.00
2.4 B Above 600 mm to 900 mm dia
(ix)
a) Labour
Mate day 0.030 300.00 9.00
Mazdoor day 0.700 200.00 140.00
b) Overhead charges @ on (a) 14.90
c) Contractor's profit @ on (a+b) 16.39
Rate per metre = a+b+c 180.29
say 180.00
2.4 C Above 900 mm
(ix)
a) Labour
Mate day 0.050 300.00 15.00
Mazdoor day 1.200 200.00 240.00
b) Overhead charges @ on (a) 25.50
c) Contractor's profit @ on (a+b) 28.05
Rate per metre = a+b+c 308.55
say 309.00
Note 1. The excavation of earth, dismantling of stone
masonry work in head walls and protection works is
not included which is to be measured and paid
separately.
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 300.00 18.00
Mazdoor for dismantling, loading and day 1.500 200.00 300.00
unloading
b) Machinery
Tractor-trolley hour 0.380 300.00 114.00
Farm tractor with ripper @ 60 cum per hour hour 0.017 350.00 5.95
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 300.00 9.00
Semi skilled mazdoor for operating pneumatic day 0.500 250.00 125.00
tools
Mazdoors as helpers including loading and day 0.500 200.00 100.00
unloading
b) Machinery
Air compressor 250 cfm with two leads for hour 1.000 250.00 250.00
pneumatic cutters/ hammers @ 1 cum per hour
Joint Cutting Machine with 2-3 blades hour 1.000 500.00 500.00
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 300.00 39.00
Mazdoor day 0.750 200.00 150.00
b) Machinery
Tractor-trolley hour 0.150 300.00 45.00
say 165.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 300.00 1.20
Mazdoor day 0.100 200.00 20.00
b) Machinery
Tractor-trolley hour 0.020 300.00 6.00
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 300.00 144.00
Mazdoor day 10.000 200.00 2000.00
Electrician/Lineman day 2.000 300.00 600.00
b) Machinery
Tractor-trolley hour 1.500 300.00 450.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-014
P&M-053
L-12
L-13
P&M-014
P&M-053
comprising of masonry,
, sorting the dismantled
and lead of 1000 metres
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-02
L-13
P&M-053
L-12
L-13
L-14
P&M-001
P&M-053
L-12
L-14
L-02
L-13
P&M-001
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-04
L-13
P&M-053
L-12
L-02
L-13
P&M-053
L-12
L-13
L-02
P&M-053
L-12
L-02
L-13
L-12
L-13
L-12
L-13
L-12
L-13
L-12
L-13
L-12
L-13
P&M-053
L-12
L-13
L-12
L-13
L-12
L-13
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
P&M-055
L-12
L-14
L-13
P&M-001
P&M-053
P&M-083
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
P&M-053
L-12
L-13
L-02
P&M-053
L-12
L-13
L-02
P&M-057
P&M-013
L-12
L-13
P&M-070
P&M-057
L-12
L-13
L-02
P&M-053
RATE ANALYSIS
TRAFFIC SIGNS, MARKINGS AND ROAD APPURTENANCES
Remark
Description Unit Quantity Rate Rs Cost Rs s/ Input
ref.
Kilometre Stone
Reinforced cement concrete M15grade kilometre stone
of standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
Item
a) M-15 grade of concrete cum 2.350 5353.00 12579.55 7.05 (A)
Item
13.6 /
b) Steel reinforcement @ 5 kg per sqm kg 22.080 53.25 1175.83
1000
Item
No. 3.13
c) Excavation in soil for foundation cum 1.680 27.00 45.36
Item 8.8
d) Painting two coats on concrete surface sqm 9.850 71.90 708.22
Remark
Description Unit Quantity Rate Rs Cost Rs s/ Input
ref.
Remark
Description Unit Quantity Rate Rs Cost Rs s/ Input
ref.
Item
13.6 /
b) Steel reinforcement @ 5 kg per sqm kg 66.000 53.25 3514.70
1000
Item
No. 3.13
c) Excavation in soil for foundation cum 1.390 27.00 37.53
DETAILS
2014-15
GRAVEL
MSAND
DETAILS RATE
CSAND
MASONI 385.00 FSAND
MASONII 345.00 CRS
Mate 345.00 ROUGH
Mazdoor skilled 357.00 BOND600
Mazdoor unskilled 295.00 SS150
SS225
SS300
QS25
QS40
ADDITIONS
OH 5.00
OH1 5.00
CP 10.00
VAT 5.00
LALI 13.00
IS:458-1988
Dia of Pipes Shell Quantity of
Outer Dia
S.No NP3 class Thick ness Concrete
(mm)
( mm ) (mm) ( cum )
1 2 3 4 5
1 600 85 770 0.1829
2 800 95 990 0.2671
3 1000 115 1230 0.4028
4 1200 120 1440 0.4976
MACHINERY
AT PLANT
Dozer 80 HP for spreading @
Motor Graders for Grading
Trac
Air C
Wet mix plant of 60
Mechanical broom @
Bitumen pressure distrib
Emulsion pressure distributor
Hot M
Hot M
Hot
Hot Mix P
Sensor Paver f
Mechanical Paver f
Smooth wheeled roller 8-10 Tones for initial b
Vibratory roller 8 Tones for
Pne
Hire charges of bitume
Electric gen
Ge
IS:458-2003
1 2 3 4 5
1 600 85 770 0.1829
2 800 95 990 0.2671
3 1000 115 1230 0.4028
4 1200 120 1440 0.4976
5 900 100 1100 0.3142
HER MATERIALS SS5 HBG METAL IRC HBG METAL
2014-15
204-15 (Excluding blasting 2014-15
Charges)
RATE SIZES RATE SIZES RATE
2014-15 2014-15
2014-15
Cement
Cement Content
Content rate
( kg)
( kg/ cum) DETAILS First 5 km Next 1 km
RATE
Lead Lead
6 7
360 65.844 600 mm 2099.00 89.000 4.13
360 96.156 800 mm 3447.00 119.000 4.80
360 145.008 1000 mm 5379.00 188.000 9.05
360 179.136 1200 mm 7477.00 228.000 9.85
2014-15
Cement
Cement Content
Content rate
( kg)
( kg/ cum)
DETAILS
First 5 km Next 1 km
RATE
Lead Lead
6 7
360 65.844 600 mm 2490.00 89.000 4.13
360 96.156 800 mm 4361.00 119.000 4.80
360 145.008 1000 mm 7428.00 188.000 9.05
360 179.136 1200 mm 10068.00 228.000 9.85
360 113.112 900 mm 5433.00 156 9.05
BUILDINGS SSR-2014-15
MASTIC PADS
25.4 mm 991.00 BMS-W.20
PAINTS 240.00
WORKS
RATE
CEMENT & STEEL
BASIC
CURRENT
MATERIAL PRICE
PRICE
FOR PIPES
2008-09
2760.00
2600.00
2250.00
1320.00
575.00
1550.00
1320.00
345.00
345.00
370.00
1320.00
290.00
940.00
690.00
15525.00
1090.00
540.00
1320.00
1035.00
920.00
1550.00
1090.00
920.00 To be Checked
4.50
4.50
40.00
2070.00
1268.00
170.00 Rate as per
local
90.00 competitive
200.00 quotations
65.00
345.00
345.00
345.00
620.00
BASIC
CURRENT
MATERIAL PRICE
PRICE
FOR PIPES
Metal/
21.00 250.61 285.7 Sand
Stone Qry
RIFYING
0.00 0 0.00 0.00
From
SSR 1 MT1 30.40 30.40 1
2 MT2 42.60 42.60 2
3 MT3 58.90 58.90 3
4 MT4 71.50 71.50 4
5 MT5 84.10 84.10 5
6 MT6 96.70 12.60 6-30 6
7 MT7 109.30 10.50 >30 7
8 MT8 121.90 162.00 8
9 MT9 134.50 168.00 9
10 MT10 147.10 174.00 10
11 MT11 159.70 180.00 11
12 MT12 172.30 186.00 12
13 MT13 184.90 192.00 13
14 MT14 197.50 198.00 14
15 MT15 210.10 204.00 15
16 MT16 222.70 210.00 16
17 MT17 235.30 216.00 17
18 MT18 247.90 222.00 18
19 MT19 260.50 228.00 19
20 MT20 273.10 234.00 20
21 MT21 285.70 5.7500 21
22 MT22 298.30 5.5000 22
23 MT23 310.90 5.0000 23
24 MT24 323.50 4.7500 24
25 MT25 336.10 4.5000 25
26 MT26 348.70 26
27 MT27 361.30 27
28 MT28 373.90 28
29 MT29 386.50 29
30 MT30 399.10 30
31 MT31 409.60 31
32 MT32 420.10 32
33 MT33 430.60 33
34 MT34 441.10 34
35 MT35 451.60 35
36 MT36 462.10 36
37 MT37 472.60 37
38 MT38 483.10 38
39 MT39 493.60 39
40 MT40 504.10 40
41 MT41 514.60 41
42 MT42 525.10 42
43 MT43 535.60 43
44 MT44 546.10 44
45 MT45 556.60 45
46 MT46 567.10 46
47 MT47 577.60 47
48 MT48 588.10 48
49 MT49 598.60 49
50 MT50 609.10 50
51 MT51 619.60 51
52 MT52 630.10 52
53 MT53 640.60 53
54 MT54 651.10 54
55 MT55 661.60 55
56 MT56 672.10 56
57 MT57 682.60 57
58 MT58 693.10 58
59 MT59 703.60 59
60 MT60 714.10 60
61 MT61 724.60 61
62 MT62 735.10 62
63 MT63 745.60 63
64 MT64 756.10 64
65 MT65 766.60 65
66 MT66 777.10 66
67 MT67 787.60 67
68 MT68 798.10 68
69 MT69 808.60 69
70 MT70 819.10 70
71 MT71 829.60 71
72 MT72 840.10 72
73 MT73 850.60 73
74 MT74 861.10 74
75 MT75 871.60 75
76 MT76 882.10 76
77 MT77 892.60 77
78 MT78 903.10 78
79 MT79 913.60 79
80 MT80 924.10 80
81 MT81 934.60 81
82 MT82 945.10 82
83 MT83 955.60 83
84 MT84 966.10 84
85 MT85 976.60 85
86 MT86 987.10 86
87 MT87 997.60 87
88 MT88 1008.10 88
89 MT89 1018.60 89
90 MT90 1029.10 90
91 MT91 1039.60 91
92 MT92 1050.10 92
93 MT93 1060.60 93
94 MT94 1071.10 94
95 MT95 1081.60 95
96 MT96 1092.10 96
97 MT97 1102.60 97
98 MT98 1113.10 98
99 MT99 1123.60 99
100 MT100 1134.10 100
101 MT101 1144.60 101
102 MT102 1155.10 102
103 MT103 1165.60 103
104 MT104 1176.10 104
105 MT105 1186.60 105
106 MT106 1197.10 106
107 MT107 1207.60 107
108 MT108 1218.10 108
109 MT109 1228.60 109
110 MT110 1239.10 110
111 MT111 1249.60 111
112 MT112 1260.10 112
113 MT113 1270.60 113
114 MT114 1281.10 114
115 MT115 1291.60 115
116 MT116 1302.10 116
117 MT117 1312.60 117
118 MT118 1323.10 118
119 MT119 1333.60 119
120 MT120 1344.10 120
121 MT121 1354.60 121
122 MT122 1365.10 122
123 MT123 1375.60 123
124 MT124 1386.10 124
125 MT125 1396.60 125
126 MT126 1407.10 126
127 MT127 1417.60 127
128 MT128 1428.10 128
129 MT129 1438.60 129
130 MT130 1449.10 130
131 MT131 1459.60 131
132 MT132 1470.10 132
133 MT133 1480.60 133
134 MT134 1491.10 134
135 MT135 1501.60 135
136 MT136 1512.10 136
137 MT137 1522.60 137
138 MT138 1533.10 138
139 MT139 1543.60 139
140 MT140 1554.10 140
141 MT141 1564.60 141
142 MT142 1575.10 142
143 MT143 1585.60 143
144 MT144 1596.10 144
145 MT145 1606.60 145
146 MT146 1617.10 146
147 MT147 1627.60 147
148 MT148 1638.10 148
149 MT149 1648.60 149
150 MT150 1659.10 150
151 MT151 1669.60 151
152 MT152 1680.10 152
153 MT153 1690.60 153
154 MT154 1701.10 154
155 MT155 1711.60 155
156 MT156 1722.10 156
157 MT157 1732.60 157
158 MT158 1743.10 158
159 MT159 1753.60 159
160 MT160 1764.10 160
161 MT161 1774.60 161
162 MT162 1785.10 162
163 MT163 1795.60 163
164 MT164 1806.10 164
165 MT165 1816.60 165
166 MT166 1827.10 166
167 MT167 1837.60 167
168 MT168 1848.10 168
169 MT169 1858.60 169
170 MT170 1869.10 170
171 MT171 1879.60 171
172 MT172 1890.10 172
173 MT173 1900.60 173
174 MT174 1911.10 174
175 MT175 1921.60 175
176 MT176 1932.10 176
177 MT177 1942.60 177
178 MT178 1953.10 178
179 MT179 1963.60 179
180 MT180 1974.10 180
181 MT181 1984.60 181
182 MT182 1995.10 182
183 MT183 2005.60 183
184 MT184 2016.10 184
185 MT185 2026.60 185
186 MT186 2037.10 186
187 MT187 2047.60 187
188 MT188 2058.10 188
189 MT189 2068.60 189
190 MT190 2079.10 190
191 MT191 2089.60 191
192 MT192 2100.10 192
193 MT193 2110.60 193
194 MT194 2121.10 194
195 MT195 2131.60 195
196 MT196 2142.10 196
197 MT197 2152.60 197
198 MT198 2163.10 198
199 MT199 2173.60 199
200 MT200 2184.10 200
201 MT201 2194.60 201
202 MT202 2205.10 202
203 MT203 2215.60 203
204 MT204 2226.10 204
205 MT205 2236.60 205
206 MT206 2247.10 206
207 MT207 2257.60 207
208 MT208 2268.10 208
209 MT209 2278.60 209
210 MT210 2289.10 210
211 MT211 2299.60 211
212 MT212 2310.10 212
213 MT213 2320.60 213
214 MT214 2331.10 214
215 MT215 2341.60 215
216 MT216 2352.10 216
217 MT217 2362.60 217
218 MT218 2373.10 218
219 MT219 2383.60 219
220 MT220 2394.10 220
221 MT221 2404.60 221
222 MT222 2415.10 222
223 MT223 2425.60 223
224 MT224 2436.10 224
225 MT225 2446.60 225
226 MT226 2457.10 226
227 MT227 2467.60 227
228 MT228 2478.10 228
229 MT229 2488.60 229
230 MT230 2499.10 230
231 MT231 2509.60 231
232 MT232 2520.10 232
233 MT233 2530.60 233
234 MT234 2541.10 234
235 MT235 2551.60 235
236 MT236 2562.10 236
237 MT237 2572.60 237
238 MT238 2583.10 238
239 MT239 2593.60 239
240 MT240 2604.10 240
241 MT241 2614.60 241
242 MT242 2625.10 242
243 MT243 2635.60 243
244 MT244 2646.10 244
245 MT245 2656.60 245
246 MT246 2667.10 246
247 MT247 2677.60 247
248 MT248 2688.10 248
249 MT249 2698.60 249
250 MT250 2709.10 250
251 MT251 2719.60 251
252 MT252 2730.10 252
253 MT253 2740.60 253
254 MT254 2751.10 254
255 MT255 2761.60 255
256 MT256 2772.10 256
257 MT257 2782.60 257
258 MT258 2793.10 258
259 MT259 2803.60 259
260 MT260 2814.10 260
261 MT261 2824.60 261
262 MT262 2835.10 262
263 MT263 2845.60 263
264 MT264 2856.10 264
265 MT265 2866.60 265
266 MT266 2877.10 266
267 MT267 2887.60 267
268 MT268 2898.10 268
269 MT269 2908.60 269
270 MT270 2919.10 270
271 MT271 2929.60 271
272 MT272 2940.10 272
273 MT273 2950.60 273
274 MT274 2961.10 274
275 MT275 2971.60 275
276 MT276 2982.10 276
277 MT277 2992.60 277
278 MT278 3003.10 278
279 MT279 3013.60 279
280 MT280 3024.10 280
281 MT281 3034.60 281
282 MT282 3045.10 282
283 MT283 3055.60 283
284 MT284 3066.10 284
285 MT285 3076.60 285
286 MT286 3087.10 286
287 MT287 3097.60 287
288 MT288 3108.10 288
289 MT289 3118.60 289
290 MT290 3129.10 290
291 MT291 3139.60 291
292 MT292 3150.10 292
293 MT293 3160.60 293
294 MT294 3171.10 294
295 MT295 3181.60 295
296 MT296 3192.10 296
297 MT297 3202.60 297
298 MT298 3213.10 298
299 MT299 3223.60 299
300 MT300 3234.10 300
301 MT301 3244.60 301
302 MT302 3255.10 302
303 MT303 3265.60 303
304 MT304 3276.10 304
305 MT305 3286.60 305
306 MT306 3297.10 306
307 MT307 3307.60 307
308 MT308 3318.10 308
309 MT309 3328.60 309
310 MT310 3339.10 310
311 MT311 3349.60 311
312 MT312 3360.10 312
313 MT313 3370.60 313
314 MT314 3381.10 314
315 MT315 3391.60 315
316 MT316 3402.10 316
317 MT317 3412.60 317
318 MT318 3423.10 318
319 MT319 3433.60 319
320 MT320 3444.10 320
321 MT321 3454.60 321
322 MT322 3465.10 322
323 MT323 3475.60 323
324 MT324 3486.10 324
325 MT325 3496.60 325
326 MT326 3507.10 326
327 MT327 3517.60 327
328 MT328 3528.10 328
329 MT329 3538.60 329
330 MT330 3549.10 330
331 MT331 3559.60 331
332 MT332 3570.10 332
333 MT333 3580.60 333
334 MT334 3591.10 334
335 MT335 3601.60 335
336 MT336 3612.10 336
337 MT337 3622.60 337
338 MT338 3633.10 338
339 MT339 3643.60 339
340 MT340 3654.10 340
341 MT341 3664.60 341
342 MT342 3675.10 342
343 MT343 3685.60 343
344 MT344 3696.10 344
345 MT345 3706.60 345
346 MT346 3717.10 346
347 MT347 3727.60 347
348 MT348 3738.10 348
349 MT349 3748.60 349
350 MT350 3759.10 350
351 MT351 3769.60 351
352 MT352 3780.10 352
353 MT353 3790.60 353
354 MT354 3801.10 354
355 MT355 3811.60 355
356 MT356 3822.10 356
357 MT357 3832.60 357
358 MT358 3843.10 358
359 MT359 3853.60 359
360 MT360 3864.10 360
361 MT361 3874.60 361
362 MT362 3885.10 362
363 MT363 3895.60 363
364 MT364 3906.10 364
365 MT365 3916.60 365
366 MT366 3927.10 366
367 MT367 3937.60 367
368 MT368 3948.10 368
369 MT369 3958.60 369
370 MT370 3969.10 370
371 MT371 3979.60 371
372 MT372 3990.10 372
373 MT373 4000.60 373
374 MT374 4011.10 374
375 MT375 4021.60 375
376 MT376 4032.10 376
377 MT377 4042.60 377
378 MT378 4053.10 378
379 MT379 4063.60 379
380 MT380 4074.10 380
381 MT381 4084.60 381
382 MT382 4095.10 382
383 MT383 4105.60 383
384 MT384 4116.10 384
385 MT385 4126.60 385
386 MT386 4137.10 386
387 MT387 4147.60 387
388 MT388 4158.10 388
389 MT389 4168.60 389
390 MT390 4179.10 390
391 MT391 4189.60 391
392 MT392 4200.10 392
393 MT393 4210.60 393
394 MT394 4221.10 394
395 MT395 4231.60 395
396 MT396 4242.10 396
397 MT397 4252.60 397
398 MT398 4263.10 398
399 MT399 4273.60 399
400 MT400 4284.10 400
401 MT401 4294.60 401
402 MT402 4305.10 402
403 MT403 4315.60 403
404 MT404 4326.10 404
405 MT405 4336.60 405
406 MT406 4347.10 406
407 MT407 4357.60 407
408 MT408 4368.10 408
409 MT409 4378.60 409
410 MT410 4389.10 410
411 MT411 4399.60 411
412 MT412 4410.10 412
413 MT413 4420.60 413
414 MT414 4431.10 414
415 MT415 4441.60 415
416 MT416 4452.10 416
417 MT417 4462.60 417
418 MT418 4473.10 418
419 MT419 4483.60 419
420 MT420 4494.10 420
421 MT421 4504.60 421
422 MT422 4515.10 422
423 MT423 4525.60 423
424 MT424 4536.10 424
425 MT425 4546.60 425
426 MT426 4557.10 426
427 MT427 4567.60 427
428 MT428 4578.10 428
429 MT429 4588.60 429
430 MT430 4599.10 430
431 MT431 4609.60 431
432 MT432 4620.10 432
433 MT433 4630.60 433
434 MT434 4641.10 434
435 MT435 4651.60 435
436 MT436 4662.10 436
437 MT437 4672.60 437
438 MT438 4683.10 438
439 MT439 4693.60 439
440 MT440 4704.10 440
441 MT441 4714.60 441
442 MT442 4725.10 442
443 MT443 4735.60 443
444 MT444 4746.10 444
445 MT445 4756.60 445
446 MT446 4767.10 446
447 MT447 4777.60 447
448 MT448 4788.10 448
449 MT449 4798.60 449
450 MT450 4809.10 450
451 MT451 4819.60 451
452 MT452 4830.10 452
453 MT453 4840.60 453
454 MT454 4851.10 454
455 MT455 4861.60 455
456 MT456 4872.10 456
457 MT457 4882.60 457
458 MT458 4893.10 458
459 MT459 4903.60 459
460 MT460 4914.10 460
461 MT461 4924.60 461
462 MT462 4935.10 462
463 MT463 4945.60 463
464 MT464 4956.10 464
465 MT465 4966.60 465
466 MT466 4977.10 466
467 MT467 4987.60 467
468 MT468 4998.10 468
469 MT469 5008.60 469
470 MT470 5019.10 470
471 MT471 5029.60 471
472 MT472 5040.10 472
473 MT473 5050.60 473
474 MT474 5061.10 474
475 MT475 5071.60 475
476 MT476 5082.10 476
477 MT477 5092.60 477
478 MT478 5103.10 478
479 MT479 5113.60 479
480 MT480 5124.10 480
481 MT481 5134.60 481
482 MT482 5145.10 482
483 MT483 5155.60 483
484 MT484 5166.10 484
485 MT485 5176.60 485
486 MT486 5187.10 486
487 MT487 5197.60 487
488 MT488 5208.10 488
489 MT489 5218.60 489
490 MT490 5229.10 490
491 MT491 5239.60 491
492 MT492 5250.10 492
493 MT493 5260.60 493
494 MT494 5271.10 494
495 MT495 5281.60 495
496 MT496 5292.10 496
497 MT497 5302.60 497
498 MT498 5313.10 498
499 MT499 5323.60 499
500 MT500 5334.10 500
From To Data
data Entry Entry
3.00 51.67 58.9 METAL L
SD54 651.10 58
SD55 661.60 59
SD56 672.10 60
SD57 682.60 61
SD58 693.10 62
SD59 703.60 63
SD60 714.10 64
SD61 724.60 65
SD62 735.10 66
SD63 745.60 67
SD64 756.10 68
SD65 766.60 69
SD66 777.10 70
SD67 787.60 71
SD68 798.10 72
SD69 808.60 73
SD70 819.10 74
SD71 829.60 75
SD72 840.10 76
SD73 850.60 77
SD74 861.10 78
SD75 871.60 79
SD76 882.10 80
SD77 892.60 81
SD78 903.10 82
SD79 913.60 83
SD80 924.10 84
SD81 934.60 85
SD82 945.10 86
SD83 955.60 87
SD84 966.10 88
SD85 976.60 89
SD86 987.10 90
SD87 997.60 91
SD88 1008.10 92
SD89 1018.60 93
SD90 1029.10 94
SD91 1039.60 95
SD92 1050.10 96
SD93 1060.60 97
SD94 1071.10 98
SD95 1081.60 99
SD96 1092.10 100
SD97 1102.60 101
SD98 1113.10 102
SD99 1123.60 103
SD100 1134.10 104
SD101 1144.60 105
SD102 1155.10 106
SD103 1165.60 107
SD104 1176.10 108
SD105 1186.60 109
SD106 1197.10 110
SD107 1207.60 111
SD108 1218.10 112
SD109 1228.60 113
SD110 1239.10 114
SD111 1249.60 115
SD112 1260.10 116
SD113 1270.60 117
SD114 1281.10 118
SD115 1291.60 119
SD116 1302.10 120
SD117 1312.60 121
SD118 1323.10 122
SD119 1333.60 123
SD120 1344.10 124
SD121 1354.60 125
SD122 1365.10 126
SD123 1375.60 127
SD124 1386.10 128
SD125 1396.60 129
SD126 1407.10 130
SD127 1417.60 131
SD128 1428.10 132
SD129 1438.60 133
SD130 1449.10 134
SD131 1459.60 135
SD132 1470.10 136
SD133 1480.60 137
SD134 1491.10 138
SD135 1501.60 139
SD136 1512.10 140
SD137 1522.60 141
SD138 1533.10 142
SD139 1543.60 143
SD140 1554.10 144
SD141 1564.60 145
SD142 1575.10 146
SD143 1585.60 147
SD144 1596.10 148
SD145 1606.60 149
SD146 1617.10 150
SD147 1627.60 151
SD148 1638.10 152
SD149 1648.60 153
SD150 1659.10 154
SD151 1669.60 155
SD152 1680.10 156
SD153 1690.60 157
SD154 1701.10 158
SD155 1711.60 159
SD156 1722.10 160
SD157 1732.60 161
SD158 1743.10 162
SD159 1753.60 163
SD160 1764.10 164
SD161 1774.60 165
SD162 1785.10 166
SD163 1795.60 167
SD164 1806.10 168
SD165 1816.60 169
SD166 1827.10 170
SD167 1837.60 171
SD168 1848.10 172
SD169 1858.60 173
SD170 1869.10 174
SD171 1879.60 175
SD172 1890.10 176
SD173 1900.60 177
SD174 1911.10 178
SD175 1921.60 179
SD176 1932.10 180
SD177 1942.60 181
SD178 1953.10 182
SD179 1963.60 183
SD180 1974.10 184
SD181 1984.60 185
SD182 1995.10 186
SD183 2005.60 187
SD184 2016.10 188
SD185 2026.60 189
SD186 2037.10 190
SD187 2047.60 191
SD188 2058.10 192
SD189 2068.60 193
SD190 2079.10 194
SD191 2089.60 195
SD192 2100.10 196
SD193 2110.60 197
SD194 2121.10 198
SD195 2131.60 199
SD196 2142.10 200
SD197 2152.60 201
SD198 2163.10 202
SD199 2173.60 203
SD200 2184.10 204
SD201 2194.60 205
SD202 2205.10 206
SD203 2215.60 207
SD204 2226.10 208
SD205 2236.60 209
SD206 2247.10 210
SD207 2257.60 211
SD208 2268.10 212
SD209 2278.60 213
SD210 2289.10 214
SD211 2299.60 215
SD212 2310.10 216
SD213 2320.60 217
SD214 2331.10 218
SD215 2341.60 219
SD216 2352.10 220
SD217 2362.60 221
SD218 2373.10 222
SD219 2383.60 223
SD220 2394.10 224
SD221 2404.60 225
SD222 2415.10 226
SD223 2425.60 227
SD224 2436.10 228
SD225 2446.60 229
SD226 2457.10 230
SD227 2467.60 231
SD228 2478.10 232
SD229 2488.60 233
SD230 2499.10 234
SD231 2509.60 235
SD232 2520.10 236
SD233 2530.60 237
SD234 2541.10 238
SD235 2551.60 239
SD236 2562.10 240
SD237 2572.60 241
SD238 2583.10 242
SD239 2593.60 243
SD240 2604.10 244
SD241 2614.60 245
SD242 2625.10 246
SD243 2635.60 247
SD244 2646.10 248
SD245 2656.60 249
SD246 2667.10 250
SD247 2677.60 251
SD248 2688.10 252
SD249 2698.60 253
SD250 2709.10 254
SD251 2719.60 255
SD252 2730.10 256
SD253 2740.60 257
SD254 2751.10 258
SD255 2761.60 259
SD256 2772.10 260
SD257 2782.60 261
SD258 2793.10 262
SD259 2803.60 263
SD260 2814.10 264
SD261 2824.60 265
SD262 2835.10 266
SD263 2845.60 267
SD264 2856.10 268
SD265 2866.60 269
SD266 2877.10 270
SD267 2887.60 271
SD268 2898.10 272
SD269 2908.60 273
SD270 2919.10 274
SD271 2929.60 275
SD272 2940.10 276
SD273 2950.60 277
SD274 2961.10 278
SD275 2971.60 279
SD276 2982.10 280
SD277 2992.60 281
SD278 3003.10 282
SD279 3013.60 283
SD280 3024.10 284
SD281 3034.60 285
SD282 3045.10 286
SD283 3055.60 287
SD284 3066.10 288
SD285 3076.60 289
SD286 3087.10 290
SD287 3097.60 291
SD288 3108.10 292
SD289 3118.60 293
SD290 3129.10 294
SD291 3139.60 295
SD292 3150.10 296
SD293 3160.60 297
SD294 3171.10 298
SD295 3181.60 299
SD296 3192.10 300
SD297 3202.60
SD298 3213.10
SD299 3223.60
SD300 3234.10
SD301 3244.60
SD302 3255.10
SD303 3265.60
SD304 3276.10
SD305 3286.60
SD306 3297.10
SD307 3307.60
SD308 3318.10
SD309 3328.60
SD310 3339.10
SD311 3349.60
SD312 3360.10
SD313 3370.60
SD314 3381.10
SD315 3391.60
SD316 3402.10
SD317 3412.60
SD318 3423.10
SD319 3433.60
SD320 3444.10
SD321 3454.60
SD322 3465.10
SD323 3475.60
SD324 3486.10
SD325 3496.60
SD326 3507.10
SD327 3517.60
SD328 3528.10
SD329 3538.60
SD330 3549.10
SD331 3559.60
SD332 3570.10
SD333 3580.60
SD334 3591.10
SD335 3601.60
SD336 3612.10
SD337 3622.60
SD338 3633.10
SD339 3643.60
SD340 3654.10
SD341 3664.60
SD342 3675.10
SD343 3685.60
SD344 3696.10
SD345 3706.60
SD346 3717.10
SD347 3727.60
SD348 3738.10
SD349 3748.60
SD350 3759.10
SD351 3769.60
SD352 3780.10
SD353 3790.60
SD354 3801.10
SD355 3811.60
SD356 3822.10
SD357 3832.60
SD358 3843.10
SD359 3853.60
SD360 3864.10
SD361 3874.60
SD362 3885.10
SD363 3895.60
SD364 3906.10
SD365 3916.60
SD366 3927.10
SD367 3937.60
SD368 3948.10
SD369 3958.60
SD370 3969.10
SD371 3979.60
SD372 3990.10
SD373 4000.60
SD374 4011.10
SD375 4021.60
SD376 4032.10
SD377 4042.60
SD378 4053.10
SD379 4063.60
SD380 4074.10
SD381 4084.60
SD382 4095.10
SD383 4105.60
SD384 4116.10
SD385 4126.60
SD386 4137.10
SD387 4147.60
SD388 4158.10
SD389 4168.60
SD390 4179.10
SD391 4189.60
SD392 4200.10
SD393 4210.60
SD394 4221.10
SD395 4231.60
SD396 4242.10
SD397 4252.60
SD398 4263.10
SD399 4273.60
SD400 4284.10
SD401 4294.60
SD402 4305.10
SD403 4315.60
SD404 4326.10
SD405 4336.60
SD406 4347.10
SD407 4357.60
SD408 4368.10
SD409 4378.60
SD410 4389.10
SD411 4399.60
SD412 4410.10
SD413 4420.60
SD414 4431.10
SD415 4441.60
SD416 4452.10
SD417 4462.60
SD418 4473.10
SD419 4483.60
SD420 4494.10
SD421 4504.60
SD422 4515.10
SD423 4525.60
SD424 4536.10
SD425 4546.60
SD426 4557.10
SD427 4567.60
SD428 4578.10
SD429 4588.60
SD430 4599.10
SD431 4609.60
SD432 4620.10
SD433 4630.60
SD434 4641.10
SD435 4651.60
SD436 4662.10
SD437 4672.60
SD438 4683.10
SD439 4693.60
SD440 4704.10
SD441 4714.60
SD442 4725.10
SD443 4735.60
SD444 4746.10
SD445 4756.60
SD446 4767.10
SD447 4777.60
SD448 4788.10
SD449 4798.60
SD450 4809.10
SD451 4819.60
SD452 4830.10
SD453 4840.60
SD454 4851.10
SD455 4861.60
SD456 4872.10
SD457 4882.60
SD458 4893.10
SD459 4903.60
SD460 4914.10
SD461 4924.60
SD462 4935.10
SD463 4945.60
SD464 4956.10
SD465 4966.60
SD466 4977.10
SD467 4987.60
SD468 4998.10
SD469 5008.60
SD470 5019.10
SD471 5029.60
SD472 5040.10
SD473 5050.60
SD474 5061.10
SD475 5071.60
SD476 5082.10
SD477 5092.60
SD478 5103.10
SD479 5113.60
SD480 5124.10
SD481 5134.60
SD482 5145.10
SD483 5155.60
SD484 5166.10
SD485 5176.60
SD486 5187.10
SD487 5197.60
SD488 5208.10
SD489 5218.60
SD490 5229.10
SD491 5239.60
SD492 5250.10
SD493 5260.60
SD494 5271.10
SD495 5281.60
SD496 5292.10
SD497 5302.60
SD498 5313.10
SD499 5323.60
SD500 5334.10
METAL LEADS & RATES SAND/ EARTH LEADS & RATES
2008-09 2008-09
From From
NOTATION RATE LEAD NOTATION RATE
SSR SSR
MLOAD 12.80 12.80 SLOAD 10.00 10.00
MUNLOAD 8.70 8.70 SUNLOAD 8.50 8.50
MSTACK 8.70 8.70 SSTACK 5.50 5.50
0.00 0 0.00
110.00 0.25 SD250 50.00 50.00
MT500 110.00 110.00 0.50 SD500 75.00 75.00
MT1 120.00 120.00 1 SD1 100.00 100.00
MT2 126.00 126.00 2 SD2 106.00 106.00
MT3 132.00 132.00 3 SD3 112.00 112.00
MT4 138.00 138.00 4 SD4 118.00 118.00
MT5 144.00 144.00 5 SD5 124.00 124.00
MT6 150.00 150.00 6 SD6 130.00 130.00
MT7 156.00 156.00 7 SD7 136.00 136.00
MT8 162.00 162.00 8 SD8 142.00 142.00
MT9 168.00 168.00 9 SD9 148.00 148.00
MT10 174.00 174.00 10 SD10 154.00 154.00
MT11 180.00 180.00 11 SD11 160.00 160.00
MT12 186.00 186.00 12 SD12 166.00 166.00
MT13 192.00 192.00 13 SD13 172.00 172.00
MT14 198.00 198.00 14 SD14 178.00 178.00
MT15 204.00 204.00 15 SD15 184.00 184.00
MT16 210.00 210.00 16 SD16 190.00 190.00
MT17 216.00 216.00 17 SD17 196.00 196.00
MT18 222.00 222.00 18 SD18 202.00 202.00
MT19 228.00 228.00 19 SD19 208.00 208.00
MT20 234.00 234.00 20 SD20 214.00 214.00
MT21 239.75 5.7500 21 SD21 219.00 5.0000
MT22 245.50 5.5000 22 SD22 224.00 4.8000
MT23 251.25 5.0000 23 SD23 229.00 4.6000
MT24 257.00 4.7500 24 SD24 234.00 4.4000
MT25 262.75 4.5000 25 SD25 239.00 4.2000
MT26 268.50 26 SD26 244.00
MT27 274.25 27 SD27 249.00
MT28 280.00 28 SD28 254.00
MT29 285.75 29 SD29 259.00
MT30 291.50 30 SD30 264.00
MT31 297.00 31 SD31 268.80
MT32 302.50 32 SD32 273.60
MT33 308.00 33 SD33 278.40
MT34 313.50 34 SD34 283.20
MT35 319.00 35 SD35 288.00
MT36 324.50 36 SD36 292.80
MT37 330.00 37 SD37 297.60
MT38 335.50 38 SD38 302.40
MT39 341.00 39 SD39 307.20
MT40 346.50 40 SD40 312.00
MT41 352.00 41 SD41 316.80
MT42 357.50 42 SD42 321.60
MT43 363.00 43 SD43 326.40
MT44 368.50 44 SD44 331.20
MT45 374.00 45 SD45 336.00
MT46 379.50 46 SD46 340.80
MT47 385.00 47 SD47 345.60
MT48 390.50 48 SD48 350.40
MT49 396.00 49 SD49 355.20
MT50 401.50 50 SD50 360.00
MT51 406.50 51 SD51 364.60
MT52 411.50 52 SD52 369.20
MT53 416.50 53 SD53 373.80
MT54 421.50 54 SD54 378.40
MT55 426.50 55 SD55 383.00
MT56 431.50 56 SD56 387.60
MT57 436.50 57 SD57 392.20
11 first class bedding with Granular material 279.36 130.95 43.65 34.92 61.11 8.73 52.38 8.73 17.46 8.73 8.73 654.75 Cum
SUMMARY OF BOX CULVERTS
CHANDRAMPET TO MARRIMADLA
Sn No. DESCRIPTION UNIT QUANTITY RATE TOTAL QUANTITY
5.01 Earthwork in excavation of foundation for structures,
including all lifts and leads complete as per drawing and
Technical Specification Clause 304 and 2903 Cun 122.62
1 0/000 Not Visible Not Visible 10.6 2m ReConstruction HP NP4 1 X1000 mm dia
2 0/800 Slab Culvert 1vx0.9x0.4 7.4 2.4 ReConstruction HP NP4 1 X1000 mm dia VILLAGE DRAINAGE
3 1/030 Slab Culvert 1vx0.9x0.4 7.7 3.5 ReConstruction HP NP4 1 X1000 mm dia VILLAGE DRAINAGE
8 2/050 Slab Culvert 2vx2.8X1.4 7.6 5.5 widening RCC SLAB 2x3x2
13 5/890 Slab Culvert 3vx3.0x1.7 8.5 19.5 widening rcc slab 3x3x2
26 13/880 RCCSlab Culvert 2vx2x1.5 7.6 6.2 widening RCC SLAB 2x2x2
"Widening of existing Single lane /Intermediate lane to Double lane for the road (1)
pwd(Chandrampet) road to Marrimadla (via) Konaraopet Mandal. Km.0/0 to 27/5 ,
(2) Vemulawada -Sirikonda road from km.28/0 to 32/6" in karimnagar district
AMOUNT OF ESTIMATE
Rs 3550 Lakhs