Professional Documents
Culture Documents
7 Earned Value Management Formulas For Project Controls
7 Earned Value Management Formulas For Project Controls
7 Earned Value Management Formulas For Project Controls
1-877-626-2690
Blog > Project Controls Tips & Tutorials > 7 Earned Value Management Formulas To Know For Project Control
EV = BAC x % Complete
To nd the Planned Value at any point in the project, simply add up all your
planned costs up to that point. Often, your planned costs are referenced from the
project’s baseline.
Like Planned Value, Actual Cost is a cummulative value that continues to grow as
the project progresses.
Budget at Completion
Budget at Completion, also called BAC, is the total amount of money that you’re
expecting to spend to nish a particular task or for the entire project. You arrive at
this number by taking all of the estimates that you’ve already conducted and
assumptions that you’ve made about things like schedule and work required and
adding them together.
SV = EV – PV
CV = EV – AC
SPI = EV / PV
CPI = EV / AC
Estimate to Complete (ETC)
The Estimate to Complete is the number that describes exactly what it will take to
nish a particular task, accounting for all of the work that you’ve done up to this
point. To nd this number, take the Estimate at Completion and subtract from it
the Actual Costs to Date.
ETC = EAC – AC
Get to know these core Earned Value Management formulas and keep them
handy. Chances are you’ll need them soon.
Comments
Reply
Reply
Azad
Reply
With out an accurate progress measurement system, EVM will be of limited use
for Project Controls personnel.
Reply
Reply
Esther Joy says:
November 13, 2015 at 7:18 am
Thanks for giving such a nice article . The information you shared will
help me to get a good knowledge.
Reply
Reply
BR
Praveen Malik
Reply
BR
Praveen Malik
Reply
Mustafa says:
December 03, 2016 at 2:41 pm
Michael
thanks.
For calculating EAC, article says as EAC= BAC-CV, but the formula below the
article says as EAC=BAC/CPI. the both formulas giving di erent values.
please advise.
regards
Mustafa
Project Manager
Cecon Contracting, Dubai
Reply
Reply
ECD will now then your realistic nish date using if your earned value is accurate.
Thanks,
Ferds
Reply
Reply
Reply
Reply
Reply
Leave a Reply
Your email address will not be published. Required elds are marked *
Comment
Name *
Email *
Post Comment
This site uses Akismet to reduce spam. Learn how your comment data is processed.
POPULAR ARTICLES