Professional Documents
Culture Documents
Report BSC
Report BSC
Report BSC
1.1 General
The work was carried out at the behest of the Executive Engineer, Punjab PWD (B&R),
Khanna.
1.2 Object
The object was to obtain sequence and extent of sub-soil and to ascertain the characteristics
of sub-soil so as to arrive at design parameters for the foundations of proposed Judicial
Complex Building.
1.3 Borehole Locations
Three boreholes each carried out upto a depth of 20.0 meter were used to carry out the
desired investigation.The existing ground level of all the three boreholes is around the same
and is eight feet below the existing Road Level.
Key Plan of borehole locations is attached.
Sub-soil water was not encountered upto a level of 20.0 metre below existing ground level at
the proposed site .
Notations
The various notations of soil parameters as recommended by BIS are given in Appendix-1.
2. FIELD INVESTIGATION:
These were done as per Appendix -2, under the following heads:
2.1 Boring Operation and Sampling
2.2 Disturbed/ Undisturbed samples
2.3 Standard Penetration Tests and related corrections
3. LABORATORY INVESTIGATIONS:
Through field and laboratory investigations, all the relevant parameters pertaining to various
strata met in three boreholes were determined. Based upon these, borehole log charts and
data sheets have been prepared and are reported in tables BH1, BH2, & BH3.
The data of these sheets form the basis of evaluation of allowable bearing capacity of the
proposed foundation.
Using the methodology as given in Appendix-2, Observed and Corrected SPT values have
been computed.
6 FOUNDATION PARAMETERS:
It is a case of Bored Cast-in-Situ Piles. Safe loads have been worked out by
using the following parameters.
7.1 General
.
The ultimate load capacity QU is estimated from the following expression:
QU = QPU + ΣQSU
QS = QU/FOS
The code recommends that for working out safe load, a minimum value of factor
of safety should be adopted as 2.5
Depending upon the nature of strata, the above ultimate resistances are computed
as under:-
i) Cohesive Soils
a) QSU = α Cu As
α = Reduction factor
The following values of α may be taken depending upon the N-value
-------------------------------------------------------------------------------------------------------------
N-value <4 4 to 8 8 to 15 >15
2
As = Surface area of the Pile Shaft in m
b) QPU = Ap Nc Cp
2
Ap = Cross sectional area of pile toe in m
Nc = Bearing capacity factor usually taken as 9
PDi = Effective overburden pressure for the ith layer where i varies from 1 to n
2
Ap = Cross sectional area of pile toe in m
D = Diameter of pile shaft in m
’
γ = Effective unit weight of soil at pile toe
PD = Effective overburden pressure at pile toe
Notes: 1. Nγ factor can be taken for general shear failure as per IS : 6403-1981.
7.2 Computations
i) Qsu
Combining the data of the boreholes, the desired pile soil interaction system
is as under.
--------------------------------------------------------------------------------------------------
Depth Range Nature of Thickness of Governing Parameters
Strata Strata
--------------------------------------------------------------------------------------------------
2
1.5 to 7.0 m Ø – Soil 5.5 m K=1.25 PDi = 5.04 t/m
Avge N”= 17
0
δ = Ø = 32.5 (As per IS)
7.0 to 7.5 m C- Soil 0.5 m α =0.3
2
Avge Cu = 0.45 kg/cm
2
or 4.5 t/m
2
7.5 to 9.5 m Ø- Soil 2.0 m K=1.25 PDi = 12.83 t/m
Avge N”= 19
0
δ = Ø = 32.5 (As per IS)
--------------------------------------------------------------------------------------------------
0
Qsu-1 = 1.25 x 5.04 x Tan 32.5 x π x 0.6 x 5.5 = 41.62 t
0
Qsu-3 = 1.25 x 12.83 x Tan 32.5 x π x 0.6 x 2.0 = 38.52 t
ii) Qpu
2
Q pu = 0.785 D (0.5 γ’ B Nγ + PD x Nq)
3
B = 0.6 m γ’= 1.89 t/m PD = 6.4 t/m2
0
N” = 19 ; Ø = 32.5 ( As per IS )
0
Against Ø = 32.5 ; Nq = 30 ; Nγ = 35.21
Qpu = 59.98 t
iii) Qu & Qs
RECOMMENDATIONS
Based on the borehole data and using static formula , safe vertical load for
piles has been worked out with details as under
reliability, Load Test on piles should be compulsorily done as per the laid
down procedure.
Er. I.J.Ghai
( For CEA, Panchkula )
APPENDIX-1
NOTATIONS
APPENDIX-2
FIELD INVESTIGATIONS
2.2 Samples
Apart from the disturbed samples retrieved from the split spoon sampler,
disturbed/undisturbed samples were obtained depending upon the nature of soil from different
depths in the borehole. These samples were subsequently tested in the laboratory so as to
determine the various index and engineering properties of the various sub soil strata met in the
borehole.
N’ = CN x N
Where ‘CN’ is overburden pressure correction and is scaled off from the figure as provided in
the code. N’ are the normalized blows.
2) Submergence Correction
Wherever both the overburden and submergence correction are necessary, the overburden
correction is applied first.
The overburden correction is meant for granular strata. Submergence correction is applied
only in case of sands and non-plastic silts.
APPENDIX-3
LABORATORY INVESTIGATIONS
SYMBOLICREPRESENTATION
FIELDDRYDENSITYG/CC
DESCRIPTIONOFSOIL
%MOISTURE
% SILT/CLAY
CORRECTED
DEPTHOFSAMPLE(FROMREFPOINT(M)
SAMPLENO
OBSERVED
%GRAVEL
BULKDENSITYgms/cc
LEVEL(M)
%SAND
Sr.No.
LL
PL
PI
Silty Sand+ Clay(0.0 -
1 SPT-1 1.5 96.0 1.5m)
5 SPT-5 7.5 90.0 Clay (7.0 - 7.3m) 3.5 2.9 93.6 28.4 18.9 9.4 1.92 24.3 1.54
6 SPT-6 9.0 88.5 27 19 0.0 92.9 7.1 NP NP NP 1.88 20.9 1.56
SYMBOLICREPRESENTATION
FIELDDRYDENSITYG/CC
BULKDENSITYgms/c
DESCRIPTIONOFSOIL
%MOISTURE
% SILT/CLAY
CORRECTED
DEPTHOFSAMPLE(FROMREFPOINT(M)
SAMPLENO
OBSERVED
%GRAVEL
LEVEL(M)
%SAND
c
Sr.No.
LL
PL
PI
Silty Sand+ Clay(0.0 -
1 SPT-1 1.5 96.0 2.3m)
2 SPT-2 3.0 94.5 10 12 0.0 94.7 5.3 NP NP NP 1.73 4.81 1.65
SYMBOLICREPRESENTATION
BULKDENSITYgms/cc
FIELDDRYDENSITYG/CC
DESCRIPTIONOFSOIL
%MOISTURE
% SILT/CLAY
CORRECTED
SAMPLENO
OBSERVED
%GRAVEL
LEVEL(M)
%SAND
Sr.No.
LL
PL
PI
Silty Sand+ Clay(0.0 -
1 SPT-1 1.5 96.0 1.5m)
2 SPT-2 3.0 94.5 12 15 0.0 95.8 4.2 NP NP NP 1.5 3.49 1.46
5 SPT-5 7.5 90.0 Clay (8.5 - 9.0) 3.5 2.9 93.6 28.4 18.9 9.4
6 SPT-6 9.0 88.5 27 19 0.0 93.9 6.1 NP NP NP 1.88 20 1.57
SAND (9 - 11.5 m)
7 SPT-7 10.5 87.0
8 SPT-8 12.0 85.5 21 15 0.0 92.3 7.7 NP NP NP 2.02 26.0 1.60
Clay (11.5-13.0 m)
9 SPT-9 13.5 84.0
10 SPT-10 15.0 82.5 50 24 Sand (13.0-17.0 m) 0.0 93.5 6.5 NP NP NP 1.9 30.29 1.46