WEEKLY PROGRESS REPORT-BKC CASTING YARD/MML2B/MBZ-RCC/CA06

START DATE OF CASTING YARD: 20.6.2018


WORK PROGRESS DATE : 21.10.2018-28.10.2018(S2S)
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
CA06 CASTING YARD DEVELOPEMNT 06-08-18 29-12-2018 100.00% 8.70% 10.05% 1.35%
A BATCHING PLANT 1 25-08-2018 14-10-2018 6.50% 4.00% 4.47% 0.47%
A-1 1ST SILO-Group B 01-09-2018 14-10-2018 09-09-2018 1.50% 100.00% 100.00% 1.50% 1.50% 0.00%
PILING P1-800 MM DIA 01-09-2018 03-09-2018 09-09-2018 11-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P2-800 MM DIA 04-09-2018 06-09-2018 12-09-2018 14-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P3-800 MM DIA 07-09-2018 09-09-2018 20-09-2018 21-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P4-800 MM DIA 10-09-2018 12-09-2018 15-09-2018 19-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
EXCAVATION 14-09-2018 14-09-2018 22-09-2018 24-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CHIPPING 15-09-2018 16-09-2018 26-09-2018 27-09-2018 Nos 4.00 4.00 4.00 100.00% 100.00% COMPLETED
PCC 17-09-2018 17-09-2018 25-09-2018 25-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CAP R/F 18-09-2018 20-09-2018 28-09-2018 29-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CAP CONCRETING 21-09-2018 21-09-2018 30-09-2018 30-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PEDESTAL 22-09-2018 22-09-2018 08-10-2018 08-10-2018 Nos 4.00 4.00 4.00 100.00% 100.00% COMPLETED
SILO ERECTION 14-10-2018 14-10-2018 13-10-2018 13-10-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED

A-2 2ND SILO- Group C 05-09-2018 14-10-2018 01-09-2018 1.50% 100.00% 100.00% 1.50% 1.50% 0.00%
PILING P1-800 MM DIA 05-09-2018 07-09-2018 07-09-2018 09-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P2-800 MM DIA 08-09-2018 10-09-2018 29-08-2018 01-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P3-800 MM DIA 11-09-2018 13-09-2018 02-09-2018 04-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILING P4-800 MM DIA 14-09-2018 16-09-2018 05-09-2018 06-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
EXCAVATION 09-09-2018 09-09-2018 22-09-2018 24-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CHIPPING 10-09-2018 11-09-2018 26-09-2018 27-09-2018 Nos 4.00 4.00 4.00 100.00% 100.00% COMPLETED
PCC 12-09-2018 12-09-2018 25-09-2018 25-09-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CAP R/F 13-09-2018 15-09-2018 01-10-2018 03-10-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PILE CAP CONCRETING 17-09-2018 17-09-2018 04-10-2018 04-10-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
PEDESTAL 18-09-2018 18-09-2018 08-10-2018 08-10-2018 Nos 4.00 4.00 4.00 100.00% 100.00% COMPLETED
SILO ERECTION 14-10-2018 14-10-2018 13-10-2018 13-10-2018 Nos 1.00 1.00 1.00 100.00% 100.00% COMPLETED
A-3 3RD SILO-Group A 13-09-2018 12-10-2018 1.50% 0.00% 0.00% 0.00% 0.00% 0.00%
PILING P1-800 MM DIA 13-09-2018 15-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P2-800 MM DIA 16-09-2018 18-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P3-800 MM DIA 19-09-2018 21-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P4-800 MM DIA 22-09-2018 24-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
EXCAVATION 26-09-2018 26-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 27-09-2018 28-09-2018 Nos 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 29-09-2018 29-09-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 30-09-2018 02-10-2018 Nos 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 03-10-2018 03-10-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 04-10-2018 04-10-2018 Nos 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SILO ERECTION 12-10-2018 12-10-2018 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
A-4 RMC PLANT FOUNDATION 60 Cum/hr 30-08-2018 14-10-2018 1.00% 100.00% 100.00% 1.00% 1.00% 0.00%
EXCAVATION 30-08-2018 31-08-2018 06-09-2018 07-09-2018 Nos. 3.00 3.00 3.00 100.00% 100.00% COMPLETED
SOLING 08-09-2018 09-09-2018 08-09-2018 08-09-2018 Nos. 3.00 3.00 3.00 100.00% 100.00% COMPLETED
PCC 10-09-2018 11-09-2018 09-09-2018 09-09-2018 Nos. 3.00 3.00 3.00 100.00% 100.00% COMPLETED
REINFORCEMENT FIXING 12-09-2018 14-09-2018 10-09-2018 12-09-2018 Nos. 3.00 3.00 3.00 100.00% 100.00% COMPLETED
FOUNDATION CONCRETING 17-09-2018 18-09-2018 12-09-2018 13-09-2018 Nos. 3.00 3.00 3.00 100.00% 100.00% COMPLETED
RMC PLANT ERECTION 13-10-2018 14-10-2018 22-09-2018 28-09-2018 Nos. 1.00 1.00 1.00 100.00% 100.00% COMPLETED
A-5 RETAINING WALL FOR STACKING BINS 25-08-2018 30-09-2018 1.00% 46.67% 0.00% 0.47% 0.47%
EXCAVATION 25-08-2018 26-08-2018 18-10-2018 Nos. 1.00 0.00 1.00 100.00% 100.00% In Progress Excavation of 24 pits done.
CONCRETING 27-08-2018 28-08-2018 Nos. 1.00 0.00 0.20 0.00% 20.00% In Progress
FABRICATION AND ERECTION 29-08-2018 29-08-2018 20-10-2018 Nos. 1.00 0.00 0.20 80.00% 20.00% In Progress Fabrication of M.S Sheet is in progress
B BATCHING PLANT 2 17-09-18 24-10-18 4.00% 0.00% 0.00% 0.00%
B-1 1ST SILO 25-09-18 24-10-18 1.50% 0.00% 0.00% 0.00% 0.00% 0.00%
PILING P1-800 MM DIA 25-09-18 27-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P2-800 MM DIA 28-09-18 30-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P3-800 MM DIA 01-10-18 03-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
PILING P4-800 MM DIA 04-10-18 06-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
EXCAVATION 08-10-18 08-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 09-10-18 10-10-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 11-10-18 11-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 12-10-18 14-10-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 15-10-18 15-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 16-10-18 16-10-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SILO ERECTION 24-10-18 24-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
B-2 2ND SILO 17-09-18 14-10-18 1.50% 0.00% 0.00% 0.00% 0.00% 0.00%
PILING P1-800 MM DIA 17-09-18 19-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P2-800 MM DIA 20-09-18 22-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P3-800 MM DIA 23-09-18 25-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P4-800 MM DIA 26-09-18 28-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
EXCAVATION 21-09-18 21-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 22-09-18 23-09-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 24-09-18 24-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 25-09-18 27-09-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 28-09-18 28-09-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 29-09-18 29-09-18 Nos. 4.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SILO ERECTION 14-10-18 14-10-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
B-3 RMC PLANT FOUNDATION 30Cum/hr 30-09-2018 26-10-2018 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
EXCAVATION 30-09-2018 01-10-2018 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 09-01-2018 10-10-2018 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 11-10-2018 12-10-2018 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
REINFORCEMENT FIXING 13-10-2018 15-10-2018 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
FOUNDATION CONCRETING 16-10-2018 17-10-2018 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RMC PLANT ERECTION 25-10-2018 26-10-2018 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
C U-GIRDER Bay I 06-08-18 17-12-18 3.00% 2.04% 2.22% 0.18%
GANTRY FOUNDATION FOR U-GIRDER 06-08-18 16-10-18
C-1 RHS (250 MTR) (SINGLE TRACK) 06-08-18 05-10-18 1.50% 75.47% 80.13% 1.13% 1.20% 0.07%
EXCAVATION 06-08-18 19-08-18 17-08-2018 Rmt 250.00 225.00 235.00 90.00% 94.00% PROGRESS
SOLING 07-08-18 30-08-18 19-08-2018 Rmt 250.00 205.00 220.00 82.00% 88.00% PROGRESS
PCC 20-08-18 03-09-18 24-08-2018 Rmt 250.00 205.00 220.00 82.00% 88.00% PROGRESS
RAFT 29-08-18 02-10-18 04-09-2018 Rmt 250.00 201.00 216.00 80.40% 86.40% PROGRESS
PEDESTAL 01-09-18 05-10-18 27-09-2018 Rmt 250.00 196.00 211.00 78.40% 84.40% PROGRESS
RAIL ALIGNMENT 04-09-18 03-10-18 Rmt 250.00 100.00 100.00 40.00% 40.00% PROGRESS
C-2 LHS (250 MTR) (DOUBLE TRACK) 13-08-18 16-10-18 1.50% 60.27% 67.60% 0.90% 1.01% 0.11%
EXCAVATION 13-08-18 26-08-18 15-08-2018 Rmt 250.00 170.00 195.00 68.00% 78.00% PROGRESS
SOLING 14-08-18 02-09-18 17-08-2018 Rmt 250.00 170.00 190.00 68.00% 76.00% PROGRESS
PCC 20-08-18 03-09-18 21-08-2018 Rmt 250.00 155.00 190.00 62.00% 76.00% PROGRESS
RAFT 01-09-18 10-10-18 30-08-2018 Rmt 250.00 155.00 185.00 62.00% 74.00% PROGRESS
PEDESTAL 04-09-18 13-10-18 23-09-2018 Rmt 250.00 296.00 154.00 61.60% 61.60% PROGRESS
RAIL ALIGNMENT 07-09-18 16-10-18 Rmt 250.00 100.00 100.00 40.00% 40.00% PROGRESS
D GANTRY ERECTION /ORDER PLACED 12-09-18 18-09-18 3.00% 25.00% 25.00% 0.75% 0.75% 0.00% PROGRESS
GANTRY ERECTION /ORDER PLACEDBAY 1 (100 T 2 12-09-18 18-09-18 24-10-2018 Nos. 2.00 0.50 0.50 25.00% 25.00%
E PILING WORK FOR LIVE END AND DEAD END 6.00% 0.26% 0.55% 0.29%
E-1 U-GIRDER 1ST LIVE END 07-09-18 11-10-18 1.50% 8.33% 18.33% 0.13% 0.28% 0.15%
PILING A1-1200 MM DIA 07-09-18 08-09-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILING A2-1200 MM DIA 09-09-18 10-09-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILING A3-1200 MM DIA 11-09-18 12-09-18 27-10-2018 Nos. 1.00 0.00 0.50 0.00% 50.00% IN PROGRESS Boring Upto 4.5Mtrs
PILING A4-1200 MM DIA 13-09-18 14-09-18 05-10-2018 09-10-2018 Nos. 1.00 1.00 1.00 100.00% 100.00% COMPLETED Concreting Done at 24 Mtrs
PILING A5-1200 MM DIA 15-09-18 16-09-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILING A6-1200 MM DIA 17-09-18 18-09-18 09-10-2018 28-10-2018 Nos. 1.00 0.00 0.70 0.00% 70.00% COMPLETED 30mtr terminated
EXCAVATION 19-09-18 26-09-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 27-09-18 30-09-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PCC 01-10-18 01-10-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 02-10-18 06-10-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 07-10-18 07-10-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
BULKHEAD 08-10-18 11-10-18 Nos. 1.00 0.00 0.00% 0.00% NO PROGRESS
E-2 U-GIRDER 2ND LIVE END 24-09-18 28-10-18 1.50% 8.33% 8.33% 0.13% 0.13% 0.00%
PILING B1-1200 MM DIA 24-09-18 25-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING B2-1200 MM DIA 26-09-18 27-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
PILING B3-1200 MM DIA 28-09-18 29-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING B4-1200 MM DIA 30-09-18 01-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING B5-1200 MM DIA 02-10-18 03-10-18 12-10-2018 19-10-2018 Nos. 1.00 1.00 1.00 100.00% 100.00% COMPLETED Concreting Done - 24mtrs
PILING B6-1200 MM DIA 04-10-18 05-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
EXCAVATION 06-10-18 13-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 14-10-18 17-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PCC 18-10-18 18-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 19-10-18 23-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 24-10-18 24-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
BULKHEAD 25-10-18 28-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
E-3 U-GIRDER 1ST DEAD END 07-09-18 11-10-18 1.50% 0.83% 5.83% 0.01% 0.09% 0.08%
PILING C1-1200 MM DIA 07-09-18 08-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING C2-1200 MM DIA 09-09-18 10-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING C3-1200 MM DIA 11-09-18 12-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING C4-1200 MM DIA 13-09-18 14-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING C5-1200 MM DIA 15-09-18 16-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING C6-1200 MM DIA 17-09-18 18-09-18 19-10-2018 Nos. 1.00 0.10 0.70 10.00% 70.00% IN PROGRESS 12mtr done /21.1mtr
EXCAVATION 19-09-18 26-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 27-09-18 30-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PCC 01-10-18 01-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 02-10-18 06-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 07-10-18 07-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
BULKHEAD 08-10-18 11-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
E-4 U-GIRDER 2ND DEAD END 23-09-18 28-10-18 1.50% 0.00% 4.17% 0.00% 0.06% 0.06%
PILING D1-1200 MM DIA 23-09-18 24-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING D2-1200 MM DIA 25-09-18 26-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING D3-1200 MM DIA 27-09-18 28-09-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING D4-1200 MM DIA 29-09-18 30-09-18 20-10-2018 Nos. 1.00 0.50 0.00% 50.00% IN PROGRESS 18mtr done/21.1mtr
PILING D5-1200 MM DIA 01-10-18 02-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILING D6-1200 MM DIA 03-10-18 04-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
EXCAVATION 05-10-18 12-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 13-10-18 17-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PCC 18-10-18 18-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 19-10-18 23-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 24-10-18 24-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
BULKHEAD 25-10-18 28-10-18 Nos. 1.00 0.00% 0.00% NO PROGRESS
F U-GIRDER CASTING BED 05-09-18 17-12-18 4.75% 0.51% 0.64% 0.13%
F-1 100 RMT 2nd BAY 05-09-18 30-11-18 1.50% 0.00% 7.14% 0.00% 0.11% 0.11%
EXCAVATION 05-09-18 25-09-18 26-10-2018 Rmt 100.00 0.00 50.00 0.00% 50.00% IN PROGRESS
SOLING 07-09-18 27-09-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 09-09-18 29-09-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 11-09-18 01-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 14-09-18 04-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 1 14-10-18 17-11-18 Nos. 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
FLOATING BEAM ASSEMBLY 18-11-18 19-11-18 Nos. 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
F-2 100 RMT 1st BAY 12-09-18 17-12-18 1.50% 34.29% 35.71% 0.51% 0.54% 0.02%
EXCAVATION 12-09-18 02-10-18 Rmt 100.00 60.00 60.00 60.00% 60.00% PROGRESS
SOLING 14-09-18 04-10-18 Rmt 100.00 60.00 60.00 60.00% 60.00% PROGRESS
PCC 16-09-18 06-10-18 05-10-2018 Rmt 100.00 100.00 100.00 100.00% 100.00% PROGRESS
RAFT 18-09-18 08-10-18 20-10-2018 Rmt 100.00 20.00 30.00 20.00% 30.00% PROGRESS
PEDESTAL 21-09-18 11-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 2 31-10-18 04-12-18 Nos 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
FLOATING BEAM ASSEMBLY 05-12-18 06-12-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
F-3 U-GIRDER STACKING BED 15-09-18 19-10-18 1.75% 0.00% 0.00% 0.00% 0.00% 0.00%
BED 1 TO 5 15-09-18 19-10-18
EXCAVATION 15-09-18 14-10-18 Rmt 405.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 17-09-18 16-10-18 Rmt 405.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 18-09-18 17-10-18 Rmt 405.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 19-09-18 18-10-18 Rmt 405.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 20-09-18 19-10-18 Rmt 405.00 0.00 0.00 0.00% 0.00% NO PROGRESS
G BAY-II (PIER CAP & I-GIRDER) 05-09-18 05-12-18 4.50% 1.13% 1.33% 0.20%
G-1 I-GIRDER 1ST LIVE END 10-10-18 01-11-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
PILING P1-1000 MM DIA 10-10-18 11-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P2-1000 MM DIA 12-10-18 13-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
EXCAVATION 15-10-18 17-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 18-10-18 21-10-18 Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 22-10-18 22-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 23-10-18 27-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 28-10-18 28-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
BULKHEAD 29-10-18 01-11-18 Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
G-2 I-GIRDER 1ST DEAD END 09-10-18 31-10-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PILING P1-1000 MM DIA 09-10-18 10-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILING P2-1000 MM DIA 11-10-18 12-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
EXCAVATION 14-10-18 16-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CHIPPING 17-10-18 20-10-18 Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 21-10-18 21-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP R/F 22-10-18 26-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PILE CAP CONCRETING 27-10-18 27-10-18 Nos 1.00 0.00 0.00 0.00% 0.00% NO PROGRESS
BULKHEAD 28-10-18 31-10-18 Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
GANTRY FOUNDATION BAY-II 05-09-18 24-10-18
G-3 RHS (250 MTR) (DOUBLE TRACK) 05-09-18 24-10-18 1.25% 53.60% 60.93% 0.67% 0.76% 0.09%
EXCAVATION 05-09-18 04-10-18 15-08-2018 Rmt 250.00 170.00 195.00 68.00% 78.00% PROGRESS
SOLING 06-09-18 07-10-18 17-08-2018 Rmt 250.00 170.00 190.00 68.00% 76.00% PROGRESS
PCC 24-09-18 08-10-18 21-08-2018 Rmt 250.00 155.00 190.00 62.00% 76.00% PROGRESS
RAFT 26-09-18 16-10-18 30-08-2018 Rmt 250.00 155.00 185.00 62.00% 74.00% PROGRESS
PEDESTAL 27-09-18 21-10-18 23-09-2018 Rmt 250.00 154.00 154.00 61.60% 61.60% PROGRESS
RAIL ALIGNMENT 30-09-18 24-10-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
G-4 LHS (250 MTR) (SINGLE TRACK) 43355 43399 1.25% 37.13% 45.47% 0.46% 0.57% 0.10%
EXCAVATION 12-09-2018 15-09-2018 Rmt 250.00 150.00 150.00 60.00% 60.00% PROGRESS
SOLING 13-09-2018 17-09-2018 Rmt 250.00 150.00 150.00 60.00% 60.00% PROGRESS
PCC 01-10-2018 28-09-2018 Rmt 250.00 130.00 130.00 52.00% 52.00% PROGRESS
RAFT 03-10-2018 03-10-2018 Rmt 250.00 127.00 127.00 50.80% 50.80% PROGRESS
PEDESTAL 04-10-2018 Rmt 250.00 0.00 125.00 0.00% 50.00% NO PROGRESS
RAIL ALIGNMENT 07-10-2018 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
H GANTRY ERECTION 30-09-18 02-10-18 2.25% 0.00% 0.00% 0.00% NO PROGRESS
GANTRY ERECTION BAY 2 30-09-18 02-10-18 Nos 1.00 0.00 0.00 0.00% 0.00%
I I-GIRDER CASTING BED 01-10-18 25-11-18 5.00% 0.00% 0.00% 0.00%
I-1 100 RMT 9 BEDS 01-10-18 25-11-18 1.50% 0.00% 0.00% 0.00% 0.00% 0.00%
EXCAVATION 01-10-18 15-10-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 02-10-18 16-10-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 03-10-18 17-10-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-10-18 19-10-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-10-18 20-10-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 1 04-11-18 23-11-18 Nos 9.00 0.00 0.00 0.00% 0.00% NO PROGRESS
FLOATING BEAM ASSEMBLY 24-11-18 25-11-18 Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
I-2 PIER CAP CASTING BED 10-10-18 20-11-18 1.50% 0.00% 0.00% 0.00% 0.00% 0.00%
100 RMT 3 BED 10-10-18 20-11-18
EXCAVATION 10-10-18 24-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 11-10-18 25-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 12-10-18 26-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 14-10-18 28-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 15-10-18 29-10-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 2 01-11-18 20-11-18 Nos 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
I-3 I-GIRDER STACKING BED 01-11-18 05-12-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
BED 1 TO 5 01-11-18 05-12-18
EXCAVATION 01-11-18 30-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 03-11-18 02-12-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 04-11-18 03-12-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-11-18 04-12-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-11-18 05-12-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
I-4 PIER CAP STACKING BED 01-11-18 29-11-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
BED 1 TO 3 01-11-18 29-11-18
EXCAVATION 01-11-18 24-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 03-11-18 26-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
PCC 04-11-18 27-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-11-18 28-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-11-18 29-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
J BAY-III (STATION BEAMS & I-GIRDER) 15-10-18 29-12-18 10.00% 0.00% 0.04% 0.04%
GANTRY FOUNDATION FOR BAY-III (STATION BEAMS &
15-10-18 26-11-18
I-GIRDER)
J-1 LHS (250 MTR) (SINGLE TRACK) 15-10-18 25-11-18 1.25% 0.00% 3.33% 0.00% 0.04% 0.04%
EXCAVATION 15-10-18 28-10-18 26-10-2018 Rmt 250.00 0.00 50.00 0.00% 20.00% In Progress
SOLING 16-10-18 31-10-18 Rmt 250.00 0.00 0.00 0.00% 0.00% In Progress
PCC 21-10-18 04-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 23-10-18 21-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 24-10-18 22-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAIL ALIGNMENT 27-10-18 25-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
J-2 RHS (250 MTR) (SINGLE TRACK) 22-10-18 26-11-18 1.25% 0.00% 0.00% 0.00% 0.00% 0.00%
EXCAVATION 22-10-18 04-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 23-10-18 07-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 25-10-18 08-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 27-10-18 25-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 28-10-18 26-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAIL ALIGNMENT 01-11-18 15-11-18 Rmt 250.00 0.00 0.00 0.00% 0.00%
J-3 GANTRY ERECTION 06-11-18 08-11-18 3.00% 0.00% 0.00% 0.00% 0.00% 0.00% NO PROGRESS
GANTRY ERECTION BAY 3 (100 T 2 NOS.) 06-11-18 08-11-18 Nos 2.00 0.00 0.00 0.00% 0.00%
J-4 I-GIRDER CASTING BED 01-11-18 12-12-18 1.25% 0.00% 0.00% 0.00% 0.00% 0.00%
100 RMT 9 BEDS 01-11-18 12-12-18
EXCAVATION 01-11-18 15-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 02-11-18 16-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 03-11-18 17-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-11-18 19-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-11-18 20-11-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 1 23-11-18 12-12-18 Nos 9.00 0.00 0.00 0.00% 0.00% NO PROGRESS
J-5 STATION BEAM CASTING BED 01-11-18 12-12-18 1.25% 0.00% 0.00% 0.00% 0.00% 0.00%
100 RMT 3 BED 01-11-18 12-12-18
EXCAVATION 01-11-18 15-11-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 02-11-18 16-11-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 03-11-18 17-11-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-11-18 19-11-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-11-18 20-11-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
ERECTION OF FORMWORK - BED 2 23-11-18 12-12-18 Nos 3.00 0.00 0.00 0.00% 0.00% NO PROGRESS
J-6 BAY-III (I-GIRDER) CASTING & STACKING BED 15-11-18 19-12-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
BED 1 TO 5 15-11-18 19-12-18
EXCAVATION 15-11-18 14-12-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 17-11-18 16-12-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 18-11-18 17-12-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 19-11-18 18-12-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 20-11-18 19-12-18 Rmt 300.00 0.00 0.00 0.00% 0.00% NO PROGRESS
J-7 BAY-III (STATION BEAMS)CASTING & STACKINGBED 01-12-18 29-12-18 1.00% 0.00% 0.00% 0.00% 0.00% 0.00%
BED 1 TO 3 01-12-18 29-12-18
EXCAVATION 01-12-18 24-12-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
SOLING 03-12-18 26-12-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PCC 04-12-18 27-12-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
RAFT 05-12-18 28-12-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS
PEDESTAL 06-12-18 29-12-18 Rmt 100.00 0.00 0.00 0.00% 0.00% NO PROGRESS

K FORMWORK FABRICATION 49.00% 0.00% 0.00% 0.00%


K-1 U GIRDER VIADUCT 25M & 28M 20.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INNER FORMWORK Nos 3.00 0.00 0.00 0.00% 0.00% PROGRESS Material order Placed for fabrication
OUTER FORMWORK Nos 3.00 0.00 0.00 0.00% 0.00% PROGRESS Material order Placed for fabrication

K-2 U GIRDER STATION 17M 12.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INNER FORMWORK Nos 5.00 0.00 0.00 0.00% 0.00% PROGRESS
OUTER FORMWORK Nos 3.00 0.00 0.00 0.00% 0.00% PROGRESS Material order Placed for fabrication
Cumulative Cumulative Cum. % Cum. % Weighted Weighted Weekly
Planned Actual
Sr.No. Task Name Unit Scope Qty. Qty on Qty on Achieved Achieved percentage percentage Weighted Work Progress Remarks
Start Finish Start Finish 21.10.2018 28.10.2018 21.10.2018 28.10.2018 21.10.2018 28.10.2018 percentage
K-3 I GIRDER 8.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FORMWORK REQUIRED SPAN Nos 6.00 0.00 0.00 0.00% 0.00% NO PROGRESS

K-5 PIER CAP 9.00% 0.00% 0.00% 0.00% 0.00% 0.00%


I GIRDER PIER CAP Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS
U GIRDER PIER CAP Nos 2.00 0.00 0.00 0.00% 0.00% NO PROGRESS

L QUALITY LAB 01-09-18 21-09-18 0.25% 10.00% 0.00% 0.03% 0.03% IN PROGRESS Completed Upto Plinth Level
QUALITY LAB 01-09-18 21-09-18 Nos 1.00 0.00 0.10 0.00% 10.00%
M STORE 01-09-18 15-09-18 0.25% 10.00% 0.00% 0.03% 0.03% IN PROGRESS Completed Upto Plinth Level
STORE 01-09-18 15-09-18 Nos 1.00 0.00 0.10 0.00% 10.00%
N OFFICE BUILDING 16-09-18 30-09-18 0.75% 0.00% 0.00% 0.00% 0.00% IN PROGRESS Completed Upto Plinth Level
OFFICE BUILDING 16-09-18 30-09-18 Nos 1.00 0.00 0.00 0.00% 0.00%
O LABOUR CAMP 01-09-18 30-09-18 0.50% 0.00% 0.00% 0.00% 0.00% NO PROGRESS
LABOUR CAMP 01-09-18 30-09-18 Nos 1.00 0.00 0.00 0.00% 0.00%
P SAFETY ROOM 16-09-18 22-09-18 0.25% 0.00% 0.00% 0.00% 0.00% NO PROGRESS
SAFETY ROOM 16-09-18 22-09-18 Nos 1.00 0.00 0.00 0.00% 0.00%
Q CANTEEN 01-09-18 01-09-18 0.00% 0.00% 0.00% 0.00% 0.00% NO PROGRESS
CANTEEN 01-09-18 01-09-18 Nos 1.00 0.00 0.00 0.00% 0.00%