Cipto LP - Schedule Alat Berat

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 8

PROYEK TOL LAMPUNG

MULTI - ACSET KSO

SCHEDULE ALAT BERAT

ON
NO PEKERJAAN / JENIS ALAT TYPE SAT KEBUTUHAN
SITE

1 CLEARING - GRABING - CUTTING

1.1 ZONA 1 : Sta. 30+600 s/d 32+800


- Excavator PC - 200 UNIT 1 1
- Dozer D - 68 UNIT 1 0

1.2 ZONA 2 : Sta. 29+700 s/d 30+600


- Excavator PC - 200 UNIT 1 1
- Dozer D-7 UNIT 1 1

1.3 ZONA 3 : Sta. 27+800 s/d 29+700


- Excavator PC - 200 UNIT 1 0
- Dozer D-8 UNIT 1 0

2 TIMBUNAN COMMON & SELECTED

2.1 ZONA 1 : Sta. 30+600 s/d 32+800


2 Team
- Dozer D - 68 UNIT 2 1
- Vibro Drum 8 - 12 Ton UNIT 2 2
- Vibro Sheep Foot 8 - 12 Ton UNIT 2 0
- Grader ………….. UNIT 1 0

2.2 ZONA 2 : Sta. 29+700 s/d 30+600


1 Team
- Dozer D-8 UNIT 1 0
- Vibro Drum 8 - 12 Ton UNIT 1 0
- Vibro Sheep Foot 8 - 12 Ton UNIT 1 0
- Grader ………….. UNIT 1 0

2.3 ZONA 3 : Sta. 27+800 s/d 29+700


2 Team
- Dozer D-8 UNIT 2 0
- Vibro Drum 8 - 12 Ton UNIT 2 0
- Vibro Sheep Foot 8 - 12 Ton UNIT 2 0
- Grader ………….. UNIT 1 0

3 QUARY MATERIAL TANAH MERAH

3.1 A. AREA JALAN LINTAS ( kantor PDI )


- Excavator PC - 200 UNIT 1 0
- Dump Truck / Tronton > 20 m3 UNIT 15 0

3.2 B. STA. 35+900


- Excavator PC - 200 UNIT 1 0
- Dump Truck / Tronton > 20 m3 UNIT 8 0
3.3 C. STA. 29+800 - 30+200
- Excavator PC - 200 UNIT 2 0
- Dump Truck / Tronton > 20 m3 UNIT 12 0

3.4 D. STA. 27+900 - 28+500


- Excavator PC - 200 UNIT 2 0
- Dump Truck / Tronton > 20 m3 UNIT 12 0

3.5 E. STA. 26+800 ( - 1 )


- Excavator PC - 200 UNIT 2 2
- Dump Truck / Tronton > 7 m3 UNIT 14 14

3.6 F. STA. 27+800 + 2 : EX WASCO


- Excavator PC - 200 UNIT 1 0
- Dump Truck / Tronton > 20 m3 UNIT 12 0

3.7 G. STA. 27+800 + 2 : GAJAH TUNGGAL


- Excavator PC - 200 UNIT 2 0
- Dump Truck / Tronton > 20 m3 UNIT 18 0
20/06/2017
SCHEDULE
KEKURANGAN
KEDATANGAN

1 On Site
1 4-7-2017

0 On Site
0 On Site

1 15-7-2017
1 15-7-2017

1 On Site
0 On Site
2 9-7-2017
1 28-8-2017

1 9-7-2017
1 9-7-2017
1 23-7-2017
1 4-9-2017

2 30-7-2017
2 30-7-2017
2 6-8-2017
1 4-9-2017

1 30-7-2017
15 30-7-2017

1 9-7-2017
8 9-7-2017
2 12-7-2017
12 12-7-2017

2 30-7-2017
12 30-7-2017

0 By Subcon
0 By Subcon

1 5-7-2017
12 5-7-2017

2 ???
18 ???
PROYEK TOL LAMPUNG
MULTI - ACSET KSO

SCHEDULE PEKERJAAN TIMBUNAN

RENCANA TARGET PENGIRIMAN TANAH ( M3 )


NO URAIAN SAT EST. QTY TARGET SISA VOL JULI 2017 AGUSTUS 2017 SEPTEM
PER DAY 22-6-2017 3-9 10 - 16 17 - 23 24 - 30 31 - 6 7 - 13 14 - 20 21 - 27 28 - 3 4 - 10

I ZONA : 1
Sta. 30+600 - 32+800

1 Clearing Grabing m2 108,000 4,000 42,000 24,000 18,000


2 Cutting Tambahan m3 25,150 1,170 13,470 7,020 6,450
3 Selected Embankment m3 25,150 750 17,150 5,250 5,250 5,250 1,400
4 Common Embankment m3 313,000 4,000 311,705 3,000 14,000 28,000 28,000 28,000 28,000 28,000 28,000 28,000 28,000

II ZONA : 2
Sta. 29+700 - 30+600

1 Clearing Grabing m2 54,000 3,000 48,000 9,000 9,000 15,000 15,000


2 Cutting Tambahan m3 14,400 1,170 13,500 6,750 6,750
3 Selected Embankment m3 14,400 850 14,400 1,700 5,950 5,950 800 1,700 5,950 5,950 800
4 Common Embankment m3 235,400 3,000 235,400 7,000 9,000 21,000 21,000 21,000 21,000 21,000 21,000

III ZONA : 3
Sta. 27+800 - 29+700

1 Clearing Grabing m2 114,000 3,000 114,000 21,000 21,000 21,000 21,000 21,000 9,000
2 Cutting Tambahan m3 38,400 1,350 38,400 6,750 9,450 9,450 9,450 3,300
3 Selected Embankment m3 38,400 1,250 38,400 6,750 9,450 9,450 9,450 3,300
4 Common Embankment m3 210,000 3,000 210,000 21,000 21,000 21,000 21,000 21,000 21,000
RENCANA TARGET PENGIRIMAN TANAH ( M3 )
SEPTEMBER 2017 OKTOBER 2017
11 - 17 18 - 24 25 - 1 2-8 9 - 15

28,000 28,000 14,705

21,000 21,000 31,500 19,900

21,000 21,000 21,000 21,000