Kaizen Sheet company /

Location MM / YY SL No
Productivity Quality Delivery Cost Safety Material Energy Morale Vizag 7/11/2018

Kaizen Title : jd 619 approach platform modification done Implemented Area: ROCK GRINDING
Implemented By: G srinivaa rao

Result/Benefit: JD 619 North side walk way plaatform has extended 6


mtrs as it will be helpful in replacement of rollers and frames
near/next to existing platform. Prevoiusly scaffoding has planned
temporarely when ever there is replacement.Now permanent
Problem/Present Status: Before Improvement: solution has done by extending the plafrom up to bottom level.
a. Qualitative

Jd 619 conveyor north side approach platform was not in condition. As


seen in pic the bottom portion supports & platform were corroded
badly . b. Quantitative
MODIFICATION :-Present platform has corrded badly and there is need in
extension of platform up to bottom level, whenever frames or rollers ( Pictorial Representation)
planned for renewal in this area , temporary scaffolding to be planned
and job has to be attended. By removing the present plaform and
extending the platform to bottom level this problem will be solved
premanently.

Real Root Cause Identification: After Improvement:

Standardization

Root cause Howmany places this kaizen can been deployed horizontally & Total benefits:
Idea to eliminate root cause
Countermeasure

Team/Individual Name : 1.. G.SRINIVASA RAO (ASST.MAN) Approved by Name Signature


sectionHead K.SRIDHAR
kaizen Champion
Finance head