Project Design Documentation Check List Instructions

This is a draft document for use on Design-Build projects. As WSDOT works through Design-Build projects areas will be completed or revised as needed.
Project team input on the development and use of this document is critical for it to be a useful tool on projects.
The check list includes all the documentation required by the Design Manual for Design-Build Projects for both the
Design Documentation Package (DDP) and the Project File (PF).
The DDP is a permanent record of the design documents and decisions. It is submitted to the region for approval and archived for 75+ years.
The Project File is kept in the Project Office and contains all documentation and data (such as quantity calcs, reports, correspondence) required for the
project.

The check list is based on the Design Manual for Design_Build Projects documentation requirements.
The purpose of the checklist is to ensure that all applicable design elements are properly addessed in the project.
It will also assist reviewers or other designers in locating information and determining what design decisions have been made.
This check list will be used for Process and Stewardship reviews.

Some chapters have supplemental check lists either for documentation requirements (3) or design parameters (3). Each supplemental chapter checklist
can be accessed by clicking on the notation provided. Chapters with supplemental documentation requirement check lists are 210, 240, and 1300.
Regions have developed the supplemental design parameter check lists for the specialty projects covered in Chapters 915, 1020, and 1060.

Description - The Project Design Check List is organized to match the Design Manual for Design-Build Projects Chapters.
Reference - This column gives the Design Manual for Design-Build Projects chapter or resources to refer to for criteria or requirements.
Status - Review all items, referring to the appropriate matrix to determine whether the item is applicable for the project. Enter date, "completed" or "NA"
for each item. If all the items in a chapter or division are not applicable, it can be hidden by pressing the "-" button on the left side-and then enter
NA in the heading.
When and By Whom - Identifies at what phase and who is responsible for documentation
Remarks - List where the information can be found in the Design Documentation Package (DDP) or Project File (PF).

The shaded chapters are areas that the check list can be used as the
documentation, when using this option include the checklist in the DDP
DESIGN ELEMENT - Items that relate to the matrix columns
DESIGN MANUAL Reference - The chapter or figure in the Design Manual that establishes the criteria for this design element.
MATRIX REQUIREMENT - Enter the design level from the appropriate matrix (F, M, B, EU/M, etc.)
EXISTING/STANDARD/DETERMINATION - List the design criteria/describe the existing condition/list what the project will provide.

To use this file, download it to your PC or local server.


Prepare and print an applicable set of documentation for each project in progress.

Revised May, 2004


Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Div. 2 - Hearings, Environ., & Permits


Public Involvement and
210
Hearings
Pre-RFP WSDOT
PF Public and/or other agency input 210
Contract DB DB responsible for any changes to configuration

for Plans, affidavits, and access report Pre-RFP WSDOT


PF 210
go to Contract DB DB responsible for any changes to configuration

Pre-RFP WSDOT
PF Public Involvement Plan 210.04
Contract DB/WSDOT
210.04(1) &
PF Study Plan Pre-RFP WSDOT
220.04(5)
PF Notice of Opportunity for a hearing 210.05(4) Pre-RFP WSDOT
Affidavit of Publication of access
PF 210.05(4) Pre-RFP WSDOT
hearing notice
DDP Access Hearing plans 210.05(5) Pre-RFP WSDOT

DDP Hearing Summary 210.05(6) Pre-RFP WSDOT

DDP Environmental hearing summary 210.06 Pre-RFP WSDOT


Justification to abandon an existing
DDP 210.07 Pre-RFP WSDOT
corridor
DDP Corridor hearing summary 210.07 Pre-RFP WSDOT

DDP Design hearing summary 210.08(1) Pre-RFP WSDOT

DDP Access Hearing Plan 210.09(3) Pre-RFP WSDOT

PF Affidavit of Service by Mailing 210.09(3) Pre-RFP WSDOT

DDP Findings and Order Plan 210.09(11) Pre-RFP WSDOT

Project Environmental
220
Documentation
Pre-RFP WSDOT
PF Commitment file 220.10
Contract DB DB responsible to update file for any modifications

Environmental
DDP NEPA Documentation Procedures
Manual
Environmental
DDP SEPA Documentation Procedures
Manual
220.07 &
Environmental
DDP Categorical Exclusion Documentation
Procedures
Manual
Environmental
Environmental Assessment
DDP Procedures
Documentation
Manual

Permits and Approvals from


240
Other Governmental Agencies

Pre-RFP WSDOT
for permits and approvals go to 240
Contract DB DB responsible to update file for any modifications

Figures 240-1a &


PF SEPA Approval
240-7a

Corps of Engineers - Section 404


PF Figure 240-1a
Individual Permits

Corps of Engineers Section 404


PF Figure 240-1a
Nationwide Permit
DDP Water Quality 401 Certification Figure 240-1a
Coastal Zone Management (CZM)
PF Figure 240-1a
Certification

PF Coast Guard Section 9 Bridge Permit Figure 240-1a

PF Corps of Engineers Section 10 Permit Figure 240-1a

Threatened and Endangered Species - Figures 240-1a &


DDP
USFWS/NMFS 240-7a
Historic Preservations Act - Section Figures 240-1b &
DDP
106 240-7c
Land and Water Conservations Act -
DDP Figure 240-1b
Section 6(f)
U.S. Dept of Transportation Act -
DDP Figure 240-1b
Section 4(f)
DDP Wild and Scenic Rivers Figure 240-1b Only if water quality permits are necessary
PF Farmland Conversion Figure 240-1b
PF Airport/Highway Clearance Figure 240-1b
NPDES Municipal Stormwater Figures 240-1b &
DDP
Discharge General Permit 240-7b
NPDES Stormwater Construction
PF Figure 240-1b
Permit
August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
NPDES Sand and Gravel General
DDP Figure 240-1b
Permit

DDP NPDES Stormwater Industrial Permit Figure 240-1b

PF Underground Injection Control Figure 240-1b


PF Hazardous Waste Tracking Form Figure 240-1c

Water Quality Permit. Use of


DDP Herbicides to control Noxious Weed on Figure 240-1c
WSDOT Properties and Projects.

Administrative Order # DE99WQ-003.


WSDOT. Use of Herbicides to Control
DDP Figure 240-1c
Non-noxious Weeds on WSDOT
Properties and Projects.
PF Water Right Permit Figure 240-1c
Figures 240-1c &
DDP State Waste Discharge (SWD) Permit
240-7b
DDP Water System Project Approvals Figure 240-1c
PF Hydraulic Project Approval (HPA) Figure 240-1c
Fish Habitat Enhancement Project
PF Figure 240-1d
Application
Figures 240-1d &
PF Aquatic Resource Use Authorization
240-7b
Figures 240-1d &
DDP Easements
240-7b
PF Monument Removal Figure 240-1d

DDP Operating Permit for Surface Mining Figure 240-1d

PF Forest Practices Application Figure 240-1d


Shoreline Substantial Development
DDP Figure 240-1d
Permit
DDP Flood Plain Development Permit Figure 240-1d
DDP Critical Areas Ordinance Figure 240-1d

PF Clearing, Grading and Building Permits Figure 240-1e

PF Temporary Air Pollution Figure 240-1e


PF New Source Construction Figure 240-1e
PF Noise Variance Figure 240-1e
Archaeological Resources Protection
DDP Figure 240-1e
Permit

DDP Bridge Scour Countermeasures 240.03

Div. 3 - Project Documentation


Value Engineering 315
Value Engineering Study Final Report
PF 315 Contract DB
and Workbook

PF Value Engineering Decision Document 315.04(2) Contract DB

Design Matrix Procedures 325

325.03(2) & Pre-RFP WSDOT Guidance to be included in the RFP


Use of a design element not covered in
DDP Figs. 325-3
the Design Manual
through 325-7 Contract DB

Pre-RFP WSDOT
DDP Design Exceptions 325.03(4)
Proposal DB P/F and then technical score

Pre-RFP WSDOT
DDP Evaluate Upgrade documentation 325.03(4)
Proposal DB P/F and then technical score

Pre-RFP WSDOT Include in RFP

DDP Approved deviations 325.03(4) Proposal DB Approved deviations included in proposal

Contract DB Would require contract change


325.03(5) &
Corridor or project analysis for change
DDP Figs. 325-5 RFP WSDOT
in design level
through 325-7
Risk project solutions based on B/C 325.03(5) &
DDP ratios - analyses, design decisions and Figs. 325-5 RFP WSDOT
program funding decisions through 325-7
Address Sidewalk Ramps for ADA
PF Figure 325-7 RFP WSDOT
compliance

Design Documentation,
330
Approval, and Process Review
60% - Design File done to an acceptable stage for
All Projects including operational RFP WSDOT
completing R/W and Access processes
changes and developer projects. All
DDP/PF 330.01
participants must provide appropriate
documentation for their decisions. Contract DB 40% - Complete balance of Design File

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Project Summary: Project Definition, 330.03, RFP WSDOT


DDP Design Decisions Summary, 330.06(1)(a),(b),
Environmental Review Summary (c)& Fig. 330-5 Contract DB

330.03,
Design Exception (DE), Evaluate RFP WSDOT
330.04,330.06,
DDP Upgrade (EU), Design Variance, DVI,
Figures 330-5
Deviation, Project Control Form Contract DB
through 330-7

Blank cell in design matrix which may RFP WSDOT


be included in the project in special 330.04(4) & Figure
DDP No blank cells in Interstate matrix
cases, if identified in the Project 330-1
Summary or Project Control Form Contract DB

Cell entry F, M, or B with no DE or EU RFP WSDOT


qualifiers and project does not correct
DDP Figure 330-1
design element/s to specified design
level Contract DB

330.04(4) & Figure RFP WSDOT 90%


DDP Deviation requests & approval
330-2a & b
Contract DB

Change in design level resulting from


an approved Route Development Plan
DDP 330.04(4)
or corridor or project analysis
documented as an EU or a deviation

330.05, &
DDP SEPA and NEPA Documentation RFP WSDOT Final
Figure 330-5

RFP WSDOT 90%


DDP Accident Analysis Figure 330-5
Contract DB

RFP WSDOT 90%


DDP Traffic Projections & Analysis Figure 330-5
Contract DB
Work Zone Transportation RFP WSDOT
Figure 330-3b,
PF Management Plan / Traffic Control
Chapter 810 Contract DB
Plan

Figure 330-5, RFP WSDOT Draft


PF Work Zone Traffic Control Strategy
Chapter 810
Contract DB

RFP WSDOT 90% - Early notification to utilities is necessary


DDP Design Clear Zone Inventory Figure 330-5
Contract DB

330.08 & RFP WSDOT 15% - 30%


DDP Cost Estimate to complete project
Figure 330-5 Contract DB

Interchange Plans, profiles, roadway Figure 330-5, RFP WSDOT 30%


DDP
sections 940.09
Contract DB

DDP R/W Plans Figure 330-5 RFP WSDOT Final

Record of Survey or Monumentation RFP WSDOT Done with R/W Plans


DDP Figure 330-5
Map Contract DB

DDP Corridor or project analysis Figure 330-5 RFP WSDOT Final

Figure 330-3a & RFP WSDOT 30% - To level needed to determine R/W footprint
DDP Intersection Plans
910.13(2)
Contract DB

FHWA determination for any new or RFP WSDOT 90%


revised access point (including
330.07 &
DDP interchanges, temp access breaks,
Chapter 1425
and locked gate access) on interstate Contract DB
system

DDP Cultural & Historical Review Environmental RFP WSDOT Final

Figure 330-5 &


DDP Interchange Justification Report RFP WSDOT Final
Chapter 1425
Decisions to differ from WSDOT RFP WSDOT 15% - 30%
DDP Figure 330-5
design guidance Contract DB

Decisions for project components for RFP WSDOT 90%


DDP which there is no WSDOT design Figure 330-5
guidance. Contract DB 10% - Temporary access breaks for construction

Figure 330-4
PF Items on Figure 330-4 Specifying Contract DB PS&E items
Note 4

DDP Design Criteria Worksheets 330.08

DDP Design Approval 330.08

Final Design Documentation


DDP 330.09
Acceptance

Div. 4 - Project Design Criteria

Full Design Level 440


August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
DESIGN
CLASS:
DESIGN MANUAL Design
DESIGN ELEMENT EXISTING STANDARD
REFERENCE Level

DDP Terrain Classification 440.05

440.07, Figure
Design Speed selection - Corridor
440-1 and
DDP Analysis required for use of
Figures 440-4
minimum design speed
through 440-8
440.08 & Figures
DDP Lane width 440-4 though RFP WSDOT
440-8
440.09, Figs
440-2, 440-3 and
DDP Shoulder width RFP WSDOT
440-4 through
440-8
440.10 and
DDP Median width Figures 440-4 RFP WSDOT
through 440-8
440.13 & Figures
DDP Pavement Type Determination 440-4 through
440-8
440.14 & Figures
DDP Structure lane & shoulder widths 440-4 through RFP WSDOT
440-8

440.15 & Figures


DDP Right of Way
440-4 through 7b

440.16 & Figures


DDP Grades
440-4 through 7b

Maintenance office requests a


DDP shoulder width different than for the 440.09
design class - justification for
At existing bridge piers and abutments,
shoulders less than full width to a
DDP 440.09
minimum of 2 ft may be used with
design exception
Evaluation of curb grinding to maintain
PF 440.11(1)
curb height
Maintenance Superintendent's
PF approval for use of curbing in areas of 440.11(1)
heavy snowfall

Justification for use of curb when


DDP 440.11(2)
posted speed is greater than 40 mph

Angle Parking on state route, requires


an engineering study approved by the
DDP 440.12
Region Traffic Engineer with final
approval by the State Traffic Engineer

Design Exception Documentation -


existing 6 lane roadway for existing 6 ft
Figures 440-4
DDP shoulders remaining when they are not
through 440-6b
being reconstructed or no other
widening is required.

Justify the selection of a P-6 design Figures 440-5a &


DDP
class on limited access highway 5b

When considering truck climbing lanes


on a design class highway, perform an Figures 440-5a
DDP
investigation to determine if a higher through 7b
class highway is justified or vice versa

Justification for Railroad Grade Figures 440-5a


DDP
Separations through 8
Justification for Design Speeds greater Figures 440-5a
DDP
than shown figures through 7b
Justification for 11 ft lanes on Urban
DDP Figure 440-8
Managed Access Highways

Div. 5 - Soils and Paving


Soils, Rock, & Surfacing
510
Materials
510.03 & Materials
PF Materials Source Report & Approvals Contract DB
Lab
PF Permits and agreements 510.04(4) RFP WSDOT Only necessary when State supplies source
PF Plan sheets 510.04(4)(b) Contract DB
PF Right of Entry to start investigation 510.04(4)(d) Contract DB
Materials Lab & RFP WSDOT Draft
DDP Surfacing Report
510.07 Contract DB
Final Geotechnical Report with boring RFP WSDOT Draft
HQ Materials Lab
DDP/PF logs and summary of geotechnical
& 510.08(2)
conditions Contract DB
Materials Lab and RFP WSDOT Draft
Pavement Determination/Life Cycle
PF HQ Pavement
August 2006 Cost Analysis - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Determination
Type
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION
Pavement Determination/Life Cycle
REFERENCE
Materials Lab and WHEN BY WHOM Status REMARKS
PF HQ Pavement
Cost Analysis Contract DB
Type

Geosynthetics 530
Characteristics of chosen geosynthetic
PF (AOS, permittivity, load-strain, 530.04 Contract DB
survivability)
Soil Information (Geotechnical Report
PF will satisfy this documentation 530.05 Contract DB
requirement.)
PF Erosion Control/Silt Fence Plan 530.05(6) Contract DB

Div. 6 - Geometrics
Traffic Analysis 610
610, Highway
DDP/PF Capacity analysis Final - Needed for Chan. Plan to determine R/W footprint
Capacity Manual

DDP Traffic Analysis 610.06

DDP TIA Report 610.12 Final - Needed for Chan. Plan to determine R/W footprint

Geometric Plan Elements 620


DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
RFP WSDOT 15%
DDP Horizontal curve radii 620.04(2)
Contract DB
RFP WSDOT 15%
DDP Lane transitions (tapers) 620.07(1)
Contract DB
RFP WSDOT 15%
DDP Median width transitions 620.07(2)
Contract DB
620.04(1) RFP WSDOT 15%
DDP Horizontal alignment justification
630.07 Contract DB
RFP WSDOT 15%
DDP Frontage road justification 620.05(2) 620.08
Contract DB
620.06(1)&(2) RFP WSDOT 15%
DDP Number of lanes justification
620.08 Contract DB
RFP WSDOT 15%
DDP Realignment 620.08
Contract DB

Geometric Profile Elements 630


DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
RFP WSDOT 15%
DDP Minimum length of vertical curves 630.03(2)
Contract DB
RFP WSDOT 15%
DDP Maximum grade 630.03(3)
Contract DB
RFP WSDOT 15%
DDP Minimum grade 630.03(4)
Contract DB
RFP WSDOT 15%
DDP Length of grade 630.03(5)
Contract DB
Sag vertical curve having a length less RFP WSDOT 15%
DDP than required for stopping sight 630.03(2)
distance Contract DB
RFP WSDOT 15%
DDP Alignment on structures analysis 630.03(6)
Contract DB
630.07 & RFP WSDOT 15%
DDP Vertical alignment modification
620.04(1) Contract DB
RFP WSDOT 15%
DDP Procedures 630.07
Contract DB

Geometric Cross Section 640


DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL

Justification for cross slopes other than RFP WSDOT 15%


DDP 640.04(1)
2% on tangents Contract DB
RFP WSDOT 15%
Justification for shoulder cross slopes
DDP 640.04(3)
different than the adjacent lane Contract DB

DDP Cut slope selection 640.07(1)

DDP Fill slope selection 640.07(1)


Economic comparison of wide to
PF narrow median where land is 640.05(2)
expensive
Justification for using steeper fill slopes
PF than shown in the tables when traffic 640.06(1)
barrier is installed.
Documentation of the reasons for
PF 640.06(1)
modifying an existing cut slope
Engineering study and
PF 640.06(2)
recommendations for rock cuts

Materials Engineer recommendation


PF 640.06(3)
for stepped slopes

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Materials Engineer recommendation


PF 640.06(4)
for ditch location at the toe of fill.

HQ Bridge and
PF Bridge end slopes
Structures

Turning Roadways 641


Use of minimum width on two-lane
DDP 641.04(1)
two-way turning roadways
Use of minimum width on two-lane
DDP 641.04(2)
one-way turning roadways
Use of minimum width on one-lane
DDP 641.04(3)
turning roadways

Superelevation 642
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
Documentation of superelevation RFP WSDOT
maximum rate being used and
DDP 642.04
justification for a rate other than 10%
maximum Contract DB

Low-Speed Urban Managed Access 642.05 and Figure RFP WSDOT


DDP
Highway Superelevation 642-4 Contract DB
RFP WSDOT
DDP Superelevation on existing curves 642.06
Contract DB
Superelevation for Turning Movements 642.07 & Figure RFP WSDOT
DDP
at Intersections 642-4 Contract DB
642.08 & Figures RFP WSDOT
Superelevation Runoff for Highway
DDP 642-5a through
Curves
642-5d Contract DB
642.09 & Figs. RFP WSDOT
Superelevation Runoff for Ramp
DDP 642-5a through
Curves Contract DB
642-6b
Justification for superelevation of
ramps in urban area with design speed
DDP 642.04
of 40 mph or less as an urban
managed access highway

Sight Distance 650


DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
650.04, Figures:
DDP Stopping sight distance 650-1 thru 5, &
650-11 &12

650.04(5), Figures RFP WSDOT


DDP Horizontal stopping sight distance 650-6, 650-7, and
650-13a Contract DB

650.07, Figures RFP WSDOT 15%


650-4, 650-5, 650-
DDP Existing Stopping Sight Distance
7, 650-8, and 650-
13b, Chapter 630 Contract DB

650.05, Figure RFP WSDOT


DDP Passing sight distance 650-7, 650-9, and
650-14 Contract DB

Justification for increase in object 650.04(1), RFP WSDOT 15%


DDP height to 2.00 ft. in urban design areas 650.04(3) and
(vertical and horizontal curves) 650.04(5) Contract DB
650.06, Figures RFP WSDOT 15%
DDP Decision sight distance 650-4, 650-5, 650-
7, and 650-10 Contract DB

Div. 7 - Roadside Safety Elements


Roadside Safety 700
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
Design Clear Zone inventory, RFP WSDOT Draft
DDP evaluation documents and justification 700.04(1)
for design decision. Contract DB

Evaluation of medians and roadside RFP WSDOT


700.04(1) & Figure
DDP clear zones in an urban environment
700-1
but outside of an incorporated city Contract DB

RFP WSDOT Draft


Design Clear Zone establish by city -
DDP 700.04(2)
managed access state highways
Contract DB
Median accident evaluation and barrier
DDP 700.06 RFP WSDOT Final
warrant determination
Median width deviation for barrier
DDP 700.06 RFP WSDOT Final
placement
Evaluation of potential hazards beyond RFP WSDOT Draft
DDP 700.04(1)
the Design Clear Zone Contract DB
Formalized agreement on
responsibility with city/county in
urbanized areas adjacent to RFP WSDOT
incorporated cities and towns 700.04(1),
DDP
Justification for the design decision to 700.04(2)
be included as part of the project or
August 2006 corridor analysis
Determination (roadside
- MS: and
Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
median)
Proj.
Project Title:
No.
Draft - DESIGN-BUILD
Formalized agreement on PROJECT DESIGN DOCUMENTATION CHECK LIST
responsibility with city/county in
Location urbanized areas adjacent to
DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
incorporated cities and towns 700.04(1),
DDP
Justification for the design decision to 700.04(2)
be included as part of the project or Contract DB
corridor analysis (roadside and
median)
Justification for barrier use not meeting RFP WSDOT
DDP 700.05
criteria in 700.05 Contract DB
700.05(1), Figure
700-5 and RFP WSDOT Draft
DDP Evaluation of slopes
Chapters 430 and Contract DB
640
RFP WSDOT Draft
700.05(2)(a)
DDP Evaluation of Fixed Objects
through (h)
Contract DB
RFP WSDOT Draft
DDP Hydraulic evaluation for culvert bars 700.05(2)c
Contract DB
RFP WSDOT Draft
DDP Evaluation of Water Depth 700.05(3)
Contract DB
Median evaluation for potential errant RFP WSDOT
DDP 700.06
crossover movements Contract DB
DDP Rumble Strips 700.07 Contract DB
RFP WSDOT Draft
DDP Glare screen justification 700.07(2)
Contract DB

Traffic Barriers 710


DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
710.04(1),
DDP Barrier terminal selection 710.06(2), Contract DB
710.08(2)
710.04(1),
DDP Transition & Connection selection 710.06(3) & Figs. Contract DB
710-6 & 710-10
RFP WSDOT 15%
DDP Standard Run of Barrier - height 710.04(2)
Contract DB
Bridge rail evaluation and upgrade RFP WSDOT 15%
DDP 710.04(4)
method Contract DB
RFP WSDOT 15%
DDP Shy distance requirements 710.05(1)
Contract DB
710.05(2) & Figure
PF Barrier Deflection Contract DB
710-2
710.05(3) & Figure
PF Flare Rate Contract DB
710-3
710.05(4) & Figs. RFP WSDOT 15%
DDP Barrier length of need calculation
710-11(a)-(c) Contract DB
Long guardrail post justification or 710.06(1) & Figure
DDP Contract DB
approved deviation 710-12
DDP Remove barrier not needed 710.04 Contract DB
PF Barrier selection 710.05 RFP WSDOT
Justification for median barrier RFP WSDOT 15%
DDP placement closer than 15' in medians 710.05(5)
wider than 30' Contract DB

Assessment of concrete barrier 710.08(3) & RFP WSDOT 15%


PF
placement impact to wildlife Figure 710-8 Contract DB
Approved public interest finding for use
PF of a sole source proprietary traffic 710.09 Contract DB
barrier
Retrofitting with new concrete bridge
PF 710.10(1) Contract DB
rail when no widening is proposed

Impact Attenuator Systems 720


DDP Approvals for use of older systems 720.01(3) Contract DB
Approved public interest finding for use
PF of a sole source proprietary impact 720.03 Contract DB
attenuator
Documentation of reasons for
DDP 720.03 Contract DB
eliminating attenuator options

Div. 8 - Traffic Safety Elements


Work Zone Traffic Control 810
Description of and the basis for the RFP WSDOT Draft
PF CWZTC strategy developed during the 810
project design Contract DB

RFP WSDOT
810.01, 810.19,
PF Work Zone Traffic Control Checklist
Figure 810-4 Contract DB

810.14, RFP WSDOT


PF Work Zone Traffic Analysis Documents
Figure 810-4
Contract DB

Contact with local & WSP enforcement 810.13, RFP WSDOT


PF
officials Figure 810-4 Contract DB
RFP WSDOT Draft
PF Time Restrictions 810.06(1)
Contract DB
Road Closures, detours and 810.18, RFP WSDOT Draft
PF
agreements Figure 810-4 Contract DB
RFP WSDOT
Notification to maintenance regarding
PF 810.07(5)(e)
oversized vehicle restrictions
August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION
Notification to maintenance regarding REFERENCE WHEN BY WHOM Status REMARKS
PF 810.07(5)(e)
oversized vehicle restrictions Contract DB

RFP WSDOT
PF Speed Limit reduction approval 810.13(8)
Contract DB
RFP WSDOT
PF Transportation Management Plan 810, 810.17
Contract DB
RFP WSDOT
PF Traffic Control Plans 810, 810.18
Contract DB

Signing 820
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
PF Replacing/modifying signs 820.01 Contract DB
PF Approval of non-standard signs 820.01 Contract DB
PF Approval of proposed guide signs 820.01 & 820.06 Contract DB
820.03(1) through RFP WSDOT To level needed to determine easements for R/W Plan
DDP Design Components
(6) Contract DB
Soils investigations for all sign bridge
PF 820.03(5) Contract DB
and cantilever sign supports
PF Sign bridge vertical clearance 820.04(2) Contract DB
Inventory of all existing signing within Traffic Office
PF Contract DB
the project limits 820.07

Delineation 830
RFP WSDOT Draft
PF Decision to omit delineation work 830.01
Contract DB
Approval of Region Traffic Engineer for
PF 830.04
use of barrier centerline
Supplemental Right Edge line
PF 830.04(4) Contract DB
markings
Use of Type 3 Raised Pavement
PF 830.03 Contract DB
Markers
Justification to use guideposts on
830.04 &
PF tangent sections due to snow, fog, or Contract DB
Figure 830-2
other reduced visibility conditions

Illumination 840
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL

Identify facilities where the required RFP WSDOT Draft


DDP 840.04
illumination is proposed Contract DB

Major parking lots - illumination design


DDP providing appropriate light levels, 840.04(7)
circuitry design for security lighting

Justification and approval for any


840.05(1) through
DDP proposal to install additional Contract DB
(11)
illumination at other highway facilities
Justification for using nonstandard
DDP luminaries and light standards on state 840.06(4) Contract DB
highways

Traffic Control Signals 850


All traffic study information used in the RFP WSDOT Draft
PF Planning
signal analysis Contract DB

A copy of the approved traffic signal Traffic Office RFP WSDOT Final
DDP
permit 850.04 Contract DB
RFP WSDOT Final
DDP Third Party Agreement Signals 850.04(2)
Contract DB
Alternative analysis for traffic signals RFP WSDOT
PF 850.05
on high speed highways Contract DB
Explanation for using normally RFP WSDOT
PF uncorrectable accidents to justify a 850.05
traffic signal Contract DB
RFP WSDOT Final
PF Signal Warrants 850.05
Contract DB

Explanation of why the desired level of RFP WSDOT Final


PF 850.06(2)(a)
service cannot be obtained Contract DB
PF Railroad preemption phasing 850.06(2)(f) Contract DB
PF Emergency vehicle preemption 850.06(7)(a) Contract DB
PF Transit priority preemption 850.06(7)(c) Contract DB
Traffic Office
PF A copy of the preliminary signal plan Contract DB
850.06(10)

Intelligent Transportation
860
Systems
Justification for the installation of ramp
PF 860 RFP WSDOT Final
meters

Designs for the ultimate system when


PF 860.01 Contract DB
staged implementation is used

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Approved traffic signal permit for ramp
DDP 860.04 RFP WSDOT Final
meters
All correspondence and coordination RFP WSDOT Contributions from both teams
PF 860.04(5)
with local agencies Contract DB

Div. 9 - Intersections & Interchanges


Most of these Items may be included in the
Intersections At Grade 910
Intersection Plan for Approval
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
RFP WSDOT 15% - designed to level of footprint
DDP Intersection angle 910.04(2)(a)
Contract DB determination for R/W
910.06, Figures RFP WSDOT 15%
DDP Intersection turning radii
910-8 & 910-11a Contract DB
RFP WSDOT 15%
DDP Sight distance at intersection 910.1
Contract DB
RFP WSDOT 15%
DDP Traffic analysis 910.04(1)
Contract DB
RFP WSDOT 15%
DDP Accident analysis 910.04(1)
Contract DB
RFP WSDOT 15%
DDP Lane alignment 910.04(2)(b)
Contract DB
Split Tee intersection evaluation / RFP WSDOT 15%
DDP 910.04(2)( c )
justification Contract DB

Justification and approval from Region


Traffic Engineer to retain existing RFP WSDOT
intersection with substandard
DDP 910.04(2)(d)
configuration when accident analysis
shows no history as a result of the Contract DB
configuration

RFP WSDOT
DDP Crossroad design 910.04(3)
Contract DB
Traffic analysis for justification to use RFP WSDOT
DDP smaller design vehicle for any 910.05
particular intersection leg Contract DB

Design Vehicle selection and RFP WSDOT 15%


DDP justifications with regard to 910.05
encroachments Contract DB

Justification for modifying right-turn


DDP corner designs as shown in Figure 910.06
910-7

Plot showing design vehicle turning


DDP 910.06
path template - right turn corner

910.07(1)(a) & RFP WSDOT 15%


Figs 910-4, 910-8b
DDP Left-turn lane storage length
& 910-9a through
9c Contract DB

Left-turn lane justification including


traffic and accident analysis - RFP WSDOT 15%
910.07(1)(a) &
DDP signalized and unsignalized
Figs 910-8a & 8b
intersections, HCM analysis if
Contract DB
performed

Evaluate upgrade when existing


RFP WSDOT
opposing left turn lanes do not meet
DDP 910.07(1)(a)
the 4 ft minimum clearance and have
split phasing Contract DB

Justify modifications made to left-turn


designs given in Figures 910-10a - RFP WSDOT
DDP 10d. Document benefits and impacts, 910.07(1)(a)(3)
include a plot of the design showing
the design vehicle turning template Contract DB

RFP WSDOT 15%


DDP Two-way left-turn lane justification 910.07(1)(b)
Contract DB
Right-turn lanes and drop lanes RFP WSDOT 15%
justification including accident study,
DDP 910.07(2)
traffic signal analysis and capacity Contract DB
analysis
RFP WSDOT 15%
DDP Speed Change Lanes justification 910.07(3)
Contract DB

Shoulder width reduction within


DDP 910.07(4)
channelized intersection areas

DDP Traffic island design 910.07(5) Contract DB


DDP U-turn justification and design 910.09 Contract DB

Document the right of way width and


provide a brief analysis of the
intersection sight distance clarifying
DDP 910.1
the reduction in setback distance.
Document there is no accident
problem and as a design exception

Interchange ramp terminals sight RFP WSDOT 15%


DDP distance and design (capacity 910.10 & 910.12
August 2006 determination
Determinationand analysis)
- MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Interchange ramp terminals sight
DDP distance and design (capacity 910.10 & 910.12
determination and analysis) Contract DB

DDP Traffic Control at intersection analysis 910.11 Contract DB

Intersection plans and supporting RFP WSDOT 15%


DDP 910.13(1) & (2)
information Contract DB
Local Agency or Developer Initiated RFP WSDOT 15%
DDP 910.13(3)
Intersections Contract DB
RFP WSDOT
DDP Median lane reduction justification Fig 910-10d
Contract DB

Roundabouts 915 Chapter 915 Supplement


Locations where roundabouts need RFP WSDOT 15%
DDP 915.01(2)
additional evaluation Contract DB
Capacity analysis for determining RFP WSDOT 15%
DDP 915.05
roundabout capacity Contract DB

Evaluation of turning radii R4 and R5 to RFP WSDOT

DDP ensure maximum speed differential 915.06(9)


between entering and circulating traffic
is no more than 12 mph Contract DB

RFP WSDOT 15%


DDP Right-Turn Slip Lane justification 915.06(13)
Contract DB
PF Striping plan 915.09 Contract DB
915.12(1), (2) &
DDP Roundabout justification RFP WSDOT Final
(3)
Approving authorities concurrence
DDP 915.12(1) RFP WSDOT Final
(other than WSDOT)
DDP HQ Design Office approval 915.12(1) & (3) RFP WSDOT Final
DESIGN MANUAL
DESIGN ELEMENT DESIGN LEVEL EXISTING STANDARD
REFERENCE
DDP Access Control

DDP Signing

DDP Pavement Markings

DDP Illumination

DESIGN MANUAL
DESIGN ELEMENT DESIGN LEVEL EXISTING STANDARD
REFERENCE
Circulating Roadway
DDP Inscribed Diameter or ICD
DDP Central Island/Truck Apron
DDP Truck Apron Design Vehicle
DDP Number of Circulating Lanes
DDP Circulating Speed
DDP Circulating Width
DDP Deflection Radius
DDP Circulating Cross Slope
DDP Deflection Clearance

Approach From… (Must include a section for each approach)


Approach Speed (Posted
DDP
Speed)
DDP Approach Design Vehicle

DDP Number of Entry Legs


DDP Entry Leg Spacing Angles
DDP Entry Speed
DDP Entry Width
DDP Approach Half Width
DDP Entry Angle
DDP Entry Deflection Radius
DDP Entry Deflection Curve

DDP Number of Exit Lanes


DDP Exit Speed
DDP Exit Width
DDP Exit Deflection Radius

DESIGN MANUAL
DESIGN ELEMENT DESIGN LEVEL EXISTING STANDARD
REFERENCE
Stopping Sight Distance
DDP Approach Roadway
DDP Circulating Roadway
DDP Departure Roadway

Intersection Sight Distance


DDP Approach Roadway - to left
DDP Approach Roadway - forward
DDP Circulatory

Approach From... (Must include a section for each approach)


August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Islands
DDP Splitter Island Length
Splitter Island Width @
DDP
Crosswalk
DDP Splitter Island Taper

Pedestrian and Bicycles


DDP Crosswalk Location
Barrier Free Passage Way
DDP
Width

Grade/Superelevation
DDP Approach Roadway Grade

Right-Turn Slip Lane


DDP Radius
DDP Lane Width

Road Approaches 920


Evaluation of existing road approaches
DDP that do not comply with access control 920.04 RFP WSDOT Final
requirements
Utility and Special Use - Managed
Access Facility when an agreement
DDF 920.05(3)(b) RFP WSDOT Final
has been reached for the special
purpose
RFP WSDOT Draft
PF Plan or list of the road approaches 920.09
Contract DB

Railroad Grade Crossing 930


RFP WSDOT Draft
DDP Easements or permits with railroad/s 930.01
Contract DB
Notice to Proceed authorizing railroad
PF 930.01
to commence work
Petition to WUTC and WUTC issued
DDP 930.01 & 930.09
Order
Sight distance evaluation and
DDP 930.03
documentation

Evauate need for median separator


DDP when lights and gate might not be 930.03
providing adequate safety to motorists.

Any engineering studies or sight


DDP 930.03
distance measurements.
Traffic control systems passive and
PF active including any signal pre-emption 930.04(a) & (b)
timing or calculations
Evaluation of railroad signal supports
DDP and gate mechanisms as roadside 930.04(b)
hazards

Most of these items may be included for the I/C plan


Traffic Interchanges 940
for approval
DESIGN MANUAL
DESIGN ELEMENT EXISTING STANDARD
REFERENCE

940.05(1) & RFP WSDOT 15%


DDP Ramp Design Speed
Figure 940-1 Contract DB
940.05(2) & RFP WSDOT 15%
DDP Ramp vertical stopping sight distance
650.05 Contract DB
Ramp horizontal stopping sight 940.05(2) & RFP WSDOT 15%
DDP
distance 650.05(5) Contract DB
RFP WSDOT 15%
DDP Ramp maximum grade 940.05(3)
Contract DB
940.05(4) & Figure RFP WSDOT 15%
DDP Ramp lane width
940-3 Contract DB
940.05(4) & Figure RFP WSDOT 15%
DDP Ramp shoulder width
940-3 Contract DB
940.06(4) & RFP WSDOT 15%
DDP Accel lane number of lanes, length
Figure 940-8 Contract DB
940.06(5) & RFP WSDOT 15%
DDP Decel lane number of lanes, length
Figure 940-10 Contract DB
RFP WSDOT 15%
DDP Left side on-off connections 940.04(1)
Contract DB
940.04(3) & RFP WSDOT 15%
DDP Spacing
Figure 940-5 Contract DB

Justification to use midrange design RFP WSDOT


speed values for portion of freeway-to-
DDP 940.05(1)
freeway ramps in lieu of upper range
values Contract DB

RFP WSDOT 15%


DDP Ramp lane increases 940.05(5)
Contract DB
Justification for ramp metering main RFP WSDOT 15%
DDP 940.05(6)
line speed reduction Contract DB

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Justification for mountable curb at
940.06, Figs. 940-
DDP interchange - speed of adjacent traffic Contract DB
13a,b, & c
exceeds 40 mph
Lane balance - Not required, but 940.06(1) & Figs.
DDP Contract DB
desirable 940-6a & 6b
Accel lane length based on a speed RFP WSDOT 15%
DDP 940.06(4)
less than design speed Contract DB
On-connection type justification, 940.06(4) (a),(c), RFP WSDOT 15%
DDP existing (with possible design (d) & Figs, 940-9a
exception) and new through 9d Contract DB

Decel lane length based on a speed RFP WSDOT 15%


DDP 940.06(5)
less than design speed Contract DB
Off-connection type justification, 940.06(5)(a),(c) RFP WSDOT 15%
DDP existing (with a possible design and Figs. 940-12a
exception) , and new through 940-12e Contract DB
940.06(5)(b) &
DDP Gores - Not required, but desirable Figs. 940-11a & Contract DB
11b
940.06(8), &
DDP Weaving analysis and design Contract DB
Figure 940-5
RFP WSDOT 15%
DDP Interchange Plan, contour grading plan 940.09
Contract DB
DDP/PF Interchange Justification Report 1425 RFP WSDOT Final

Median Crossovers 960

Median crossover may be provided


based on an analysis demonstrating
DDP 960.01 Contract DB
that access through interchanges or
intersections is not practical

DDP Operational Analysis 960.02 RFP WSDOT Final

Right of Way or Limited Access Plan


PF approval, need, and design data 960.04 RFP WSDOT Final
showing a opening

Div. 10 - Auxiliary Facilities


Auxiliary Lanes 1010
1010.04(1)(2)(3) &
Documentation that climbing lane Figs. 1010-2a,
DDP RFP WSDOT Final
Warrant has been met 1010-2b and
1010-3
Justification for waiving climbing lane
DDP 1010.04(1) RFP WSDOT Final
Warrant 1 or 2
Justification of shoulder width
DDP reduction on Two-Way Two-Lane 1010.04(4)
climbing lane section.
1010.05(1),(2) &
DDP Justification for passing lanes Figures 1010-5
and 1010-6
Justification of shoulder width
DDP 1010.05(2)
reduction on passing lane sections
Slow moving vehicle turnout
DDP documentation (need, location, and 1010.06(2)
why selected)
DDP Shoulder Driving for Slow Vehicles 1010.07(2)

Emergency escape ramp


DDP 1010.08(2)
documentation
1010.09 &
DDP Chain-up Areas
Figure 1010-9

Bicycle Facilities 1020 Chapter 1020 Supplement


Coordination with Region Bicycle RFP WSDOT
DDP 1020.01
Coordinator Contract DB
RFP WSDOT 15%
DDP Facility Selection 1020.04
Contract DB
DESIGN MANUAL
DESIGN ELEMENT EXISTING STANDARD
REFERENCE

Width

DDP Shared-Use Path or Bike Lane

DDP Separation to Obstructions

DDP Graded Area

Clearance to Obstructions

DDP Horizontal Clearance

DDP Vertical Clearance

Intersections with Highways

DDP Intersection Crossing Angle

DDP Approach Treatment

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
DDP Ramp Widths

DDP Refuge Islands

DDP At-Grade Railroad Crossings

DDP Separation, Barrier, Fencing

DDP Design Speed


Horizontal Alignment and Cross
DDP
Section
DDP Stopping Sight Distance
Sight Distance - Crest Vertical
DDP
Curves
Lateral Clearance - Horizontal
DDP
Curves
DDP Grades

DDP Pavement Structural Section

DDP Structures

DDP Drainage

DDP Signing and Pavement Markings

DDP Illumination

Pedestrian Design
1025
Considerations
Investigate and document options to RFP WSDOT 15%
modify the scope of pedestrian
DDP 1025.04(1)
improvements on a project or separate Contract DB
into another project

Exceptions to adopted design RFP WSDOT


DDP standards require a deviation approved 1025.04(1)
by the designated authority Contract DB

Agreements with cities to install RFP WSDOT 15%


pedestrian sidewalks or walkways 1025.04(2)(a),
DDP
along state highways within their 1025.07(2)(a)
jurisdiction Contract DB

RFP WSDOT 15%


PF Shoulder Width 1025.07(2)(b)
Contract DB
1025.07(2)(e) & RFP WSDOT 15%
DDP Justification for sidewalks
Figure 1025-3 Contract DB

1025.07(2)(e) & RFP WSDOT 15%


PF Side slopes adjacent to sidewalks
Figs. 1025-2a & 2b
Contract DB
Decisions to prohibit a pedestrian
DDP 1025.07(3) Contract DB
crossing at an intersection
Approval of the installation of a
DDP 1025.07(3) Contract DB
midblock pedestrian crossing
Approval of the installation of a bulb
PF 1025.07(3) Contract DB
out on a state highway

High Occupancy Vehicle


1050
Facilities
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
1050.05(1)
PF Operations RFP WSDOT
through (3)

DDP Analysis of Need for HOV Lanes 1050.01 & 1050.04 RFP WSDOT Final

DDP Freeway Operational Alternatives 1050.04(3) RFP WSDOT


Conversion of existing freeway lane to RFP WSDOT
DDP an HOV lane requires a deviation 1050.04(3)(b)
request. Contract DB

Conversion of existing shoulder to an RFP WSDOT


DDP 1050.04(3)(c)
HOV lane requires a deviation request.
Contract DB

Agreement with transit agency when RFP WSDOT


DDP 1050.04(3)(c)
shoulder is converted to HOV use
Contract DB
RFP WSDOT 15%
DDP Arterial Street Operational Alternatives 1050.04(4)
Contract DB
1050.06(1) RFP WSDOT 15%
DDP Design Criteria
through (8) Contract DB

Deviation required when any proposed RFP WSDOT


element or existing design element
DDP does not meet the applicable design 1050.06(2)
level for the project.
Contract DB

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Shoulder reduction to 2 feet on an RFP WSDOT


1050.06(4)(c) &
DDP arterial street with a proposed HOV
Fig 1050-2
lane requires justification. Contract DB

RFP WSDOT
Location of an observation
DDP point/enforcement area other than that 1050.06(4)(e)
shown in figures 1050-4a and 4b Contract DB

HOV Direct Access 1055


Access Point Decision Report
DDP 1055.01(2)
(Interchange Justification Report)
Operational Analysis portion of the IJR 1055.01(2) &
PF
for flyer stop approval. 1055.05(9)
DDP Site Evaluation 1055.04
DDP Evaluation of ramp connection spacing 1055.04(1)(a)
Traffic analysis to determine
PF 1055.04(1)(a)
degradation of traffic operations
Deviation for on-ramp or off-ramp
PF grades increased by 1% and 2% 1055.05(4)
respectively
Justification for use of tapered off-
PF 1055.05(7)(b),(d)
connection

Deviation for 14.5 foot minimum


DDP vertical clearance for a new HOV direct 1055.05(8)
access ramp under an existing bridge.

PF ADA accessibility compliance 1055.06

Transit Benefit Facilities 1060 Chapter 1060 Supplement


Park & Ride Lots:
DDP MOU 1060.03(1) RFP WSDOT Final
Public Meetings & Environmental
DDP 1060.03(2) RFP WSDOT Final
Processes
RFP WSDOT 15%
DDP Document design decisions 1060.03(3)
Contract DB
Bus Stops & Pullouts:
Consent of jurisdiction having authority
DDP over R/W and transit authority for bus 1060.05(2) RFP WSDOT Final
stop placement

Div. 11 - Structures
Site Data for Structures 1110
1110.03(2),
DOT Form 235-002, "Bridge Site Data Figure 1110-1 &
PF Contract DB
- General" Bridge Design
Manual

1110.04,
DOT Form 235-001, "Bridge Site Data Figure 1110-1 &
PF Contract DB
for Stream Crossings" Bridge Design
Manual

PF United States Coast Guard permit 240.03, & 1110.04 RFP WSDOT Final

Coast Guard permit exemption -


PF 1110.04 RFP WSDOT Final
Environmental Classification Summary

1110.06,
DOT Form 235-002a, "Supplemental
Figure 1110-1 &
PF Bridge Site Data - Contract DB
Bridge Design
Rehabilitation/Modification"
Manual

Bridges 1120
DESIGN MANUAL DESIGN
DESIGN ELEMENT EXISTING STANDARD
REFERENCE LEVEL
RFP WSDOT 15%
DDP Vertical Clearance 1120.04(5)
Contract DB

DDP Final Geotechnical Foundation Report 510.04(13) Contract DB

DDP Structural Capacity Report 1120.04(1)(b) Contract DB


1120.04(3) & The RFP WSDOT 15%
DDP Horizontal Clearance Bridge Design
Manual Contract DB
Evaluation of need and approval for
DDP enclosing the median area between 1120.04(4) Contract DB
bridges

Agreement between railroad company


and approval of WUTC for reduced
1120-04(5)(a)(2),
clearance for closed or dedicated rail
DDP (b)(4), Figs 1120-
corridors that do not intermix with
1, 1120-2a & 2b
general rail freight rail traffic, new and
existing

On existing structures being widened


with a vertical clearance less than 16 ft
1120.04(5)(b)(1) &
DDP on Interstate or other freeways and
Fig 1120-1
less than 15.5 ft on non freeway routes
an approved deviation is required

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Resurfacing under an existing


structure reducing vertical clearance to
less than 16 ft on the interstate or 1120.04(5)(b)(2) &
DDP
other freeways or less than 15.5 ft on Fig 1120-1
nonfreeway routes evaluate options an
approved deviation is required

Contact Materials
Justification for eliminating an overlay Lab and/or Bridge
DDP
in the vicinity of a bridge Office 1120.04(5)
(b)(2)

Materials Engineer approval to mill an


PF 1120.04(5)(b)(2)
existing surface
Project with existing bridge and no
widening on or under bridge but
already has a vertical clearance under 1120.04(5)(b)(3) &
DDP
14.5 ft, an approved deviation is Fig 1120-1
required. For clearance of 14.5 ft
documentagreement
Railroad only. allowing less than
DDP 1120.04(5)(b)(4) RFP WSDOT Final
22.5 ft. vertical clearance
Correspondence involving the
PF 1120.04(5)(d)
MTMCTEA
Justification and HQ concurrence for
PF 1120.04(6) Contract DB
omitting bridge approach slabs
Analysis of need and approval for
DDP protective screening on highway 1120.04(11) Contract DB
structures

Retaining Walls and Steep


1130
Reinforced Slopes
Traffic Barrier Shape in front of wall
DDP 1130.04(1)
deviation
RFP WSDOT Draft
DDP Geotechnical/Soils Report 1130.04(2)
Contract DB
PF Drainage detail deletions 1130.04(4) Contract DB

Bridge & Structures Principal Architect


PF 1130.04(5) Contract DB
approval of aesthetic features

Consideration of site constraints on


DDP 1130.04(6) Contract DB
constructibility
Impact of other interfering design
PF 1130.04(7)(a) Contract DB
elements
Consideration of Fall Protection for
DDP 1130.04(7)(b) Contract DB
walls 10 ft or greater in height

Approved work plan for an


PF 1130.06(1)
experimental proprietary retaining wall

Approved public interest finding for use


PF of a sole source proprietary retaining 1130.06(1)
wall
PF HQ Approval of Consultant designs 1130.06(2) Contract DB
1130.06(3)(b) - RFP WSDOT 15%
Wall Site Data Check List,
PF Check with Bridge
DOT351-009EF, and attachments Contract DB
Office

Noise Barriers 1140

1140.01 - See
Noise Policies on
DDP Noise Report HQ Environmental RFP WSDOT
Affairs Office
homepage

RFP WSDOT Draft


DDP Geotechnical/Soils Report 1140.03(2)
Contract DB
List of design options considered and RFP WSDOT 15%
PF 1140.03(2)
summary of evaluations Contract DB
Traffic Barrier Shape in front of wall
DDP 1140.03(2)(f) Contract DB
deviation
DDP Openings approvals 1140.04 Contract DB
DDP Wall attachments approval 1140.04 Contract DB
DDP Report on impact due to change 1140.04 Contract DB
PF Final Selection approval 1140.04 Contract DB

Div. 12 - Hydraulics
Hydraulic Design 1210
Hydraulics RFP WSDOT Draft
DDP Hydraulics Report
Manual Contract DB
RFP WSDOT Draft
DDP Hydraulics Summary Hydraulics Manual
Contract DB
Temporary Erosion & Sediment Control Highway Runoff RFP WSDOT Draft - 15%
PF
(TESC) Plans Manual Contract DB
Highway Runoff RFP WSDOT Draft - 15%
PF Stormwater Site Plans (SSP)
Manual Contract DB

Div. 13 - Roadside Development


Roadside Development 1300
August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Roadside
Classification Plan
& Roadside
Manual
VisualDiscipline Reports/Visual Impact
DDP
Assessment
1300.06 DB Chapter 1300 Supplement

Contour Grading 1310


1310.01 &
PF Contour Grading Plan Contract DB
Roadside Manual

Vegetation 1320
Mature characteristics of plant species
PF 1320.04(1) DB
evaluation

Irrigation 1330
PF Irrigation Plan 1330.01 Contract DB
1330.03(c) listed
Approved public interest finding for use
PF under the design Contract DB
of a sole source proprietary products
phase

Soil Bioengineering 1350


For streambank/shoreline as part of
PF the recommendations of the Hydraulic 1350.04 Contract DB
Report
As part of the recommendations in the
PF 1350.04 Contract DB
Stormwater Site Plan (SSP)
For slope stabilization as part of the
PF recommendations in the Geotechnical 1350.04 Contract DB
Report
As part of the recommendations in the
PF 1350.04 Contract DB
Environmental Documents

PF Summary of site analysis Roadside Manual Contract DB

PF Roadside Restoration Plan Roadside Manual Contract DB

Div. 14 - Right of Way & Access Control


Right of Way Considerations 1410
Approval of any approach on Limited
PF 1410.03(1) RFP WSDOT Final
Access Highways
RFP WSDOT 15%
DDP New Approach - Permits 1410.03(1)
Contract DB
PF Cattle pass studies and approvals 1410.03(2) N/A
PF Detour and Haul Road Agreements 1410.03(3) Contract DB
International Boundary Commission
DDP 1410.03(4) N/A
approval
RFP WSDOT 15%
PF Construction permit and map 1410.04(4)
Contract DB
1410.04,
PF Approved Easements & Permits 1410.07(3), Contract DB
1410.07(4)
FHWA authorization for federal
PF 1410.05
participation in right of way costs
Condemnations for emergency
PF projects of immediate need for a 1410.05(6)
sundry site
Approvals of Access Report Plan,
PF Access Hearing Plan, R/W Plans and Figure 1410-1
L/A Plans

Access Control 1420


DDP Access connection permit 1420.03 RFP WSDOT
Access deviation approval - State
DDP 1420.03 RFP WSDOT
Design Engineer
RFP WSDOT
PF Application for an access connection 1420.03
Contract DB
RFP WSDOT
DDP Easement 1420.03
Contract DB
DDP Findings and order 1420.03 Contract DB
DDP Findings and order plan 1420.03 Contract DB
USFS request to obtain a road 1420.03 & MOU
approach permit for a new access to a Highways Over
DDP N/A
state highway that is crossing Forest National Forest
Service Land Lands

Interchange Justification Report 1425

Request for acceptance and approval 1425.01,


and the associated Interchange 1425.05(1) thru (8) Final - This must be completed prior to the Access Report
PF RFP WSDOT
Justification Report and supporting and Figures 1425- and Plan process
records 1 and 1425-4

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Transportation Systems study (study


1425.04(1), (2)
DDP area and/or area of influence), traffic
and (3)
analyses, operational/safety analyses

DDP Acceptance and approval documents 1425.04(3) RFP WSDOT Final

Justification for omitting a request and


DDP Figure 1425-3 RFP WSDOT Final
IJR

Limited Access 1430

Evaluation of access control type (F, P,


or M) when ROW is being acquired on
DDP an existing highway if shown on the 1430.01 RFP WSDOT Final
ACTS list as either established or
planned for access control

Cost evaluation of acquiring limited


PF 1430.01 RFP WSDOT Initial cost estimate
access
1430.02(1)(d) &
DDP Findings and Order RFP WSDOT Final - WSDOT/GEC Lead - Risk Item
210

DDP Access Report and Plan 1430.02(2)(f) & (g) RFP WSDOT Final - WSDOT/GEC Lead - Risk Item

1430.02(3) &
DDP Access Hearing Plan Plans Preparation RFP WSDOT Final - WSDOT/GEC Lead - Risk Item
Manual

Request and approval of gated


DDP 1430.03(1) RFP WSDOT Final
approaches
Staged access acquisition - access
DDP 1430.03(1) RFP WSDOT Final
deviation approval
Decision to defer acquisition of limited
DDP control of access - access deviation 1430.03(1) RFP WSDOT Final
approval

The evaluation of full control for


principal arterial highways requiring
four or more through traffic lanes within
DDP a 20-year design period unless 1430.03(2)(b) N/A
approved for partial or modified control
on existing highways by the
Transportation Commission.

Limited access falls short of 300 ft or


any access that has been allowed to 1430.03(3)(d),
DDP RFP WSDOT Final
remain within the first 130 ft. - Access 1430.04(3)(a)
deviation
Headquarters approval of trails within
DDP the limits of full control limited access 1430.03(6) RFP WSDOT Final
highways
State Design Engineer approval of
altering right of access by abutting
DDP 1430.04(1) N/A
property owner - partial limited access
control
State Design Engineer approval of
DDP shorter interval spacing for public road 1430.04(3)(b) RFP WSDOT Final
intersections
State Design Engineer approval of
excess approaches allowed as stage
DDP 1430.04(4)(b) N/A
construction on partial control limited
access highways.

Department approval of designated


school bus loading zone on traveled
DDP lane or adjacent thereto on two or four- 1430.04(5)(b) N/A
lane highways with partial limited
access control

1430.04(6) &
Bicycle or pedestrian prohibition on Traffic Engineering
DDP partial control limited access facilities Branch of N/A
due to unusual safety conditions. Operations and
Maintenance

Headquarters approval of trails within


DDP the limits of partial control limited 1430.04(7) N/A
access highways
State Design Engineer approval of
altering right of access by abutting
DDP 1430.05(1) N/A
property owner - modified limited
access control
Design analysis of highways on which
DDP modified access control may be 1430.05(2)(b) N/A
applied

Access deviation approval where


modified control is to be established
and commercial areas may be
DDP 1430.05(2)(c) N/A
excepted from control when all or most
of the abutting properties have been
developed…

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Access deviation for any access that
has been allowed to remain within the
DDP 1430.05(3) N/A
first 130 ft of an intersection - modified
access control

Department approval of designated


school bus loading zone on traveled
1430.05(5)(b) &
DDP lane or adjacent thereto on rural two N/A
1430.04(5)(b)
or four-lane highways with modified
control

1430.05(6) &
Bicycle or pedestrian prohibition on Traffic Engineering
DDP modified control facilities due to Branch of N/A
unusual safety conditions. Operations and
Maintenance

When trails are allowed on modified


DDP 1430.05(7) N/A
control limited access highways
RFP WSDOT 15%
DDP Negotiated width for approach type 1430.06(2)
Contract DB
Local agency approval for any planned
DDP frontage road, county road, city street 1430.07 RFP WSDOT Final
or cul de sac.

Local agency written agreement to RFP WSDOT Draft


DDP accept and maintain the new section 1430.07
as a county road or city street Contract DB

Request of local agency, private


RFP WSDOT 15%
agency or private individual for state to
DDP build frontage road not the 1430.07(1)
responsibility of the state upon
reimbursement for all costs Contract DB

1430.08 & RFP WSDOT 15%


DDP Turnback Agreement Agreements
Manual Contract DB

Special Provisions for use of a direct RFP WSDOT 15%


approach by a railroad company for
DDP other than those shown on the right of 1430.09(3)
way and limited use plan and included
in the right of way negotiations Contract DB

Approval of modification to limited


access highways by the E&EP Director
or FHWA including right of way and
DDP limited access plan. New deeds if 1430.10(1) & (2) RFP WSDOT Final
private approaches involved.
Engineering review and
recommendations, appraisals

Modifications for Public At-Grade


1430.10(1),(2) &
DDP Intersections - request by or through RFP WSDOT 15%
(3)
local agency, intersection plan

Managed Access 1435

1435.01, 1435.05,
Access connection permits for all state I-405 is a full control access highway. All connecting state
1435.06,
DDP managed access highways outside N/A highways are either full control or are within city limits so
1435.06(1), (2), (3)
incorporated towns and cities managed access does not apply.
& (4)

1435.01, 1435.06,
DDP Conforming Access Connection Permit N/A
& 1435.06(1)
1435.01, 1435.06
DDP Median Openings N/A
& 1435.06(4)
Nonconforming access connection 1435.02(1)(b)(2) &
DDP N/A
permit Class 1 1435.06(2)
Justification through traffic analysis
signed and sealed by a qualified
DDP professional engineer for exception to 1435.02(1)(b)(2) N/A
right turn only access connection to
multilane facility - Class 1

Addition of new access points, public


or private, that might require
signalization need engineering
DDP 1435.02(2)(b)(1) N/A
analysis signed and sealed by a
qualified professional engineer - Class
2

Nonconforming access connection 1435.02(2)(b)(2) &


DDP N/A
permit - Class 2 1435.06(2)
Variance permit based on special
conditions and the exception is justified
DDP through traffic analysis signed and 1435.02(2)(b)(2) N/A
sealed by a qualified professional
engineer - Class 2

For private access connections


justification through traffic analysis
signed and sealed by a qualified
DDP professional engineer for exception to 1435.02(2)(b)(2) N/A
right turn only access connection to
multilane facility, only if left turn
channelization is provided - Class 2

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS
Special conditions justify TWLTL and
DDP main line volumes are below 25,000 1435.02(3)(a) N/A
ADT - Class 3

Addition of new access points, public


or private, that might require
signalization need engineering
DDP 1435.02(3)(b)(1) N/A
analysis signed and sealed by a
qualified professional engineer - Class
3
Nonconforming access connection
DDP 1435.02(3)(b)(2) N/A
permit - Class 3
Variance permit based on special
conditions and the exception is justified
1435.02(3)(b)(2) &
DDP through traffic analysis signed and N/A
1435.06(3)
sealed by a qualified professional
engineer - Class 3

Addition of new access points, public


or private, that might require
signalization need engineering
DDP 1435.02(4)(b)(1) N/A
analysis signed and sealed by a
qualified professional engineer - Class
4

Nonconforming access connection 1435.02(4)(b)(2) &


DDP N/A
permit - Class 4 1435.06(2)
Variance permit based on special
conditions and the exception is justified
1435.02(4)(b)(2) &
DDP through traffic analysis signed and N/A
1435.06(3)
sealed by a qualified professional
engineer - Class 4

Addition of new access points, public


or private, that might require
signalization need engineering
DDP 1435.02(5)(b)(1) N/A
analysis signed and sealed by a
qualified professional engineer - Class
5

Nonconforming access connection 1435.02(5)(b)(2) &


DDP N/A
permit - Class 5 1435.06(2)
Variance permit based on special
conditions and the exception is justified
1435.02(5)(b)(2) &
DDP through traffic analysis signed and N/A
1435.06(3)
sealed by a qualified professional
engineer - Class 5

Corner Clearance - Single access


1435.03,
connection closer than minimum
DDP 1435.03(c) & WAC N/A
access point spacing requirements -
468-51
conforming clearance permit

Backup data justifying a significant


change in use causing a change in the
category of the access connection
1435.08(1) & (2)
PF permit or one that causes an N/A
(a)
operational, safety or maintenance
problem on the state highway -
requiring a new permit

Department construction projects


notification to affected property
DDP 1435.08(2)(b) N/A
owners, permit holders, business
owners and emergency services
Variance permit if a business cannot
function properly with only one access
DDP 1435.08(2)(b) N/A
connection as a result of a department
construction project
Surety Bond when owner's contractor
1435.08(3) & WAC
PF performs construction work to N/A
468-51-070
complete access connection
Adjudicative proceedings -
DDP 1435.10 N/A
correspondence, exhibits

Surveying and Mapping 1440


Notification of impact to geodetic
PF monuments to HQ Geographic 1440.03(2)(c) DB
Services Office
Document the procedure and
PF combined factor for converting 1440.03(2)(d)
between datums

DNR Permit application for monuments


PF 1440.03(2)(e) DB
to be disturbed or removed

Record of Survey or Monumentation


PF 1440.03(2)(h) WSDOT Submitted with Right of Way Plan
Map

DDP Post Construction Survey 1440.03(3)(a)

DNR Completion Report (copy)


DDP 1440.03(3)(b)
Original to DNR
PF Report of Survey Marks 1440.06 DB
PF Summary of Legal Research 1440.03(1)(b) DB
Primary and secondary survey control
1440.09 DB
data to WSDOT Monument Data Base

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
Proj.
Project Title:
No.
Draft - DESIGN-BUILD PROJECT DESIGN DOCUMENTATION CHECK LIST
Location DESCRIPTION REFERENCE WHEN BY WHOM Status REMARKS

Monumentation 1450
General statement about project's 1450.01, &
PF Contract DB
impacts on existing monuments Figure. 1450-1
General statement concerning new 1450.01, &
PF Contract DB
monuments Figure. 1450-1
1450.01, &
PF DNR Permit for disturbing monuments
Figure. 1450-1

PF Variance for omitting monumentation 1450.04 RFP WSDOT Final

PF Record of Survey Mark 1450.04 Contract DB


1450.04, .05, .07,
PF Monumentation Map RFP WSDOT Final
1450.09(2)
PF Record of Survey 1450.06 RFP WSDOT Final
1450.07, &
PF Land Corner Record Contract DB
1450.09(3)
DNR Permit for any monumentation
PF 1450.09(1) Contract DB
work
Hwy Surveying RFP WSDOT 30%
PF Field notes
Manual Contract DB
PF DNR Completion Report 1450.09(1) Contract DB

Fencing 1460
1460.03(1)
Reasons for providing fencing and for through (4) and
DDP Contract DB
the type and configuration selected 1460.04(1)
through (3)

Justification for deferring or not


providing fencing on a highway with
DDP 1460.03(2) Contract DB
limited access control or as otherwise
recommended

Evaluation of need to provide fencing


DDP 1460.03(4)
around stormwater detention facilities

Evaluation on need to provide fencing


DDP 1460.03(4)
for wetland mitigation sites

Justification for why corrective action is


not taken when existing fencing with a
DDP 1460.04 Contract DB
rigid top rail will be left in place within
the limits of a proposed project.

Approval for gates on limited access


DDP 1460.05 Contract DB
highways

Maintenance
Area Maintenance RFP WSDOT 30%
PF Maintenance concerns addressed
Supervisor Contract DB

Utilities
Utilities Manual,
PF Preliminary Engineering Agreement RFP WSDOT Final
2-4
Utilities Manual,
PF Construction Agreement RFP WSDOT Final
2-5
Utilities Manual,
PF Railroad agreements RFP WSDOT Final
3-5
Utilities Manual,
PF Railroad insurance and flagging Contract DB
3-9
Utilities Manual,
PF Detour or Haul Road Agreement Contract DB
4-2
Utilities Manual,
PF Service Agreements Contract DB
4-3
Utilities Manual,
PF Local Agency Agreements RFP WSDOT Final
4-5
Utilities Manual,
PF Transit Agreement RFP WSDOT Final
4-7
Utilities Manual, RFP WSDOT Areas determined to included on Right of Way Plans
PF Turnback Agreements
6-1 Contract DB Agreement completed

Post Project Development


Construction changes that affect
DDP Contract DB
design
DDP As - Built Plans Contract DB

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

DB responsible for any changes to configuration

DB responsible for any changes to configuration

DB responsible to update file for any modifications

DB responsible to update file for any modifications

Only if water quality permits are necessary

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Guidance to be included in the RFP

P/F and then technical score

P/F and then technical score

Include in RFP

Approved deviations included in proposal

Would require contract change

60% - Design File done to an acceptable stage for


completing R/W and Access processes

40% - Complete balance of Design File

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

No blank cells in Interstate matrix

90%

Final

90%

90%

Draft

90% - Early notification to utilities is necessary

15% - 30%

30%

Final

Done with R/W Plans

Final

30% - To level needed to determine R/W footprint

90%

Final

Final

15% - 30%

90%

10% - Temporary access breaks for construction

PS&E items

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

DETERMINATION

Only necessary when State supplies source

Draft

Draft

Draft
August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final - Needed for Chan. Plan to determine R/W footprint

Final - Needed for Chan. Plan to determine R/W footprint

DETERMINATION

15%

15%

15%

15%

DETERMINATION

15%

15%

15%

15%

DETERMINATION

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

DETERMINATION

DETERMINATION

15%

15%

DETERMINATION

Draft

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Draft

Draft

Draft

Draft

Draft

DETERMINATION

15%

15%

Draft

Draft

Draft

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

DETERMINATION

To level needed to determine easements for R/W Plan

Draft

DETERMINATION

Draft

Final

Final

Final

Final

Final

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final

Contributions from both teams

Most of these Items may be included in the


Intersection Plan for Approval
DETERMINATION

15%

15%

15%

15%

15%

15%

15%

15%

15%

15%

15%

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

15%

15%

Chapter 915 Supplement


15%

15%

15%

Final

Final

Final

DETERMINATION

DETERMINATION

DETERMINATION

(Must include a section for each approach)


August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final

Final

Draft

Draft

Most of these items may be included for the I/C plan


for approval
DETERMINATION

15%

15%

15%

15%

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

15%

15%

15%

15%

15%

Final

Final

Final

Final

Final

Chapter 1020 Supplement

15%

DETERMINATION

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

15%

15%

15%

15%

15%

DETERMINATION

Final

15%

15%

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Chapter 1060 Supplement

Final

Final

15%

Final

Final

Final

DETERMINATION

15%

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final

Draft

15%

Draft

15%

Draft

Draft

Draft - 15%

Draft - 15%

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Chapter 1300 Supplement

Final

15%

15%

Final - This must be completed prior to the Access Report


and Plan process

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final

Final

Final

Initial cost estimate

Final - WSDOT/GEC Lead - Risk Item

Final - WSDOT/GEC Lead - Risk Item

Final - WSDOT/GEC Lead - Risk Item

Final

Final

Final

Final

Final

Final

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

15%

Final

Draft

15%

15%

15%

Final

15%

I-405 is a full control access highway. All connecting state


highways are either full control or are within city limits so
managed access does not apply.

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Submitted with Right of Way Plan

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard
DESIGN DOCUMENTATION CHECK LIST
REMARKS

Final

Final

Final

30%

30%

Final

Final

Final

Final

Final

Areas determined to included on Right of Way Plans

August 2006 Determination - MS: Meets Standards ENNF: Existing Nonstandard, No Fix ENF: Existing Nonstandard, Will Fix PN: Proposed Nonstandard