Professional Documents
Culture Documents
Answer The Following Questions
Answer The Following Questions
Answer The Following Questions
Question 1: 10 Points
A. Define productivity.
B. What is an irregular work element?
C. What is a worker-machine system?
D. What is a manual assembly line?
E. What are the objectives of using charts and diagrams to study work?
F. What is a therblig? Identify some of the ineffective therbligs.
G. Identify the five steps in the direct time study procedure.
H. What are the differences between snapback and continuous timing
method when using a stopwatch during direct time study?
Question 2: 10 Points
(b) In the next month, the same worker group produced 8000 units but
there were 22 workdays in the month and the size of the work group
was reduced to 14 workers. What is the labor productivity ratio for
this second month?
(c) What is the productivity index using the first month as a base?
1
Question 3: 10 Points
The continuous timing method in direct time study was used to obtain the
times for a worker-machine task as indicated in the table below. Element C
is a machine - controlled element and the time is constant. Elements A, B,
D, E, and F are operator - controlled and were performance rated at 95%;
they are all external elements performed in sequence with machine element
C. The machine allowance is 30%, and the PFD allowance is 15%.
Determine (a) the normal time and (b) standard time for the cycle.
(d) For the number of parts computed in (c), what is the worker’s efficiency
for this shift?
Element A B C D E F
Question 3:
Solution 3 :
(a) Tc = 60(0.96)/48 = 1.2 min, Ts = 1.2 – 0.1 = 1.1 min
For perfect balance, w = Min Int 36.3/1.1(1.0) = 33 workers. Actual
number of workers is three more than for perfect balance.
Therefore, w = 33 + 3 = 36 workers
(b) Given that 12 stations have 2 workers (total 24 workers), so the
remaining 12 stations have 1 worker each.
n = 12 + 12 = 24 stations
(c) Eb = 36.3/36(1.1) = 0.9167 = 91.67%
(d) M = 36/24 = 1.5
(e) Labor efficiency = E Er Eb = 0.96(1.1/1.2)(0.9167) = 0.8067 = 80.67%
Question 4:
Solution:
(a) Observed times must be determined for each element: Te(A) = 0.22 min,
Te(B) = 0.18 min, Te(C) = 0.68 min, Te(D) = 0.21 min, Te(E) = 0.46 min,
and Te(F) = 0.35 min
For elements A, B, D, E, and F,
Tnw = (0.22 + 0.18 + 0.21 + 0.46 + 0.35)(0.95) = 1.349 min
For the cycle, Tn = 1.349 + 0.68 = 2.029 min
(b) Tstd = 1.349(1 + 0.15) + 0.68(1 + 0.30) = 1.551 + 0.884 = 2.435 min
(c) Worker performance Pw = 100% for 7.25 hr worked during an 8-hour
shift
Tc = 1.349/1.00 + 0.68 = 1.349 + 0.68 = 2.029 min
Q = 7.25(60)/2.029 = 214.4 rounded to 214 pc
(d) Hstd = 214(2.435)/60 = 8.685 hr, and Ew = 8.685/8.0 = 1.086 = 108.6%