Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Task Name Start Finish Duration

Mode -1 8 16 24 32 40 48 56 64 72 80 88
1 BOBBY BROWN-YAS MALL ABU DHABI Wed 08/03/17 Sun 30/04/17 46 days
2 GENERAL REQUIREMENTS Wed 08/03/17 Sat 08/04/17 27 days
3 Receive notice to proceed and sign contract Wed 08/03/17 Wed 08/03/17 0 days
4 Receive advance payment Wed 08/03/17 Wed 08/03/17 0 days
5 Prepration of Architectural and MEP drawings Tue 14/03/17 Sun 19/03/17 5 days
6 Submission of shop drawings Sun 19/03/17 Sun 19/03/17 1 day
7 Approval of drawings Mon 20/03/17 Thu 23/03/17 4 days
8 Submission of Materials samples Sat 25/03/17 Sat 25/03/17 1 day
9 Approval of material samples Sun 12/03/17 Mon 20/03/17 8 days
10 Obtain work permit Sun 19/03/17 Thu 23/03/17 5 days
11 PRODUCTION/PROCUREMENT SCHEDULE Wed 22/03/17 Sat 08/04/17 15 days
12 Procurement of local/long lead items Wed 22/03/17 Thu 30/03/17 8 days
13 Delivery of items Sat 01/04/17 Sat 08/04/17 7 days
14 SITE WORKS Thu 23/03/17 Sun 30/04/17 33 days
15 SITE MOBILIZATION Thu 23/03/17 Sat 25/03/17 2 days
16 Setting up the site with all necessary requirements Sat 25/03/17 Sat 25/03/17 1 day
17 Installation of hoardings Thu 23/03/17 Thu 23/03/17 0 days 23/03
18 Site mobilization complete Thu 23/03/17 Thu 23/03/17 1 day
19 MEP WORKS Sat 25/03/17 Mon 17/04/17 21 days
20 Electrical works-Power Sat 25/03/17 Wed 12/04/17 17 days
21 Fire alarm works Sat 25/03/17 Thu 13/04/17 18 days
22 Fire fighting works Sun 26/03/17 Sun 16/04/17 19 days
23 HVAC Ducting works Tue 28/03/17 Wed 12/04/17 14 days
24 FITOUT WORKS Thu 23/03/17 Tue 25/04/17 29 days
25 Flooring finishes Sat 01/04/17 Tue 11/04/17 10 days
26 Wall finishes Wed 29/03/17 Sun 23/04/17 22 days
27 Ceiling finishes Mon 17/04/17 Mon 24/04/17 7 days
28 MISCALLANEOUS WORKS Sat 01/04/17 Tue 25/04/17 22 days
29 Electrical works-Lighting Tue 04/04/17 Thu 13/04/17 9 days
30 Installation of Signage Thu 06/04/17 Sat 08/04/17 2 days
31 Application of paint Wed 08/03/17 Thu 16/03/17 8 days
32 FINAL ACCEPTANCE Mon 24/04/17 Sun 30/04/17 6 days
33 Snagging Tue 25/04/17 Sun 30/04/17 5 days
34 Final inspection Sat 29/04/17 Sun 30/04/17 2 days
35 Handing over Sun 30/04/17 Sun 30/04/17 0 days
36 Note:Above program will carryout as per site conditions Tue 14/03/17 Tue 14/03/17 1 day
and subject to all operational approvals

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: BOBBY BROWN Split External Tasks Inactive Summary Manual Summary Progress
Date: 09/03/2017
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
88 96 104 112 120 128 136 144 152 160 168 176 184 192 200 208 216 224 232 240 248 256 264

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: BOBBY BROWN Split External Tasks Inactive Summary Manual Summary Progress
Date: 09/03/2017
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2

You might also like