Safe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS)
ORGANISATION DETAILS
PROJECT DETAILS
Switch off and Lock + Electrical Shock Fatality -Switching will be done by Amco personnel USJ Supervisor,
Tagging the main supply -Double lock will be used (1 from Amco and 1 from -AMCO Safety Dept.
to bailing machine, LEV USJ supervisor)
system, shredder & -Tagging must be used and sign by both party
blower machine & all
electrical equipment such
as lighting,etc
Testing of all electrical Fall from Ladder Broken Bones, Fatality -Use of A frame ladder & certified by Amco USJ Supervisor,
equipment that had been personnel -AMCO Safety Dept.
lock (To ensure zero -Safe use of Ladder Toolbox meeting conducted to
energy before the the all workers before start work
other task can be started)
Electrical Shock Fatality -Use of Multitester for all the incoming cable at the USJ Supervisor,
bailing,LEV & shredder machine Control panel. No
test pen is allowed
Slip Trip & Fall Broken Bones, Fatality Ensure the housekeeping had been done before USJ Supervisor,
commencing any task,
Ensure the working area is free from slip,trip & fall
hazard
Dismantling all the control Ergonomic Backache Heavy item to be lift by 2 people USJ Supervisor,
panels,electrical fitting &
cables
Sharp object from the Cut,hand injury Use of Anti cut Glove Level 5 USJ Supervisor,
cable,electrical fitting/ Use
of knife to cut the cable
Slip Trip and Fall Injury Ensure the housekeeping is maintain all the time USJ Supervisor,
Fall from Ladder Broken Bones, Fatality -Use of A frame ladder & certified by Amco USJ Supervisor,
personnel AMCO Safety Dept.
-Safe use of Ladder Toolbox meeting conducted to
all workers before start work
This SWMS has been developed in consultation and has been read, understood and signed by all workers undertaking the scope of works: