MECHANICAL

LOCO No.-13383 WDG3A 5RV


Schedule particular
PIC 13.11.07 POH 13.07.16-PR
M-24 05.08.18 TS 30.11.18 LSO

DATE Sch. Repair


L-4, 5, 8 Cam shaft changed. & cam eye DPT cut out. R-5 cylinder
05.08.18 M-24
head changed as leak of hole given smoke. Load box carried out.
16.08.18 GI Schedule carried out.
R-1 Lifter removes & fit with new pump (due to lifter phasing
plate & pump broken found) R-8 Lifter remove & fit (due to
01.09.18 TS exhaust roller pitted) overhaul R-1, 8 Lifter work completed with
tappet phasing carried out. L-4 High pressure tube changed. L-7
Fuel pump changed as rack jam. Measuring valve changed.
R-5,6,7& L5,6,7 Lifters remove as metal found overhaul lifters
27.09.18 TS fitted work completed with tappet phasing carried out.MR-1 ADC
CHNAGED.
Line massage lube oil drain out from lube oil sump abnormal
14.10.18 FAILURE
sound from engine block
R-8 LINER PISTON BROKEN & DAMAGE AS INTHIS LOCO. LOCO
29.10.18 M-2 NO. 13472 3RV M-24 SCHEDULE DUE BLOCK FITTEED NO. 2614
Load box carried out.
02.11.18 FAILURE Line massage D/E/L Side cylinder no.8 water drain out.
DR. Booking Low water indication LOCO shut down .Cylinder n0.8
with head water leakage attended by M.H QU STAFF. FUEL
SECONDARY FILTER CHANGED. Lube oil priming carried out.
06.11.18 TS
FOUND L-1 cylinder water riser pipe leakage attended. BY M.H
QU Left side riser + bubble collector dresser attended & made BY
M.H QU
L-7 Cylinder dummy as H.P. line tube broken changed. at COR
Checked ok Water glow rod changed as dirty bleed test carried
30.11.18 TS
out by QU STAFF . FUEL PRIMARY FILTER CHANGED.+FUEL
SECONDARY FILTER CHANGED. AS DUE.