WORK SCHEDULE at Unit-3 Area: (Working Time)
WORK SCHEDULE at Unit-3 Area: (Working Time)
WORK SCHEDULE at Unit-3 Area: (Working Time)
December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Working Time]
Start: 7:00 7:00 7:00 7:00 7:00 7:00 7:00 0:00 0:00 0:00 0:00 0:00 0:00 0:00 0:00 00.00 00.00 00.00 00.00 00.00
Finish: 18:00 18:00 18:00 18:00 18:00 18:00 24:00 24:00 24:00 24:00 24:00 24:00 24:00 24:00 24.00 24.00 24.00 24.00 24.00 24.00
[Work Schedule]
1 Preparation Work
D/G house Construction (Fuel tank Plan
1
Foundation) Act
Plan
2 Excavation Work (Up to GL -2.5m)
Act
Temporary Drainage Construction Plan
3
(excavation work) Act
Temporary Drainage Construction (Stone Plan
4
masonry work) Act
Plan
5 Water Pipe Installation
Act
2 Test Piling Works
Plan
1 Static Load test 600-2
Act
Dismantling Main beam, cross beam and Plan
2 concrete block at loading test 1200-1
Act
Mobilize Main beam & Cross beam to Plan
3 Pcs 36
loading test 600-2 Act
Concrete block, Main & Cross beam Plan
4
arrangement for Loading test 600-2 Act
Plan
5 Rebar Fabrication
Act
Plan
6 Bentonite Plant Erection (Silo & Pipe line)
Act
Plan
7 Drilling & Concreting for Test Pilling work
Act
4 Temporary Office Work 1 ls
5 Temporary Access Road Work 1 ls
6 Soil Investigation 1 ls
Plan
1 Well pumping test (Pump Pit area)
Act
Plan
2 Soil Investigation (Turbine Area)
Act
Transportation Boring Rig to South Slope Plan
3
Area Act
Plan
3 Soil Investigation (South slope area)
Act
1/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation
December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
2/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation
December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Construction Equipment]
1 Mobile Crane(150 ton) Unit 1 1 1 1
2 Crawler Crane(35 ton) Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Crawler Crane(50 ton) 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Generator Set 250kVA Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Excavator Unit 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
5 Drilling Machine (For Soil Investigation) Unit 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Drilling Machine (For Bore Pile) Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Truck Mixer Unit 0 0 0 0 0 4 4 4 4 4 4 4 4 4 4 4 4 4
7 Dump Truck Unit 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
8 Pick Up Truck or Trailer Unit 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
9 Light Vehicle Unit 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
[Manpower]
1 Manager person 1 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2
2 Engineer person 1 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5
3 Supervisor person 1 7 7 7 7 7 7 5 5 5 5 5 5 5 5 5 5 5 5 5
4 Safety Officer person 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
5 Surveyor person 1 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4
6 Mechanic / Electrician person 1 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6
7 Foreman person 1 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5
8 Skilled Worker person 5 6 6 6 6 6 6 5 5 5 5 5 5 5 5 5 5 5 5 5
9 Worker person 15 53 53 53 53 53 53 63 63 63 63 63 63 63 63 63 63 63 63 63
10 Driver/Operator person 22 22 22 22 22 22 22 27 27 27 27 27 27 28 28 28 28 27 27 27
11 Security person 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
SUBTOTAL 33 114 114 4 114 114 114 114 129 129 129 129 129 129 130 130 130 130 129 129 129
3/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation
January-2009 February-2009
[Work Schedule]
1 Lifting Work
Lifting Diesel Generator set (2 units) Plan
1
including oil tank (2 units) in foundation Act
Plan
2 Lifting Genset House Rafter to support
Act
Plan
3 Install Roofing
Act
2 Piping Work
Plan
1 Fuel pipe installation from Tank to DG
Act
Plan
2 Return fuel pipe installation from DG to Tank
Act
3 Grounding
Plan
1 Installation grounding
Act
4/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation
January-2009 February-2009
[Manpower]
1 Manager person 1 1 1 1
2 Engineer person
3 Supervisor person 1 1 1 1
4 Safety Officer person 1 1 1 1
5 Surveyor person
6 Mechanic / Electrician person 1 1
7 Foreman person
8 Skilled Worker person 1 1 1 1
9 Worker person 4 4 4 4
10 Driver/Operator person 1 1 1 1
11 Security person
SUBTOTAL 0 0 0 0 0 0 0 9 10 10 9 0 0 0 0 0 0 0 0 0 0