SUNWAY CONSTRUCTION SDN BHD

INSPECTION CHECKLIST

PROJECT : SUNWAY SERENE DESCRIPTION OF JOB : Inspection Checklist of Public Address System
TYPE OF EQUIPMENT TESTED :
LOCATION : DRAWING REF NO :

GRIDLINE : DATE :

ACTIVITY/TEST GRIDLINE
N/A N/A N/A N/A N/A N/A
Cable
Wiring
Termination
Equipment
Intensity
Sensitivity (dB
SPL)
Sound Pressure
Level (SPL)
Loudness
Attenuation over
Distance
Frequency (Hz)
Decibel
Masking
Reverbation
Equalization
Impendance
Reason for Failure/Re-inspection ;

AL ALLLOWED to proceed ALLLOWED to proceed


Name/Signature Designation; Date;
of Sub-Contractor Subcon
Representatives
Name/Signature Designation; Date;
of Main Contractor SunCon
Representatives
Name/Signature Designation; Date;
of Client’s
Client’s Consultant
Consultant
Representatives

Status Of Inspection: _ = Acceptable , X = Not Acceptable, – = Not Applicable