Ref MS-MAC-1031
Revision 0
Method Statement
For
Trench excavation
PROJECT:
SAFETY
Contractor
Method statement for trench excavation
METHOD STATEMENT
TO : Mahindra Susten Company
Title :
Page 2 of 25
Method statement for trench excavation
Table of contents
1.0 Purpose
2.0 Scope
3.0 Planning and preparation
3.1 Consultation
3.2 Planning
3.3 Planning by Mashael Asser Contracting Est.
3.4 Planning by contractor
3.5 Hazard identification, risk assessment and control
3.6 Hierarchy of control measure
3.7 Preparation
3.8 Emergency and rescue procedure
Page 3 of 25
Method statement for trench excavation
4.14.4 Scaffolding
4.14.5 Fixed platforms, walkways, stairways and ladders
4.15 Works near traffic or moving plant
4.16 Noise
5.0 Inspection and maintenance of plant and equipment
5.1 Routine inspection
5.2 Repairs and maintenance
5.3 Reporting defects
5.4 Log book and inspection check list
6.0 Training and instruction
7.0 Personal protective equipment
7.1 Provision of PPE
7.1.1 Safety helmets
7.1.2 Eye protection
7.1.3 Personal hearing protection
7.1.4 High visibility garments/safety reflective vests
7.1.5 Safety gloves
7.2 Maintenance and use of PPE
8.0 Occupational health and safety
9.0 Risk assessment
10.0 Job safety analysis
Page 4 of 25
Method statement for trench excavation
1.0 Purpose
This method statement provides guidance to prevent injury to persons
engaged in excavation works.
2.0 Scope
Planning, preparation conduct and Method of excavation work.
3.2 Planning
Planning and preparation will be the first essential step in ensuring that
work is done safely. Planning and preparation will involve consultation
with all relevant persons engaged in the work and will include hazard
identification, risk assessment and risk control processes. Where
appropriate, the advice of a geotechnical engineer will be sought before
starting excavation work. The Mashael Asser Contracting Est. and the
Page 5 of 25
Method statement for trench excavation
Page 6 of 25
Method statement for trench excavation
Page 7 of 25
Method statement for trench excavation
associated with excavation work, the risk assessment and the risk control
measures will be documented.
The process of hazard identification, risk assessment and control is made
up of the following steps:
1. Identification of hazard
2. Assess the risk(s) arising from the hazards.
3. Use appropriate control measures to eliminate or reduce the
risk(s).
4. Monitor and review the control measures to ensure continual
safety.
After identifying the hazards involved in carrying out the work the Mashael
Asser Contracting Est. in consultation with the contractor will assess the
health and safety risks and determine what type of safeguards or systems of
work will be implemented to ensure the health and safety of all persons on
site. This will always include eliminating exposure of persons to the hazard.
The control measures at Level 1 (eliminate the hazard) give the best results
and will be adopted. The measures at Levels 2 (minimize the risk) and 3 (other
controls) are less effective and they require more frequent reviews of the
hazards and systems of work. In some situations a combination of control
measures may need to be used.
The control measures recommended by the contractor will be considered by
the Mashael Asser Contracting Est. as part of the health and safety
Page 8 of 25
Method statement for trench excavation
3.7 Preparation
When preparing for the commencement of work the Mashael Asser
Contracting Est. and the contractor doing the work will ensure that the
workplace is safe based on the health and safety management plan. They will
also check to ensure that all controls identified by the risk assessment have
been put in place and that no new hazards exist.
Preparation will also at least include:
a) An assessment of climatic/environmental conditions.
b) Access to and from the workplace.
c) Specific instructions for employees.
d) That plant and equipment is suitable for the intended use and
inspected by a third party before use and is properly
maintained.
e) Personal protective equipment.
f) That the location of underground, above ground and overhead
services are identified and clearly marked.
g) Emergency and rescue procedures in the event of an accident,
injury or other emergency, including the means of protect any
other persons in the vicinity.
The contractor will plan for such matters and ensure that appropriate control
measures are in place. The risk assessment will take into account the
following factors:
a) Nature of hazard and possible emergencies;
b) Size and location of place of work;
c) Number and mobility of persons at the workplace; and
d) Location of nearest emergency services.
Control measures may include:
a) Development and communication of a warning system.
b) Development and communication of safe and rapid
evacuation procedures, including injured persons.
Page 9 of 25
Method statement for trench excavation
Page 10 of 25
Method statement for trench excavation
Removal of soil from an excavation causes unbalanced soil stresses which reduce the capacity of
the excavation to support itself. There may be additional geotechnical engineering issues that will
be considered. Accordingly where the risk assessment identifies the risk of an unstable condition,
the following measures will be considered before starting excavation work:
Shoring systems, benching and battering are engineering issues that involve both structural design
and soil mechanics. The use of adequate shoring, benching and battering is essential to control the
risk of a collapse or failure of a trench or open excavation.
Page 11 of 25
Method statement for trench excavation
4.3 Shoring
Where necessary, all trenches and excavations will be adequately shored or
supported to prevent a fall or dislodgement of earth, rock or other material
forming the side of or adjacent to, any excavation work from burying, trapping or
striking a person that is in the excavation. Where such a risk also exists for those
installing supports, other appropriate control measures will be in place to
ensure the safety of persons entering the excavation. A shoring system will not
be required if, having regard to the nature and slope of the side of the excavation
and other relevant circumstances there is no reasonable likelihood that earth,
rocks other material will fall or dislodge from a height of more than1.5m and
bury, trap or strike a person that is in the excavation. The risk assessment process
will be used to identify unstable conditions and the risks involved. Shoring the
face of an excavation will proceed as the work of excavation progresses. Where a
mechanical digger is used, the risk assessment will be used to determine whether
any part of the trench may be left unsupported. Shoring may include any suitable
system of temporary supports and sheeting material used to maintain the
stability of the sides of an excavation. The installation and removal of shoring will
take place from outside an excavation.
Page 12 of 25
Method statement for trench excavation
The control measures implemented will be appropriate and effective for the
hazards and risks of the situation. Consideration will be given to factors such as
how long the excavation will be open, and who may gain access to the
excavation. The following control measures will be considered:
Page 13 of 25
Method statement for trench excavation
Signs will be erected around the site showing the name and contact telephone
number (including afterhours emergency number) of the Mashael Asser
Contracting Est./contractor emergency numbers.
Page 14 of 25
Method statement for trench excavation
work. The contractor will allow for inaccuracies and the possibility of other
unknown or hidden services.
Further, the Mashael Asser Contracting Est. will arrange for these services to be
clearly marked according to the available plans and on site checks prior to
commencement of work. Services will be exposed at sufficient intervals to
positively identify their location and/or lie. The following are ways of checking for
underground services:
All persons whose work may be affected by an underground service will be advised of the location
of every underground service.
Appropriate control measures will be implemented after consultation with relevant service
providers. These measures may include the protection, support or removal of services to ensure
safety of workers.
In assessing the risk, measures such as the following will be considered before
starting excavation work:
The contractor will also ensure the stability of vehicular access which might be affected by the work.
Page 15 of 25
Method statement for trench excavation
Where the risk assessment has identified a risk of collapse as a result of loads or
materials above or near the excavation, shoring will be in place before any
person enters the excavated area.
The following measures will also be considered before starting excavation work:
a) Controlling access to exclude persons from hazardous areas, eg relocating
means of access
b) Moving and storing loads outside the zone of influence of the excavation
c) Provision of wheel stoppers to limit movement of mobile equipment adjacent
to the excavation
d) Reducing the number of trench shields stored near excavation by pulling
along trench shields and backfilling as the excavation progresses.
e) Securing all loose materials in place. When working on a slope, a risk
Page 16 of 25
Method statement for trench excavation
As far as practicable, loads will not be suspended or travel over a person. The following
control measures will be considered:
a) Fences
b) Hand rails and toe boards
c) Overhead protection
d) Enclosed walkways
e) Safety helmets and other adequate means of protection
f) Provision of safe means of lowering and raising plant, materials, spoil, etc
g) Use of lanyards to secure loose tools
h) Loads will be lifted/suspended within the safe working limits of the machinery load
used.
Page 17 of 25
Method statement for trench excavation
The contractor will assess and control the risks involved in carrying out manual
handling tasks. This will be done in consultation with employees who are
required to carry out the work.
4.14 Access
An assessment of access requirements will take into account the number of
persons using them and any tools and equipment that they may be required to
carry to and from the work site.
Page 18 of 25
Method statement for trench excavation
4.14.1 Lighting
Adequate lighting (natural or artificial) will be provided to ensure the
work areas and access ways are well lit. Adequate local lighting will be
provided for detailed work, for dangerous processes and where
machinery is being operated. When artificial lighting is used, including
lighting for night work, the contractor will ensure it does not create
excessive glare or shadows.
4.14.2 Ramps
When access ramps are provided they will not exceed 1:2.7 (20 degrees).
Ramps steeper than 1:8 (7 degrees) will be cleared, grated or have
surfaces which allow adequate foot grip. Where such ramps form part of
an excavation, a risk assessment will be conducted to determine the
maximum safe soil height above the ramp before some sort of soil
support (eg trench shield) is provided. Ramps will be designed and
constructed to effectively withstand any anticipated load that they may
be required to support during use.
4.14.3 Ladders
When ladders are used for access the contractor will provide the following:
a) The ladder will be secured at both top and bottom against
displacement. Ladders will have non-slip feet and whenever
practicable will be set up at an angle of 1:4 (75degrees).
b) A safe and adequately sized landing place when stepping off the
ladder will be provided.
c) The stiles of the ladder will extend at least one meter above the
landing place.
d) Metal or wire reinforced ladders will not be used where there is a risk
of contact with electrical conductor wires(power lines) or of electric
shock. Non- conducting ladders will be used or a clearance of at least
4metres from conductors will be maintained.
Page 19 of 25
Method statement for trench excavation
4.14.4 Scaffolding
Scaffolding will be used to provide workers with a safe temporary
work platform. It will be planned, erected, inspected and tagged by
competent persons and will be regularly inspected to ensure there are
no risks to safety and will comply with the requirements of HSE
regulations.
Page 20 of 25
Method statement for trench excavation
f) The use of audible reversing alarms and/or other technologies or other safe
work practices. Note: reversing
g) Aalarms may cause confusion where multiple plant is using the same area and
other systems of work may be required.
h) Minimizing the number of moving plant working at one time. Where multiple
plant is being operated around the work site a competent person will be used
to direct the plant:
i) When operating in close proximity to each other;
j) When reversing;
k) Where persons are on the ground; and
l) In other situations as indicated by the risk assessment.
m) Where construction vehicles or plant enter or leave the work area by public
roads, systems of control and notices will be placed at all entrances and exits
to the work area to protect and warn all persons approaching or in the vicinity
n) Where plant is being operated near persons, near underground or above
ground services (any other workers, soils technicians, surveyors, visitors etc)
o) Designated delivery and turning areas. The movement of delivery vehicles on
construction sites frequently
p) Presents a hazard particularly when reversing, loading and unloading.
4.16 Noise
Noise management provisions will be carried out by the contractor doing the
work and will ensure noise levels from machinery or equipment being used do
not become a risk to hearing or health.
Page 21 of 25
Method statement for trench excavation
The contractors will ensure that all necessary prevention or protection measures
are taken to ensure the health and safety of persons who may be exposed to
excavated material.
The risk assessment process will be used to determine the engineering controls,
work practices and site, atmospheric monitoring required.
The contractor will also ensure that exposure to nonhazardous substances such
as nuisance dust is at a level not greater than that established by safe exposure
standards. In dry conditions, frequent watering, where practicable, or other
similar methods will be used to reduce nuisance dust that will not exceed
20mg/m3.
Page 22 of 25
Method statement for trench excavation
All plant such as excavators, tractors, etc used for lifting will have their safe working
loads displayed and maintained. If the function or condition of plant represents an
immediate risk to health and safety, operation will cease and the plant will be
withdrawn from use until a risk assessment and appropriate control measures are
implemented.
Page 23 of 25
Method statement for trench excavation
The training provided and the instruction given will at least include:
a) Induction training which complies with Construction Safety & HSE regulation
b) The work method to be used for the excavation or associated work and the manual
handling procedures for the work to be carried out, including control measures based on the
risk assessment to prevent injury.
c) The correct use, care and storage in accordance with the manufacturer’s
recommendations where appropriate, of:
d) Personal protective equipment; and
e) Tools and equipment to be used.
f) The use of plant and associated equipment, including electrical safety and
hazardous substances.
g) Procedures to be adopted in the event of accident, injury or other emergency,
including evacuation.
Page 24 of 25
Method statement for trench excavation
Page 25 of 25