Project Resources: Double - Storey Bungalow

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

PROJECT RESOURCES

Task Name unit quantity group of production rate duration 5% risk estimated duration Estimation
work day
Double -Storey
Bungalow
Project Start
Preliminary
Work
Performance
Bond
Insurance
Monthly Report

Monthly 25 1 20 1.25 0.06 1.31 2


Report 1

Survey Work m2 250 1 80 3.13 0.16 3.129 4


2
Site Clearing m 150 1 15 10.00 0.50 10.50 11
Excavation
Work
Remove Top Soil m2 1500 2 190 3.95 0.20 4.14 5
Pad Footing m3 30 3 35 0.29 0.01 0.30 1
Excavation
Task name unit quantity Group of production rate duration 5% risk estimated estimation
work duration
Building Work
Ground Floor
Substructure
Foundation
Pad Footing
Formwork m2 650 2 103 3.16 0.16 3.31 2
Reinforcement kg 700 3 50 4.67 0.23 4.90 2
Concrete Work m3 685 3 120 1.90 0.10 2.00 3
Dismantle of m2 1000 5 50 4.00 0.20 4.20 5
Formwork
Column Stump
Reinforcement kg 110 3 350 0.10 0.01 0.11 1
Formwork m2 89 2 200 0.22 0.01 0.23 1
Concrete Work m3 100 2 11 4.55 0.23 4.77 5
Dismantle of m2 55 3 140 0.13 0.01 0.14 1
Formwork
Task name unit quantity Group of production duration 5% risk estimated estimation
work rate duration
Superstructure
Beam (GF)
Formwork m2 1740 3 150 3.87 0.19 4.06 5
Reinforcement kg 1960 3 250 2.61 0.13 2.74 3
Concrete Work m3 1467 2 400 1.83 0.09 1.93 2
Dismantle of m2 1350 2 150 4.50 0.23 4.73 5
Formwork
Slab (GF)
Reinforcement kg 3564 5 330 2.16 0.11 2.27 3
Concrete Work m3 4500 5 450 2.00 0.10 2.10 3
Column (GF)
Reinforcement kg 658 3 150 1.46 0.07 1.54 2
Formwork m2 768 2 210 1.83 0.09 1.92 2
Concrete Work m3 445 3 230 0.64 0.03 0.68 1
Dismantle of m2 338 2 130 1.30 0.07 1.37 2
Formwork
Brickwork Wall
Ground Floor
Internal m2 699 2 150 2.33 0.12 2.45 3

External m2 699 2 150 2.33 0.12 2.45 3


Task name unit quantity Group of production duration 5% risk estimated estimation
work rate duration
First Floor
Superstructure
Beam (1F)
Formwork m2 453 2 120 1.89 0.09 1.98 2
Reinforcement kg 450 3 125 1.20 0.06 1.26 2
3
Concrete Work m 448 2 140 1.60 0.08 1.68 2
Dismantle of m2 250 2 160 0.78 0.04 0.82 1
Formwork
Slab (1F)
Reinforcement kg 455 2 170 1.34 0.07 1.41 2
3
Concrete Work m 353 1 170 2.08 0.10 2.18 2
Column (1F)
Reinforcement 440 2 150 1.47 0.07 1.54 2
2
Formwork m 500 2 140 1.79 0.09 1.88 2
Concrete Work m3 510 2 120 2.13 0.11 2.23 3
2
Dismantle of m 320 1 230 1.39 0.07 1.46 2
Formwork
Brickwork
Wall (1F)
Internal m2 521 2 245 1.06 0.05 1.12 2
External m2 521 2 245 1.06 0.05 1.12 2
Staircase
Reinforcement kg 360 2 125 1.44 0.07 1.51 2
Formwork m2 85 2 120 0.35 0.02 0.55 1
Concrete Work m3 150 2 140 0.54 0.03 0.57 1
Dismantle of m2 60 1 150 0.40 0.02 0.42 1
Formwork
Task name unit quantity Group of production rate duration 5% estimated estimation
work risk duration
Roof
Roof Beam
Formwork m2 450 2 120 1.88 0.09 1.97 2
Reinforcement kg 552 2 110 2.51 0.13 2.63 3
Concrete Work m3 525 2 130 2.02 0.10 2.12 3
2
Dismantle of m 234 1 150 1.56 0.08 1.64 2
Formwork
Roof Trusses m2 990 3 90 3.67 0.18 3.85 4
Roof Coverings m2 990 3 90 3.67 0.18 3.85 4
Architectural Work
Window and
Door
Installation
Window And Door no 28 2 90 0.16 0.01 0.17 1
Frame
Window And Door no 28 2 90 0.16 0.01 0.17 1
Leaf
Wall
Finishing m2 2500 6 50 8.33 0.42 8.75 9
2
Painting m 2500 4 90 6.94 0.35 7.29 8
Floor Finishes
Waterproofing m2 250 3 45 1.85 0.09 1.94 2
Cement Render m2 250 3 20 4.17 0.21 4.38 5
Floor Tiles m2 85 2 62 0.69 0.03 0.72 1
Task name unit quantity Group of production rate duration 5% risk estimated estimation
work duration
Infrastructure
Work
M&E
Electrical
Ground Floor
342 1 90 3.80 0.19 3.99 4
First Floor 260 1 90 2.89 0.14 3.03 4
Plumbing
Ground Floor 200 1 70 2.86 0.14 3.00 3
First Floor 100 1 70 1.43 0.07 1.50 2
External Work
Fencing and m2 250 1 80 3.13 0.16 3.29 4
Gate
Concrete m3 5 1 50 0.10 0.01 0.11 1
Driveway
Sewerage 80 1 50 1.60 0.08 1.68 2
Road and 90 1 60 1.50 0.08 1.58 2
Drainage
Testing/ m2 250 1 160 1.56 0.08 1.64 2
Inspection/
Handover
Project Finish