Bar Bending Schedule for Tie Beams/Strap Beams:-

Bar Bending Schedule Plays a vital role in finding the quantities of the
reinforcement required for the building. Well, In order to understand the tie
beam/Strap beam reinforcement in Substructure, I refer you to learn the
Bar Bending Schedule for footings.

Tie Beam and Strap Beam:-

Tie Beam (Straight beam) is a beam which connects the two footings in
the substructure. Tie beam is provided when the two footings are in the
same line. Strap Beam(inclined beam) is similar to tie beam but it
connects two footings at a certain angle. Strap beam is laid when two
footings are in different levels. Tie beam/ Strap beam are specifically
located between pile caps and shallow foundations. their primary function is
to force all shallow foundations or pile caps to have approximately the
same settlements.
Quantity of reinforcement (steel) required for Tie Beam/ Strap beams
or Bar bending schedule for Tie Beam/ Strap Beam:-

In this post, I am finding out the Estimation of Steel reinforcement in Tie


Beam or Strap Beam / Bar Bending Schedule for Tie Beam/ Strap beam.
For this, I considered a plan as shown below.

The horizontal bars which ties one footing to the other footing are main
bars and the vertical bars are called stirrups. Stirrups helps in framing the
main bars in correct position.

Before getting into this article I recommend you to remember these


Important Points to understand the reinforcement in tie beams:-

1. Main Bars (Top bar, Bottom bar, Side bar) are tied to the center the of
one footing to the center of another footing.
2. Whereas stirrups starts from one face of footing to the another face of
footing. Refer the below image for clear view how reinforcement is
tied in Tie beam.

Steps to be followed while finding out the total wt. of steel required
for constructing Tie beams / Strap beams:-

Tie beam reinforcement calculation is divided into two parts Main bars and
stirrups.

Part-I:- Main Bars

1. Check the Length of Main bars in top, bottom, side bars.


2. Then Check the No. of Main bars in top, bottom, side bars
3. Check the Diameter of Main bars in top, bottom, side bars
4. Calculate the total length of Main bars in top, bottom and side
direction.
5. Find the total wt of Main bars.

Part-II:- Stirrups

1. Deduct the concrete cover from all sides of tie and find out the
length of stirrup.
2. Calculate the length of stirrup including hook.
3. Calculate the total no. of stirrups.
4. Find the total length of stirrups
5. Then Calculate the total wt. of stirrups.

Length, Dia and No. of Bars are adopted and designed by the structural
engineer by executing the load analysis.

Consider the below shown Figure.


Assume for calculation:-

Dia of Top Bars = 10mm, Dia of Bottom bars = 10mm ,Dia of Side bars =
8mm, Dia of Stirrups = 6mm, Spacing between ties = 0.1m.
No. of Top Main bars = 4, No. of Bottom Main bars = 4 , No. of Side Main
bars = 2

Calculation for the Quantity of Tie beams (Main Bars):-

All beams in horizontal axis are all Tie beams except the beam between F5
and F6.

Treat all the beams are tie beams, as the direct value of length of beam is
already given for all. If the length of Strap beam isn’t given then obtain the
Length of Strap beam by using Pythagorean theorem,

Hyp^2 = Adj^2+ Opp^2

Hypotenuse = length of strap beam.

From the figure,

Part- I. Calculate the Total wt required for Main bars


Apply the above method for all the tie beams in Horizontal and the vertical
axis. the result of all tie beams have been entered in the below table.
Calculation for the quantity of Tie Beams (Stirrups):-

As I have already mentioned that Stirrups are started from one face of
footing to the another face footing.

Tie Beam on Axis I between A-B:-

Below are the five steps for finding the quantities of Tie beam (Stirrups)

1. Deducting the concrete cover from all sides of the tie beam for
finding out the length of each tie
From the figure, it implies that reinforcement details of Tie beams
in horizontal axis and vertical axis are different.

As per the condition deduct the concrete cover of 0.05 from all
sides of stirrups for Horizontal axis tie beams and 0.025 from all sides
of stirrups for Vertical axis tie beams
Apply the above method for remaining tie beams. The result is mentioned
below. Check you result with the below table.

Abstract For Finding out the total quantity of Steel reinforcement


required for Tie Beam/Strap Beam for the above given plan:-

Hence, Total wt of Steel 512.81 Kgs required for Tie beam/Strap Beam (for
above plan).