Bar Bending Schedule Plays a vital role in finding the quantities of the
reinforcement required for the building. Well, In order to understand the tie
beam/Strap beam reinforcement in Substructure, I refer you to learn the
Bar Bending Schedule for footings.
Tie Beam (Straight beam) is a beam which connects the two footings in
the substructure. Tie beam is provided when the two footings are in the
same line. Strap Beam(inclined beam) is similar to tie beam but it
connects two footings at a certain angle. Strap beam is laid when two
footings are in different levels. Tie beam/ Strap beam are specifically
located between pile caps and shallow foundations. their primary function is
to force all shallow foundations or pile caps to have approximately the
same settlements.
Quantity of reinforcement (steel) required for Tie Beam/ Strap beams
or Bar bending schedule for Tie Beam/ Strap Beam:-
The horizontal bars which ties one footing to the other footing are main
bars and the vertical bars are called stirrups. Stirrups helps in framing the
main bars in correct position.
1. Main Bars (Top bar, Bottom bar, Side bar) are tied to the center the of
one footing to the center of another footing.
2. Whereas stirrups starts from one face of footing to the another face of
footing. Refer the below image for clear view how reinforcement is
tied in Tie beam.
Steps to be followed while finding out the total wt. of steel required
for constructing Tie beams / Strap beams:-
Tie beam reinforcement calculation is divided into two parts Main bars and
stirrups.
Part-II:- Stirrups
1. Deduct the concrete cover from all sides of tie and find out the
length of stirrup.
2. Calculate the length of stirrup including hook.
3. Calculate the total no. of stirrups.
4. Find the total length of stirrups
5. Then Calculate the total wt. of stirrups.
Length, Dia and No. of Bars are adopted and designed by the structural
engineer by executing the load analysis.
Dia of Top Bars = 10mm, Dia of Bottom bars = 10mm ,Dia of Side bars =
8mm, Dia of Stirrups = 6mm, Spacing between ties = 0.1m.
No. of Top Main bars = 4, No. of Bottom Main bars = 4 , No. of Side Main
bars = 2
All beams in horizontal axis are all Tie beams except the beam between F5
and F6.
Treat all the beams are tie beams, as the direct value of length of beam is
already given for all. If the length of Strap beam isn’t given then obtain the
Length of Strap beam by using Pythagorean theorem,
As I have already mentioned that Stirrups are started from one face of
footing to the another face footing.
Below are the five steps for finding the quantities of Tie beam (Stirrups)
1. Deducting the concrete cover from all sides of the tie beam for
finding out the length of each tie
From the figure, it implies that reinforcement details of Tie beams
in horizontal axis and vertical axis are different.
As per the condition deduct the concrete cover of 0.05 from all
sides of stirrups for Horizontal axis tie beams and 0.025 from all sides
of stirrups for Vertical axis tie beams
Apply the above method for remaining tie beams. The result is mentioned
below. Check you result with the below table.
Hence, Total wt of Steel 512.81 Kgs required for Tie beam/Strap Beam (for
above plan).