Task Identification Team member(s) responsible

assemble team members L. Mtolo,M.L Lituka


case scenario research Z. Zondi,M. Shelembe
identification of main problems M. Mkuzo,M.L Lituka
identification of stakeholder needs L. Mchunu,M. Mkuzo
identification of documentation required M. Shelembe,Z. Zondi
identification of critical tasks L. Mtolo,L. Mchunu
delegation of tasks L. Mtolo,M.L Lituka
analysis of requirements M.L Lituka,L. Mtolo
preliminary scope planning L. Mtolo,L. Mchunu
preliminary project schedule L. Mtolo,L. Mchunu
project scope statement planning M.L Lituka,M. Mkuzo
WBS M.L Lituka,L. Mtolo
budget estimation Z. Zondi,M. Shelembe
costs estimation M. Shelembe,Z. Zondi
allocation of finances Z. Zondi,M. Shelembe
allocation of resources M. Mkuzo,M.L Lituka
communication management plan L. Mtolo,L. Mchunu
documentation of phase events L. Mtolo,M.L Lituka
review of system documentation L. Mtolo,L. Mchunu
review of previous system problems Z. Zondi,M. Shelembe
review of implemented system solutions Z. Zondi,M. Shelembe
review of security implementation documentation M.L Lituka,M. Mkuzo
documentation of system review findings L. Mchunu,L. Mtolo
review of GPO settings L. Mtolo,L. Mchunu
review of security settings L. Mtolo,L. Mchunu
review of logical network layout M.L Lituka,M. Mkuzo
review and evaluation of workstations L. Mchunu,L. Mtolo
review and evaluation of servers M.L Lituka,M. Mkuzo
review of network resources Z. Zondi,M. Shelembe
Physical server requirements planning M.L Lituka,M. Mkuzo
workstation requirement planning L. Mchunu,L. Mtolo
network resources requirement planning Z. Zondi,M. Shelembe
server installation planning M.L Lituka,M. Mkuzo
client O.S deployment planning M.L Lituka,M. Mkuzo
physical and logical system protection planning M.L Lituka,M. Mkuzo
physical client installation planning Z. Zondi,M. Shelembe
network resources purchasing planning L. Mchunu,L. Mtolo
review of current floor plans Z. Zondi,M. Shelembe
review of current cabling schemes Z. Zondi,M. Shelembe
planning of new floor plans Z. Zondi,M. Shelembe
planning of new cabling schemes Z. Zondi,M. Shelembe
project schedule update L. Mtolo,L. Mchunu
documentation of phase requirements
budget allocation Z. Zondi,M. Shelembe
purchasing of all physical resource requirements M.L Lituka,M. Mkuzo
resource allocation M. Mkuzo,M.L Lituka
drawing of floor planning Z. Zondi,M. Shelembe
drawing of proposed cabling schemes
preparation of workspace Skype-Net Technicians
installation of communication lines Telkom
installation of network cabling Skype-Net Technicians
purchasing of network software M.L Lituka,M. Mkuzo
ordering of volume licensing L. Mtolo,L. Mchunu
planning of security policies L. Mtolo,L. Mchunu
installation and testing of sever hardware M. Mkuzo,M.L Lituka
installation of server software on virtual server M.L Lituka,M. Mkuzo
installation of workstations Skype-Net Technicians[1 Technical
installation (deployment) of client software M.L Lituka,M. Mkuzo
testing of virtual network M. Mkuzo,M.L Lituka
review of phase costs costs Z. Zondi,M. Shelembe
allocation of resources M. Mkuzo,M.L Lituka
documentation of phase requirements L. Mtolo,L. Mchunu
TOTAL

Team member Teriff per hour


L. Mtolo R 400.00
M.L Lituka R 350.00
M. Mkuzo R 300.00
M. Shelembe R 300.00
L. Mchunu R 300.00
Z. Zondi R 300.00
Time allocated per task Cost per task
per team member (task * tariff)

1 day R 750.00
1 day R 600.00
1 day R 650.00
1 day R 600.00
1 day R 600.00
1 day R 700.00
1 day R 750.00
2 days R 1,500.00
1 day R 700.00
1 day R 700
1 day R 650
2 days R 1,500.00
2 days R 600.00
2 days R 1,200.00
1 day R 600.00
2 days R 1,300.00
1 day R 700.00
1 day R 750.00
1 day R 700.00
1 day R 600.00
1 day R 600.00
1 day R 650.00
2 days R 1,400.00
1 day R 700.00
1 day R 700.00
1 day R 650.00
2 days R 1,500.00
2 days R 1,300.00
2 days R 1,200.00
2 days R 1,300.00
1 day R 700.00
1 day R 600.00
2 days R 1,300.00
1 day R 650.00
2 days R 1,300.00
1 day R 600.00
2 days R 700.00
1 day R 600.00
1 day R 600.00
1 day R 600.00
1 day R 600.00
1 day R 700.00
1 day
1 day R 600.00
2 days R 650.00
1 day R 650.00
2 days R 600.00
1 day R 50,000.00
4 days R 200,000.00
2 days R 16,000
2 days R 100,000
2 days R 1,300.00
1 day R 700.00
2 days R 1,400.00
1 day R 650.00
2 days R 1,300.00
2 days R 100,000.00
2 days R 1,300.00
5 days R 3,250.00
1 day R 600.00
1 day R 650.00
1 day R 700.00
R 515,450.00