Notice of Delay: PM Mccrann Construction and Trading
Notice of Delay: PM Mccrann Construction and Trading
Notice of Delay: PM Mccrann Construction and Trading
PROJECT : ALTA SPATIAL LAND DEVELOPMENT DPI – Inspector: Engr. Ivan Lorenz O. Aguilar
Engr. Edmar D. Lozano
Engr. John Errol Marcos
LOCATION : Karuhatan Road, Brg. Karuhatan,
Valenzuela City
This is due to your registered negative slippage of _ _which is over the 5% margin under exiting
DPI policy. Kindly submit your Catch – Up Schedule within Three (3) days after receipt of this notice.
Despite our previous notice, your slippage further dropped to – 9.54%, which is below the –15%
margin for second offense under the current DPI policy. Should you fail to implement corrective
measures, Contract Clause imposition will follow to protect DPI’s interest.
Please submit you Final Catch Up Program within three (3) days after receipt of this notice.