Daily Working Record

Name : PHAL Pisey


Month : Oct 2017
Date Contents Achievement Remark

1 Sun

2 Mon

3 Tue

4 Wed

5 Thu

6 Fri

7 Sat

8 Sun

9 Mon

10 Tue

11 Wed

12 Thu Understanding of cross-section.

Revise quantity of Roadway excavation


13 Fri
and Embankment from CAD to Excel.
Input the quantity of Roadway
14 Sat excavation and Embankment from CAD
into Excel.
15 Sun
Revise the size of median in cross-
16 Mon
section.
Revise the size of median in cross-
17 Tue
section.
Revise the size of median in cross-
18 Wed
section.
19 Thu Plot cross-section.
Revise Cross-section Sta.
20 Fri
39+880~42+820
Revise Cross-section Sta.
21 Sat
42+840~46+270
22 Sun
Find Area of Roadway Excavation,
23 Mon Embankment and Sub-grade. (CAD) 49
stations
Find Area of Roadway Excavation,
24 Tue Embankment and Sub-grade. (CAD) 58
stations
Draw shop drawing of Pipe Culvert
25 Wed
with diameter 1.0m (10 stations)
Draw shop drawing and Quantity of
26 Thu Pipe Culvert with diameter 1.0m (Detail Would finished by 28, Oct.
wingwall and apron)
Draw shop drawing and Quantity of
27 Fri Pipe Culvert with diameter 1.0m (Detail First check done by CAD operator.
wingwall and apron)
Revise shop drawing and Quantity of
28 Sat Pipe Culvert with diameter 1.0m (Detail Not yet finished.
wingwall and apron)
29 Sun

30 Mon

31 Tue