PERT CHART - LIMESTONE HANDLING SYSTEM

Start Date Days to Completion


10/15/2012 21.67
Finish Date
11/13/2012
Times (in Days)
Time Distribution: Triangular [42]

ID Task Name Predecessors O M P Duration ES EF LS LF Slack


(Enter one ID per cell) (min) (most likely) (max) (exp. time)
10 Start 0.00 0.00 0.00 0.00 0.00 0.00
20 Cable Laying 10 2 4 6 4.00 0.00 4.00 1.67 5.67 1.67
30 Field Instruments & 10 3 5 9 5.67 0.00 5.67 0.00 5.67 0.00
40 Field-IO-MCC side ter 20 30 4 5 7 5.33 5.67 11.00 5.67 11.00 0.00
50 DCS implementation 10 4 6 10 6.67 0.00 6.67 4.33 11.00 4.33
60 MCC-IO checking 40 50 4 5 7 5.33 11.00 16.33 11.00 16.33 0.00
70 All process signals che 40 50 3 4 8 5.00 11.00 16.00 16.67 21.67 5.67
80 All drives DCS trial a 60 3 5 8 5.33 16.33 21.67 16.33 21.67 0.00
90 Finish 70 80 0.00 21.67 21.67 21.67 21.67 0.00
[42]

9
Days:
0 5 10 15 20 25
Slack Flexible Critical ES Events 8
Start

7
Cable Laying

6
Field Instruments & JB mounting

Field-IO-MCC side termination 5

DCS implementation 4

MCC-IO checking
3

All process signals checking


2

All drives DCS trial after clearance


1

Weeks: Finish
0