Professional Documents
Culture Documents
Example 3
Example 3
Example 3
========
(The layout of this sewer network will only allow Dynamic Wave
flow routing to be used.)
1. After opening the file, note how the pump station is modelled
with a storage node and a Type4 pump. Bring up the Controls
Editor to view the rules that control the on/off status of the
pump.
2. Also view the hourly DWF time patterns that are assigned to
each node that receives DWF. The base-line DWF was set to 1.0
for these nodes, so the pattern multipliers are the actual flows
in this example.
4. Create one time series plot of water depth at the storage node
and another for flow in the pump. With both plots visible,
select Window | Tile so that they can both be viewed without
any overlap. See if the plots reflect the desired control rules.