Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Legally Speaking

Change Orders 201: Practical Tips and Tricks


by Joe Katz, Esq., Huddles Jones Sorteberg & Dachille, P.C.
In my construction litigation prac- Pricing Practice Tip #1
tice I have seen virtually every trick in A change order should always View all project occurrences through
the book concerning change orders include pricing to account for the a “change order lens” by assessing
practice: the good, the bad and the direct costs of the change, as well as the suitability of a change order in vir-
ugly. I want to highlight what to the indirect costs. Direct costs include tually any scenario. If the field crew
watch out for, and the work-arounds extended manpower (always include is instructed to wash down the steel
you should incorporate within your because it was provided dirty by oth-
the labor burden) and extended ers, or kept waiting because the trade
change order routine. equipment (from heavy equipment ahead of it is not ready, a compensable
to scissor lifts and even the com- change order should be priced using the
First, What Is a Change Order? pany vehicles), as well as the addi- above methodology. Realize, of course,
According to R.S. Means, a change tional material or sub-subcontractor that this requires precision coordina-
order is “a written authorization pro- tion between the field, estimating, and
costs, if any. Indirect costs seek to
the back office to perceive the change
vided to a contractor approving a value the less tangible cost impact of order through the fast-paced chaos of a
change from the original plans, spec- the change, and include field supervi- busy construction site—which should be
ifications, or other contract docu- sion (extended project management, going on in any event.
ments, as well as a change in cost.” superintendent costs), field overhead
Practically, change orders are most (extended trailer, on-site person-
commonly caused by design errors, nel and related costs), and extended The Subcontract as an IED
differing site or project conditions, main office overhead. For large Once a subcontract is signed, vir-
incomplete drawings at the time of changes or delays, the greater impact tually every imaginable situation is
bid, and owner changes. Other, less of the change should also be calcu- governed by the provisions of the
common sources of change orders lated—this generally involves utilizing subcontract, including the poten-
include scope gaps, a particular a claim methodology such as the total tial for changes orders and addi-
instruction as to means and method cost method, measured mile, or other tional compensation for changed or
or the sole sourcing of manufactured impact tracking formula beyond the extra work. Understand that subcon-
items, project delay, acceleration and scope of this article. Finally, be sure tracts are drafted to reduce and shift
the accompanying added labor force to capture the miscellaneous “reim- as much risk as possible away from
(or overtime). In other words, virtually bursables” such as fuel, lodging, tolls, the general contractor and onto the
never the cause or fault of the sub- bond, insurance, etc.—while not sep- subcontractor. Think of an unmodified
contractor. Moreover, when played arately recoverable in a fixed-fee con- subcontract as an improvised explo-
correctly, the subcontractor maintains tract, these costs should always be sive device, just waiting to explode
tremendous leverage in the change tracked, captured and priced within a when necessary.
order process, and should both be change order request.
mindful of that leverage, and use it For example, many subcontracts
wisely. will include a pre-existing obligation
to perform change order work even

26 N O V E M B E R 2 0 1 8 T H E C O N T R A C T O R ’ S C O M P A S S
without an agreement on price, or Pass-Through Claims
agreement whether such work is even Practice Tip #4
Many subcontracts will permit
a change. This is compounded when a Pass-through claims should be initiated
the subcontractor to make a claim as a matter of course. Any claim, includ-
pay-if-paid provision is in use, which for changes or extra compensa- ing a request for change order, can dou-
will also apply to change order pay- tion directly to the owner, through ble as an official “pass-through” claim
ment—if the owner does not believe the “pass-through” provision. This by identifying it as such, and if neces-
the work is a change, it will most cer- clause obligates the general contrac- sary on a state or federal job, including
tainly not be paid for! Adding insult to the certification language as provided
tor to pass-through claims submitted under the Contract Disputes Act or simi-
injury, many subcontracts will include by a subcontractor for consideration lar state law. This will shift the burden to
a generic no-damages-for-delay by the owner, when the responsibil- the general contractor to formally pass
clause, and/or a waiver of consequen- ity for the excess costs is attributed to the claim through to the owner, where it
tial damages—which will preclude the owner. However, it is a doubled- will hopefully be given the consideration
many of the indirect pricing strategies edged sword, because it often com- it deserves.
outlined above. pletely frees the general contractor
from responsibility to the subcontrac-
tor unless and until payment is made
Partial Releases Are
Practice Tip #2 Anything But!
by the owner.
All subcontracts should be modified
as necessary to reflect, at minimum, (i) I often encounter subcontrac- Beware of the “partial” release
the subcontractor’s option not to per- tors who did not pass through via- used, ostensibly, to ensure that a cor-
form change order work in the absence ble claims because they perceived it responding amount of each monthly
of an advance, mutually agreed price
as too difficult, too expensive or too progress payment is released from
or pricing methodology, (ii) payment lien, bond and breach of contract
for change order work is not dependent speculative. Remember, however, that
many changes are only an extra cost claims. The partial release, however,
on owner payment, (iii) delay damages
may be awarded for change order work, to the subcontractor, and not the gen- will often be so broad as to include
or, at minimum, that the subcontractor eral contractor. If the general con- within it retention, and the work per-
is vested with all the rights the general tractor does not stand to make any formed since the date of the last
contractor maintains against the owner. pay application through the date of
significant money on the subcontrac-
tor’s claim, there is little incentive to the release, whether billed or not.
actually pass it through unless the Pending change orders, and even
Overbroad Scope subcontractor has formally triggered approved but unpaid change orders,
Regardless of the subcontractor’s the pass-through requirement. would also be caught in the dragnet
proposal and its specific inclusions of such broad release language.
Recently, a client of mine was hit
and exclusions, standard subcon-
with thousands of dollars in back-
tract language will typically include
charges for supplemental labor. He
language similar to the following: Practice Tip #5
readily admitted to me he was una-
“The Subcontractor’s Work includes All releases, even “partial” releases,
ble to provide sufficient manpower should be modified to include lan-
everything necessary to complete
for the second phase of the job, and guage similar to the following:
the ____________ scope of work.”
the backcharges for supplemental “Notwithstanding anything herein to the
Disagreements between what was contrary, this release shall not apply to
labor were justified. But when I dug
included in the subcontractor’s price retention, unapproved and/or unbilled
deeper, asking how is it that he had
and what was not are one of the change order or other extra work, and
the manpower for phase one but not work performed since the last pay appli-
most common disputes surround-
phase two, I learned that there was a cation for which this payment is made.”
ing change orders—but faced with
differing site condition that had to be I have commissioned a rubber stamp
the above language, the subcontrac-
remedied in between phase one and with this language that I send to my cli-
tor will usually not have a leg to stand ents with instructions to stamp on every
two, setting the phase two work back
on. After all, it committed to perform release they sign.
by several months. During that time
everything necessary, didn’t it?
period, my client’s union employ-
ees took other jobs and he could Joe Katz, Esq., Huddles Jones
not get enough qualified labor back Sorteberg & Dachille, P.C., based out
Practice Tip #3
when phase two was actually ready of Columbia, Md., has practiced con-
Be absolutely sure you incorporate, at
minimum, the proposal’s scope of work to begin. Putting my change order struction law exclusively for nearly
within the subcontract. This should be glasses on, we drafted a pass-through 15 years. Katz regularly represents
done using language that provides claim in the amount of the back- subcontractors and suppliers on fed-
“Notwithstanding anything herein to the charges, representing the increase eral, state and municipal construc-
contrary, Subcontractor’s proposal is tion projects. He is experienced in
adopted and incorporated herein by ref- labor costs on account of the differing
site condition encountered at the job. all facets of construction litigation,
erence.” In this way, the proposal can at
least be considered on par to the sub- including mechanic’s liens, Miller Act
contract, and not subservient to it. And payment bond claims, arbitration, and
in preparing your proposal, be crystal civil actions in both state and federal
clear what is included within the quoted court. He can be reached at (410) 499-
price, and what is excluded.
2615 or katz@constructionlaw.com.

T H E C O N T R A C T O R ’ S C O M P A S S N O V E M B E R 2 0 1 8 27

You might also like