Professional Documents
Culture Documents
Change Orders 201 - Tips and Tricks - Legally Speaking November 2018
Change Orders 201 - Tips and Tricks - Legally Speaking November 2018
26 N O V E M B E R 2 0 1 8 T H E C O N T R A C T O R ’ S C O M P A S S
without an agreement on price, or Pass-Through Claims
agreement whether such work is even Practice Tip #4
Many subcontracts will permit
a change. This is compounded when a Pass-through claims should be initiated
the subcontractor to make a claim as a matter of course. Any claim, includ-
pay-if-paid provision is in use, which for changes or extra compensa- ing a request for change order, can dou-
will also apply to change order pay- tion directly to the owner, through ble as an official “pass-through” claim
ment—if the owner does not believe the “pass-through” provision. This by identifying it as such, and if neces-
the work is a change, it will most cer- clause obligates the general contrac- sary on a state or federal job, including
tainly not be paid for! Adding insult to the certification language as provided
tor to pass-through claims submitted under the Contract Disputes Act or simi-
injury, many subcontracts will include by a subcontractor for consideration lar state law. This will shift the burden to
a generic no-damages-for-delay by the owner, when the responsibil- the general contractor to formally pass
clause, and/or a waiver of consequen- ity for the excess costs is attributed to the claim through to the owner, where it
tial damages—which will preclude the owner. However, it is a doubled- will hopefully be given the consideration
many of the indirect pricing strategies edged sword, because it often com- it deserves.
outlined above. pletely frees the general contractor
from responsibility to the subcontrac-
tor unless and until payment is made
Partial Releases Are
Practice Tip #2 Anything But!
by the owner.
All subcontracts should be modified
as necessary to reflect, at minimum, (i) I often encounter subcontrac- Beware of the “partial” release
the subcontractor’s option not to per- tors who did not pass through via- used, ostensibly, to ensure that a cor-
form change order work in the absence ble claims because they perceived it responding amount of each monthly
of an advance, mutually agreed price
as too difficult, too expensive or too progress payment is released from
or pricing methodology, (ii) payment lien, bond and breach of contract
for change order work is not dependent speculative. Remember, however, that
many changes are only an extra cost claims. The partial release, however,
on owner payment, (iii) delay damages
may be awarded for change order work, to the subcontractor, and not the gen- will often be so broad as to include
or, at minimum, that the subcontractor eral contractor. If the general con- within it retention, and the work per-
is vested with all the rights the general tractor does not stand to make any formed since the date of the last
contractor maintains against the owner. pay application through the date of
significant money on the subcontrac-
tor’s claim, there is little incentive to the release, whether billed or not.
actually pass it through unless the Pending change orders, and even
Overbroad Scope subcontractor has formally triggered approved but unpaid change orders,
Regardless of the subcontractor’s the pass-through requirement. would also be caught in the dragnet
proposal and its specific inclusions of such broad release language.
Recently, a client of mine was hit
and exclusions, standard subcon-
with thousands of dollars in back-
tract language will typically include
charges for supplemental labor. He
language similar to the following: Practice Tip #5
readily admitted to me he was una-
“The Subcontractor’s Work includes All releases, even “partial” releases,
ble to provide sufficient manpower should be modified to include lan-
everything necessary to complete
for the second phase of the job, and guage similar to the following:
the ____________ scope of work.”
the backcharges for supplemental “Notwithstanding anything herein to the
Disagreements between what was contrary, this release shall not apply to
labor were justified. But when I dug
included in the subcontractor’s price retention, unapproved and/or unbilled
deeper, asking how is it that he had
and what was not are one of the change order or other extra work, and
the manpower for phase one but not work performed since the last pay appli-
most common disputes surround-
phase two, I learned that there was a cation for which this payment is made.”
ing change orders—but faced with
differing site condition that had to be I have commissioned a rubber stamp
the above language, the subcontrac-
remedied in between phase one and with this language that I send to my cli-
tor will usually not have a leg to stand ents with instructions to stamp on every
two, setting the phase two work back
on. After all, it committed to perform release they sign.
by several months. During that time
everything necessary, didn’t it?
period, my client’s union employ-
ees took other jobs and he could Joe Katz, Esq., Huddles Jones
not get enough qualified labor back Sorteberg & Dachille, P.C., based out
Practice Tip #3
when phase two was actually ready of Columbia, Md., has practiced con-
Be absolutely sure you incorporate, at
minimum, the proposal’s scope of work to begin. Putting my change order struction law exclusively for nearly
within the subcontract. This should be glasses on, we drafted a pass-through 15 years. Katz regularly represents
done using language that provides claim in the amount of the back- subcontractors and suppliers on fed-
“Notwithstanding anything herein to the charges, representing the increase eral, state and municipal construc-
contrary, Subcontractor’s proposal is tion projects. He is experienced in
adopted and incorporated herein by ref- labor costs on account of the differing
site condition encountered at the job. all facets of construction litigation,
erence.” In this way, the proposal can at
least be considered on par to the sub- including mechanic’s liens, Miller Act
contract, and not subservient to it. And payment bond claims, arbitration, and
in preparing your proposal, be crystal civil actions in both state and federal
clear what is included within the quoted court. He can be reached at (410) 499-
price, and what is excluded.
2615 or katz@constructionlaw.com.
T H E C O N T R A C T O R ’ S C O M P A S S N O V E M B E R 2 0 1 8 27