JP (K1022) Document Status - Latest Only: in Reference Reply Referece
JP (K1022) Document Status - Latest Only: in Reference Reply Referece
JP (K1022) Document Status - Latest Only: in Reference Reply Referece
No. Document No Rev. Description In Reference Reply Referece Status Due Date Disp. Review Remarks
JP TR # TR Date SEPOC TR # TR Date
DS Data Sheet
1 1022-12-EJ-8175 0 Data sheet for Pressure Gauge K1022-EDT-061 21-Jul-10 A INST 23-Aug-Issam
2 1022-12-EJ-8176 0 Data sheet for Temperature Gauge K1022-EDT-061 21-Jul-10 A INST 23-Aug-Issam
3 1022-12-EJ-8177 0 Data Sheet for Pressure Transmitter K1022-EDT-066 23-Jul-10 A INST 23-Aug-Issam
4 1022-12-EJ-8178 0 Data Sheet for Temperature Transmitter K1022-EDT-066 23-Jul-10 A INST 23-Aug-Issam
6 1022-12-EJ-8180 2 Data Sheet for Ultra Sonic flow Meter K1022-EDT-076 29-Jul-10 B INST 23-Aug-Issam
7 1022-12-EJ-8181 C Data Sheet for Control Valve K1022-EDT-114 26-Aug-10 09-Sep-10 INST
8 1022-12-EJ-8182 1 Data Sheet for Pig Signaler K1022-EDT-077 29-Jul-10 A INST 23-Aug-Issam
9 1022-12-EJ-8183 A Data Sheet for Orifice Plate Assembly K1022-EDT-050 18-Jun-10 02-Jul-10 INST
10 1022-12-EJ-8184 A Data Sheet for Instrument Cable K1022-EDT-116 28-Aug-10 11-Sep-10 INST
11 1022-12-EJ-8185 A Data Sheet for Junction Box K1022-EDT-109 20-Aug-10 03-Sep-10 INST
12 1022-12-EJ-8186 A Data Sheet for Instrument Differential Pressure Transmitter K1022-EDT-049 17-Jun-10 01-Jul-10 INST
13 1022-12-EJ-8187 A Data sheet for Blow down Valve K1022-EDT-096 11-Aug-10 B INST 28-Aug-Issam
14 1022-12-EJ-8188 1 Data Sheet for Pressure Safety Valves K1022-EDT-075 29-Jul-10 A INST 23-Aug-Issam
17 1022-12-EJ-8211 A Data Sheet for Alarm Annunciator K1022-EDT-096 11-Aug-10 A INST 28-Aug-Issam
18 1022-12-EJ-8212 A Data Sheet for Control Panel K1022-EDT-107 19-Aug-10 02-Sep-10 INST
19 1022-12-EJ-8213 A Data Sheet for Restriction Orifice K1022-EDT-096 11-Aug-10 A INST 28-Aug-Issam
20 1022-12-EJ-8217 A Data sheet for Flow Totalizer K1022-EDT-102 14-Aug-10 A INST 28-Aug-Issam
21 1022-12-EM-3850 B Data Sheet for Pig Launcher K1022-EDT-059 21-Jul-10 04-Aug-10 MECH
22 1022-12-EM-3851 B Data Sheet for Pig Receiver K1022-EDT-059 21-Jul-10 04-Aug-10 MECH
23 1022-12-EM-3852 B Data Sheet for Cyclone Separator K1022-EDT-059 21-Jul-10 04-Aug-10 MECH
25 1022-12-EM-3854 C Data Sheet for Filter Separator K1022-EDT-059 21-Jul-10 04-Aug-10 MECH
DWG Drawings
2 043-003-12-D-3016 A North Treating Train Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
3 043-003-12-D-3017 A North Treating Train Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
4 043-003-12-D-3018 A North Treating Train Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
5 043-003-12-D-3019 A North Treating Train Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
6 043-003-12-D-3042 A Piping Plan Compressor Area Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
7 043-003-12-D-3043 A Piping Plan Compressor Area Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
8 043-003-12-D-3044 A Piping Plan Compressor Area Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
9 043-003-12-D-3045 A Piping Plan Compressor Area Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
10 043-003-12-D-3058 A North Treating Train Pipe Rack CPU (Modification) K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
11 1022-12-D-1300 A Process Flow Diagram - CPU-PEC Pipeline, Liquid Removal Facilities at PEC, Process Flow Diagram - K1022-EDT-006 29-Mar-10 12-Apr-10 PROC
Heat & Material Balance (300 MMSCFD)
12 1022-12-D-1300 C Process Flow Diagram - CPU PEC Line, Liquid Removal Faciliteis at PEC, Heat & Material Balance K1022-EDT-064 22-Jul-10 05-Aug-10 PROC
(200MMSCFD)
13 1022-12-D-1305 A P&ID Legends and Symbols K1022-EDT-016 23-Apr-10 07-May-10 PROC
22 1022-12-D-1314 B P&ID - Existing Line to Marib #1 Power Station K1022-EDT-056 15-Jul-10 29-Jul-10 PIP
24 1022-12-D-2575 A Equipment/Pipe Support Foundation Layout-PEC Area K1022-EDT-113 26-Aug-10 09-Sep-10 PIP
27 1022-12-D-3982 A Plot Plan/Equipment Layout - CPU Area K1022-EDT-079 31-Jul-10 14-Aug-10 PIP
30 1022-12-D-3985 A Piping Layout - CPU Area Pig Launcher K1022-EDT-082 31-Jul-10 14-Aug-10 PIP
33 1022-12-D-3988 A Piping Layout - PEC Area Slug Catcher K1022-EDT-082 31-Jul-10 14-Aug-10 PIP
34 1022-12-D-3989 A Piping Layout - PEC Cyclone Separator A/B K1022-EDT-082 31-Jul-10 14-Aug-10 PIP
35 1022-12-D-3990 A Piping Layout - PEC Area Filter Separator A/B K1022-EDT-082 31-Jul-10 14-Aug-10 PIP
40 1022-12-D-3995 A Piping Layout - CPU Area 12" Pipeline & 2" Drain Line K1022-EDT-088 06-Aug-10 20-Aug-10 PIP
48 1022-12-D-4007 0 Typical Open Cut Road Crossing K1022-EDT-089 06-Aug-10 20-Aug-10 CIV
51 1022-12-D-8195 A Instrument Cable Block Diagram ( 6 sheets) K1022-EDT-107 19-Aug-10 02-Sep-10 INST
53 1022-12-D-8198 A Hook up drawings for Pressure Gauge K1022-EDT-039 10-Jun-10 A INST 21-Jun-10
54 1022-12-D-8199 0 Hook up drawings for Temperature Gauge K1022-EDT-052 23-Jun-10 A INST 23-Aug-Issam
55 1022-12-D-8200 A Hook up drawings for Control Valve K1022-EDT-035 08-Jun-10 A INST 21-Jun-10
56 1022-12-D-8201 A Hook up drawings for Pressure Transmitters K1022-EDT-035 08-Jun-10 A INST 21-Jun-10
58 1022-12-D-8203 0 Hook up drawings for Temperature Transmitters K1022-EDT-052 23-Jun-10 A INST 23-Aug-Issam
59 1022-12-D-8204 0 Hook up drawings for Ultra Sonic Flow Meter K1022-EDT-052 23-Jun-10 A INST 23-Aug-Issam
60 1022-12-D-8205 A Hook up drawing for Orifice Flow Meter K1022-EDT-037 09-Jun-10 A INST 21-Jun-10
61 1022-12-D-8208 0 Typical Drawings for Instrument Pedestal K1022-EDT-052 23-Jun-10 A INST 23-Aug-Issam
62 1022-12-D-8209 A Typical Instrument Cable Trench Drawing K1022-EDT-036 09-Jun-10 A INST 21-Jun-10
63 1022-12-D-8210 0 Typical Instrument Drawwing for Field Transmitter Installation K1022-EDT-052 23-Jun-10 A INST 23-Aug-Issam
65 1022-12-D-8213 A Instrument Power Supply Diagram CPU Area K1022-EDT-107 19-Aug-10 02-Sep-10 INST
GEN General
1 1022-12-ER-1281 A Operation & Control Philosophy K1022-EDT-063 22-Jul-10 05-Aug-10 PROC
MR Material Requisition
1 1022-12-EJ-8191 A Material Requisition for Gauges K1022-EDT-074 29-Jul-10 A INST 23-Aug-Issam
3 1022-12-EJ-8193 B Material Requisition for Control Valve K1022-EDT-115 28-Aug-10 11-Sep-10 INST
4 1022-12-EJ-8194 B Material Requisition for Pig Signaler K1022-EDT-077 29-Jul-10 A INST 23-Aug-Issam
6 1022-12-EJ-8197 B Material Requisition for Ultrasonic Flow Meter K1022-EDT-076 29-Jul-10 B INST 23-Aug-Issam
7 1022-12-EJ-8199 A Material Requisition for Junction Box K1022-EDT-112 26-Aug-10 09-Sep-10 INST
8 1022-12-EJ-8200 B Material Requisition for Safety Valves K1022-EDT-075 29-Jul-10 A INST 23-Aug-Issam
9 1022-12-EJ-8215 A Material Requisition for Restriction Orifice K1022-EDT-101 13-Aug-10 A GEN 28-Aug-Issam
10 1022-12-EJ-8216 A Material Requisition for Control Panel with Accessories K1022-EDT-108 20-Aug-10 03-Sep-10 INST
11 1022-12-EM-3860 B Material Requisition for Pig Launcher/Pig Receiver K1022-EDT-067 24-Jul-10 07-Aug-10 MECH
12 1022-12-EM-3861 B Material Requisition for Cyclone Separator K1022-EDT-068 24-Jul-10 07-Aug-10 MECH
13 1022-12-EM-3862 B Material Requisition for Slug Catcher K1022-EDT-069 24-Jul-10 07-Aug-10 MECH
14 1022-12-EM-3863 B Material Requisition for Filter Separator K1022-EDT-070 24-Jul-10 07-Aug-10 MECH
2 1022-12-EP-4851 A Specificaiton/MTO for Pipes, Pipe fittings, SS Tubing, Flanges, Gaskets, Bolts & Special Piping Items K1022-EDT-065 23-Jul-10 06-Aug-10 PIP
3 1022-12-EP-4865 B Specification/MTO for Hot Induction Bends K1022-EDT-073 27-Jul-10 10-Aug-10 PIP
PLN Plan
1 1022-12-PG-0040 A Project Execution Plan K1022-EDT-004 11-Mar-10 25-Mar-10 GEN
REG Register
1 1022-12-D-8190 A Instrument Index K1022-EDT-087 05-Aug-10 B INST 28-Aug-Issam
RPT Report
1 1002-SEPOC-PP-003 A Proposal for LOP Residue Gas Treatment K1022-EDT-003 25-Feb-10 11-Mar-10 GEN
3 1022-12-EP-4871 B 12" Pipeline Road Crossing Calculation Report K1022-EDT-099 13-Aug-10 27-Aug-10 PIP
4 1022-12-EP-4872 A Critical Line List for Stress Analysis K1022-EDT-079 31-Jul-10 14-Aug-10 PIP
5 1022-12-EP-4874 A Report on Horizontal spacing between existing 12" and new 16" gas line K1022-EDT-008 31-Mar-10 14-Apr-10 PIP
8 1022-12-ER-1280 1 Process HAZOP study report by GLIC and HAZOP Review Action Report by JP K1022-EDT-071 24-Jul-10 07-Aug-10 PROC
12 JP-SEPOC-ESC-0004 A Scope of Work for LOP Residue Gas Treatment K1022-EDT-002 31-Dec-09 14-Jan-10 GEN
SPE Specification
4 1022-12-EC-2553 0 Structural General Notes for the project LOP Residue Gas Treatment K1022-EDT-098 12-Aug-10 26-Aug-10 CIV
6 1022-12-EJ-8206 0 Specification for Cables and Cable Glands K1022-EDT-026 11-May-10 A INST 12-05-10
7 1022-12-EJ-8207 0 Specification for Ultra Sonic Flow Meter K1022-EDT-026 11-May-10 A INST 12-05-10
8 1022-12-EJ-8214 A Specification for Control Panel with Accessories K1022-EDT-109 20-Aug-10 03-Sep-10 INST
12 1022-12-EM-3874 0 Specification for Protection of Goods During Shipment K1022-EDT-095 11-Aug-10 25-Aug-10 MECH
13 1022-12-EM-3875 0 Specification for Spare Part Requirements K1022-EDT-095 11-Aug-10 25-Aug-10 MECH
16 1022-12-EP-4854 0 Specification for Pressure Testing of Piping System K1022-EDT-029 12-May-10 26-May-10 PIP
17 1022-12-EP-4855 0 Specification for Installation and Testing of Steel Piping K1022-EDT-029 12-May-10 26-May-10 PIP
22 1022-12-EP-4861 0 Specification for Radiographic Inspection of Pipeline Welds K1022-EDT-029 12-May-10 26-May-10 PIP
24 1022-12-EP-4863 0 Specification for Hydrostatic Testing of Pipelines K1022-EDT-031 13-May-10 27-May-10 PIP
25 1022-12-EP-4864 A Specification/Data Sheet/MTO for 16" Pipeline Valves K1022-EDT-015 23-Apr-10 07-May-10 PIP
26 1022-12-EP-4870 B Wall thickness Calculation for 12" Gas pipeline K1022-EDT-099 13-Aug-10 27-Aug-10 PIP
WR Weekly Report
1 PR-7 - Progress Report No. 7 K1022-EDT-053 12-Jul-10 26-Jul-10 GEN