Professional Documents
Culture Documents
Earned Value Management
Earned Value Management
Management
Todays Discussion
Earned Value Management Definition
Required Planning Data
Earned Value Indices
Example
Data Representation
Guidelines
Standards
1
Tracking Requirements
Project Progress
Cost Variance
Time Variance
Impact on the remaining Project Progress
Time required to complete the remaining work
Cost for completing the remaining work
Tracking Requirements
Expected Cost Variance at Project Completion
Expected Time Variance at Project Completion
Required efficiency of resources for catching
up on delays and completing the project within
the estimated cost
2
Issue
Projects include work with different units of
measurement
3
Planning Requirement
Performance Measurement Baseline
Activities List
Quantity of Work
WBS
•Duration Estimation
•Time
•Resource Requirement
•Resource
•Cost
•Cost
Sequence of Work
Network Diagram
and Scheduling
Added to a project for unexpected costs that are within project scope.
Not an allowance for changes to scope.
Not part of the cost estimate.
Added by upper management, not the project manager. Project
Budget (PB)
450.00
MANAGEMENT RESERVE
400.00
Budgeted at
350.00 Completion
(BAC)
CUM UL AT IV E CO S T
300.00
250.00
200.00
150.00
100.00
50.00
-
1 2 3 4 5 6 7 8 9 10 11 12
TIME
4
HYBRID APPROACH
Planning Requirement
Control Account Plans (CAP)
Work Package Level at which Project
Performance shall be monitored
Responsibility – Organisational, Individual
Division (if necessary) into lower work packages
Metrics for measuring performance
Milestones
% complete
Other
Sum of CAPs constitutes the
Performance Measurement Baseline
5
Planning Requirement
Variance Thresholds
450.00
400.00
Budgeted at
350.00 Completion
(BAC)
CUM UL AT IV E CO S T
300.00
250.00
200.00
150.00
100.00
50.00
-
1 2 3 4 5 6 7 8 9 10 11 12
TIME
6
Planning Requirement
Subsidiary Management Plans
7
Variance Analysis
Backward Looking
Trends Forecasting
Forecasting estimated progress for remaining work
BCWS
ACWP
8
ETC
9
ETC
10
Derived Indices – Trends Forecasting
SPI: Schedule Performance Index (BCWP/BCWS)
SPI<1 means project is behind schedule
Ref: http://www.theprojectgroup.com/blog/en/earned-
value-analysis-with-microsoft-project/#prettyPhoto/2/
11
Example – Planned Data
450.00
408.60
400.00
CUMULATIVE COST (LAKHS)
350.00
300.00
250.00
200.00
150.00
100.00
50.00
-
1 2 3 4 5 6 7 8 9 10 11 12
TIME (MONTHS)
12
Example – Tracking Data upto Month 3
13
450.00
408.60
400.00
CUMULATIVE COST (LAKHS)
350.00
300.00
250.00
200.00
150.00 91.50
100.00
100.00
50.00 89.25
-
1 2 3 4 5 6 7 8 9 10 11 12
TIME (MONTHS)
14
SPI = 89.25 / 91.5 = 0.98
Derived Indices –
Impact on Cost of Remaining Work
Estimate To Complete (ETC): BAC – BCWP
CPI
15
ETC
Example
Estimate to Complete (ETC) = 408.60 - 89.25 = 358.82
0.89
16
Derived Indices –
Impact on Duration of Remaining Work
TAC: PAC
SPI
Example
Time at Completion (TAC) = 12 / 0.98 = 12.24
17
500.00 458.82
VAC
450.00
400.00
350.00
408.60
DAC
300.00
250.00
200.00
91.50
150.00
100.00
100.00
50.00
89.25
-
1 2 3 4 5 6 7 8 9 10 11 12 13
TIME (MONTHS)
CPM vs EVM
18
Derived Indices - % Complete
Project percent Complete Indices (PCIB)
PCIBBAC: BCWP
BAC
% Completion with respect to the original Budget of the
project. Preferred when there is high level of confidence
in the original cost estimate
PCIBEAC: ACWP
EAC
% Completion with respect to Actual cost incurred and
Estimate to Complete the remaining work. Preferred because
includes newer and more complete information
Example
PCIBBAC = 89.25 / 408.60 = 0.2184
21.84%
19
Derived Indices –
Productivity of Resources for Remaining Work
20
EVM Calculations
SV = -2.25
CV = -10.75
SV% = -0.02 or 2% delay in progress
CV% = -0.12 or 12% cost overrun
SPI = 0.98
CPI = 0.89
CSI = 0.87
EVM Calculations
EAC = 458.82 Lakhs
VAC = -50.22 Lakhs
DAC = -0.24 months
PCBI = 21.8%
TCPI = 1.03 or 103%
21
Data Representation
On Schedule
On Budget
CV%
0
SV% = -0.02
-
CV% = -0.12
- 0 +
SV%
Data Representation
1.2
CPI Cost Perf. Index (CPI)= BCWP
SPI ACWP
"GOOD"
1
CPI
"BAD"
0.9 SPI
0.8
22
EVM Scenarios
On Budget & Behind Schedule
Negative Position
Under Budget & Behind Schedule
Mixed Position
Over Budget & Ahead of Schedule
Mixed Position
Over Budget & Behind Schedule
Negative Position
Under Budget & Ahead of Schedule
Good Position!!!!
23
Project Management - Session 11
24
How can you use this information?
Careful analysis of variance and trends
Resetting schedule or budget, when appropriate
Benefits
EVM at Project level
Measures achieving Project Objectives
25
Data Representation –
Program Managers
Create project snapshot in Excel
Helps in project tracking and Project prioritisation
26
Project Management can be practiced without
EVM
EVM Standards
PMI Practice Standard for Earned Value
Management www.pmi.org
BIS Code 15883 (Part 2) –
Construction Project Management Guidelines –
Time Management
27
vahuja@ricssbe.edu.in
28