Daily Working Record

Name : PHAL Pisey

Month : Jan 2018


Date Contents Achievement Remark
-Revise cross section section 8 Sta.
6 Sat -5 cross sections revised.
14+000 to Sta. 20+300.
7 Sun Victory Over Genocide Day

8 Mon
-Understanding drawing of the urgent
replacement bridges in flood-prone
areas.
9 Tue -All have been done.
-Prepare summary of briges type
-Calculate quantity of substructure for
Prek Anlong Khle Bridge.
-Calculate quantity of sub-structure for
10 Wed -All have been done.
Prek Chhloung and Peam Te Bridge.
-Understanding in detail of 7 bridges.
-Mode of demolision
-Mode of construction
-Material resource
11 Thu -All things have learned.
-Schedule of the project
-Necessary work for Cambodia side to
be completed before and at the time of
construction period.
-Prepare BOQ table and calculate
12 Fri quatity of superstructure for Prek -All have been done. -Revise new quantity table.
Anlong Khle Bridge.
-Calculate quatity of superstructure for
13 Sat
Prek Chhloung Bridge.