QUOTATION

Kepada : jakarta Januari 21-2019


Management building No : 012/QT-DMK/2019
ARKADIA GREEN PARK
Jakarta
Up : Bp syauqi

Subyek : pekerjaan instalasi ducting Exaust


No U R A I AN PEKERJAAN Qty Vol Harga Jumlah
1 Pekerjaan persiapan
Mobilisasi de mobilisasi alat kerja dan material ls ls 500,000 500,000
pengukuran ulang ls ls 250,000 250,000
pembersihan berkala ls ls 300,000 300,000
koordinasi lapangan ls ls 500,000 500,000
sub-total 1,550,000

2 Pekerjaan Instalasi ground floor-basement


Pabrikasi dan instalasi ducting uk 400x350 bjls 0,5 20 m' 565,000 11,300,000
fan centrifugal 2000cfm ex cke 1 unit 9,000,000 9,000,000
bracket support unit fan 4 ttk 550,000 550,000
hanger suppor ducting besi siku 3x3 10 ttk 75,000 750,000
cooring flat lantai 1 ttk 500,000 500,000
panel power + instalasi wearing kabel 3x2,5 1 ls 2,000,000 2,000,000
drain dan penampungan 1 ls 250,000 250,000
sub-total 24,350,000

3 instalasi control selenoid gas 1 ls 900,000 900,000


sub-total 900,000
JUMLAH 26,800,000
PPN 10% 2,680,000
TOTAL 29,480,000

Terbilang : Dua puluh sembilan juta empat ratus delapan puluh ribu rupiah

NOTE : listrik dan ruang pabrikasi By owner


waktu pelaksanaan 10 hari kalender

Demikian penawaran ini kami buat,terimaksih atas perhatian dan kerjasamanya

ttd