Professional Documents
Culture Documents
MECH3110 Final Design Report Group22
MECH3110 Final Design Report Group22
MECH3110 Final Design Report Group22
MECH 3110
Mechanical Design I
Major Assignment:
Recovery Systems Inc. Final Design Proposal
Group 22
ii
Table of Contents
Executive Summary ................................................................................................................................ ii
Figures and Tables ................................................................................................................................. vi
1 Introduction ..................................................................................................................................... 4
2 Problem Analysis ............................................................................................................................ 4
2.1 Problem Statement .................................................................................................................. 4
2.2 Client Requirements and Constraints ...................................................................................... 5
2.3 System Requirements............................................................................................................. 6
2.3.1 Artefact Recovery Device ............................................................................................... 6
2.3.2 Winching System ............................................................................................................ 6
2.3.3 Power Train and Power Supply ...................................................................................... 6
2.3.4 Support Structure ............................................................................................................ 6
3 Preliminary Report Summary ......................................................................................................... 7
4 System Design ................................................................................................................................ 8
4.1 Winching System. ................................................................................................................... 9
4.1.1 Overview of Sub-System ................................................................................................ 9
4.1.2 Integration with other components.................................................................................. 9
4.1.3 Design justification and validation ............................................................................... 10
4.2 Power Train........................................................................................................................... 14
4.2.1 Overview of Sub-System .............................................................................................. 14
4.2.2 Integration with other components................................................................................ 14
4.2.3 Design justification and validation ............................................................................... 14
4.3 Supporting Structure ............................................................................................................. 17
4.3. Overview of Sub-System ................................................................................................. 17
4.3.2 Integration with other components................................................................................ 19
4.3.3 Design justification and validation ............................................................................... 27
4.4 Artefact Recovery Device ..................................................................................................... 36
4.4.1 Overview of Sub-System .............................................................................................. 37
4.4.2 Integration with other components................................................................................ 38
4.4.3 Design justification and validation ............................................................................... 39
5 Costing .......................................................................................................................................... 45
5.1 Materials ............................................................................................................................... 45
5.2 Labour ................................................................................................................................... 46
6 Conclusion .................................................................................................................................... 47
References ............................................................................................................................................. 48
Appendix A: Detailed Calculations ...................................................................................................... 49
Appendix A.1: Winch Component Calculation ................................................................................ 49
iii
Appendix A.2: Bearing Stress in Sheave .......................................................................................... 51
Appendix A.3: Winch Drum Flange Analysis .................................................................................. 52
Appendix A.4: Winch Drum Stand Analysis .................................................................................... 54
Appendix A.5: Counter Weight Analysis ......................................................................................... 57
Appendix A.6: Counter Moment Analysis ....................................................................................... 58
Appendix A.7: Gantry Joint Analysis ............................................................................................... 60
Appendix A.8: Rail Powertrain Analysis .......................................................................................... 62
Appendix A.9: Upper Carriage Analysis .......................................................................................... 63
Appendix A.10. Actuator Force Analysis ......................................................................................... 67
Appendix A.11: Oil Reservoir Volume Analysis ............................................................................. 69
Appendix A.12: Stroke Time Analysis ............................................................................................. 70
Appendix A.13: Deflection in Recovery Device .............................................................................. 71
Appendix A.14: Housing Lid Analysis ............................................................................................. 75
Appendix A.16: Velocity of Under Carriage .................................................................................... 77
Appendix A.17: Shaft Force Analysis .............................................................................................. 78
Appendix A.18: Shaft Material Properties and Correction Factors .................................................. 79
Appendix A.19: Gantt Chart ............................................................................................................. 80
Appendix B: Engineering Drawings ..................................................................................................... 81
Appendix B.1: ARD.......................................................................................................................... 81
Appendix B.1.1: Left Web ............................................................................................................ 81
Appendix B.1.2: Right Web .......................................................................................................... 82
Appendix B.1.3: Scoop ................................................................................................................. 83
Appendix B.1.4: Scoop Shafts ...................................................................................................... 84
Appendix B.1.5: Holding Jig ........................................................................................................ 85
Appendix B.1.6: Housing.............................................................................................................. 86
Appendix B.1.7: Outer Arms ........................................................................................................ 87
Appendix B.1.8: Arm Shafts ......................................................................................................... 88
Appendix B 1.9: Housing Lid ....................................................................................................... 89
Appendix B.2: Support Structure ...................................................................................................... 90
Appendix B.2.1: Crane Wheel ...................................................................................................... 90
Appendix B.2.2: Hydraulic Brake................................................................................................. 91
Appendix B.2.3: Undertray Shaft ................................................................................................. 92
Appendix B.2.4: Overcarriage ...................................................................................................... 93
Appendix B.3: Winching System...................................................................................................... 94
Appendix B.3.1: Winch Drum ...................................................................................................... 94
Appendix B.3.2: Sheave................................................................................................................ 95
Appendix B.3.3: Drum Stand ........................................................................................................ 96
iv
Appendix B.3.4: Jib Stand ............................................................................................................ 97
v
Figures and Tables
Figure 1 – Final Design........................................................................................................................... 8
Figure 2 - Winch Drum and Stand .......................................................................................................... 9
Figure 3 - 34mm Sheave ....................................................................................................................... 10
Figure 4 - DIEPA B75 Cross Section ................................................................................................... 10
Figure 5 - Finite Element Analysis of Drum......................................................................................... 12
Figure 6 - Finite Element Analysis of Drum Stand............................................................................... 12
Figure 7 - Finite Element Analysis of Drum Stand Deformation ......................................................... 13
Figure 8. Free body diagram of winch drum ........................................................................................ 14
Figure 9 - Exploded View of Upper Carriage ....................................................................................... 18
Figure 10 - View of Under Carriage Slew ............................................................................................ 19
Figure 11 - Gantry Rail ......................................................................................................................... 19
Figure 12 - Boom .................................................................................................................................. 20
Figure 13 - Cross Section of Boom....................................................................................................... 20
Figure 15 - Schematic of Sheaves ......................................................................................................... 21
Figure 14 - Sheave Connector............................................................................................................... 21
Figure 16 - Jib Connector ..................................................................................................................... 22
Figure 17 - Boom Mounts ..................................................................................................................... 22
Figure 18 - Counter Weight .................................................................................................................. 23
Figure 19 - Guy Wire ............................................................................................................................ 23
Figure 20 - Slewing Bearing ................................................................................................................. 24
Figure 21 - Slew Bearing Mount........................................................................................................... 24
Figure 22: SKF NCF Bearing interface with gantry wheel................................................................... 25
Figure 23: Gantry wheel on I beam ...................................................................................................... 26
Figure 24: Interfacing for motor ........................................................................................................... 26
Figure 25 - FEA of Boom ..................................................................................................................... 27
Figure 26 - FEA of Upper Carriage ...................................................................................................... 28
Figure 27 - Safety Factor of Carriage ................................................................................................... 28
Figure 28. Space frame design of upper carriage .................................................................................. 29
Figure 29 - Bearing Location FBD ....................................................................................................... 31
Figure 30: Equivalent stress on the wheel ............................................................................................ 32
Figure 31: Total deformation on the wheel ........................................................................................... 32
Figure 32 - FEA Deflection of Gantry .................................................................................................. 34
Figure 33 - FEA Stress of Gantry ......................................................................................................... 34
Figure 34 - Joint Plate ........................................................................................................................... 34
Figure 35 - FEA of Axial Force Gantry ................................................................................................ 35
Figure 36: Recovery device when open ................................................................................................ 36
Figure 37: Recovery device when closed ............................................................................................. 36
Figure 38 - Waterproof Housing ........................................................................................................... 38
Figure 40 - Winch for Electrical Cable ................................................................................................. 39
Figure 39 - Camera on Holding Jig....................................................................................................... 39
Figure 41 Depiction of partial nylon tubing around electrical cable..................................................... 43
vi
Table 7: Motor technical data [5] .......................................................................................................... 15
Table 8: Pump technical data [6] .......................................................................................................... 16
Table 9: Pump technical data ................................................................................................................ 16
Table 10. Assumed supporting structure dimensions ........................................................................... 17
Table 11. Material properties of Amstrong Ultra 960QL ..................................................................... 17
Table 12 - Loads of Upper Carriage ..................................................................................................... 18
Table 13- Properties of Bearing KUDO01900-030VA15-900-000 ...................................................... 24
Table 14. Counter weight at different lengths....................................................................................... 29
Table 15:Initial Correction Factors ....................................................................................................... 30
Table 16. Section Properties of Custom I-Beam................................................................................... 32
Table 17. Section Properties of 200x200x16 SHS AS1163/C350LO(Orrcon) ..................................... 33
Table 18. Properties of Grade 350 XLERATE Steel Plate (BlueScope) .............................................. 33
Table 19. Required Material Length ..................................................................................................... 33
Table 20: RR10018 Technical Specifications [9] ................................................................................. 40
Table 21: ZE6410SW Technical Specifications [10]............................................................................ 40
Table 22- Deflection in ARD ................................................................................................................ 41
Table 23 - Laser Sensor ........................................................................................................................ 42
Table 24 - GPS ...................................................................................................................................... 42
Table 25 - Optic Fibre ........................................................................................................................... 43
Table 26 - Electrical Cable ................................................................................................................... 43
Table 27 - Nylon Tubing....................................................................................................................... 44
Table 28 - Winch Device ...................................................................................................................... 44
vii
1 Introduction
The UNSW School of Mechanical and Manufacturing Engineering had recently obtained a
decommissioned Nimitz class aircraft carrier and wishes to employ it in order to perform treasury
recovery operations off the coast of Thessia, Oceania in order to support its limited budget constraints.
The following report presents the preliminary design of an artefact recovery system to be placed on a
Nimitz class aircraft carrier. An analysis of the problem from the client’s needs and the system
requirements was first carried out in seeking to design a feasible and competitive solution. A recovery
system was to be designed such that it can obtain artefacts deep below the ocean and will be mounted
and operated from the deck of the provided retired Nimitz class aircraft carrier. In the designing of an
appropriate solution, in which the system must be able to operate according to the clients
requirements, this report details the process and the optimisation of creating a feasible solution.
Initially in the previous preliminary report, conceptual designs were drawn and broken down, where a
final concept design was then selected according to its advantages. Following this an analysis of the
chosen concept is carried out with calculations validating structural integrity and compliance with
AS1418.1-2002 standards. This report details the finished final design of a suitable and competitive
recovery system that will meet the requirements of the UNSW School of MME.
2 Problem Analysis
The following section details the analysis of the given design request from the perspective of the
client, as well as, the needs of the system.
4
2.2 Client Requirements and Constraints
The following requirements and constraints, found in Table 1 and Table 2 respectively, were derived
from client negotiations and a thorough understanding of the design brief.
Table 1. Functional requirements of overall artefact recovery system
Functional Requirements
1.1 The system must lift 25 tonnes
1.2 The system must be operational at 1km below sea level
1.3 The cycle time of the system shall be a maximum of 3 hours
1.4 The system shall operate between recovery zones a and b
1.5 The system shall be able to place the artefact at the designated drop site
1.6 The system shall recover all items fitting within a 12x5x5m envelope
1.7 The system is expected to last for full system life
1.8 The system shall retrieve artefacts of both fragile and robust nature
Constraints
2.1 The system must comply with AS1418.1-2002 (Section 1-7)
2.5 The system shall allow space for a designated drop site of minimum
dimension 12x5x5m
2.5 The system shall not interfere with the 3rd party rail system and Operations
head quarters
5
2.3 System Requirements
The technical requirements of each subsystem are presented below.
6
3 Preliminary Report Summary
After negotiations with the client in light of the requirements of the proposed solution, three concepts
were designed, where they were then evaluated and compared with each other in order to determine
the most feasible solution that best meets the client’s needs. Through the use of a Pugh’s matrix, an
optimised design was derived from the drawn concepts and was developed. Recovery Systems Inc.
had presented a preliminary and validated artefact recovery system in line with AS1418.1-2002
standards for implementation to The School of Mechanical and Manufacturing Engineering at UNSW.
The system presented featured a double gantry support structure with a crane housing and
counterweight mounted upon a slewing drive. The slewing unit is mounted upon an under carriage
which traverses the central I-beams with custom made wheels to ensure versatility of placement of the
recovery device. A fixed length boom is also mounted onto the crane housing, through which a
DIEPA B75 cable acts as a winch with a custom-made steel drum for storage. The winch is powered
by a Bosh Rexroth gearbox, a fixed plug-in hydraulic motor, A4VSO 500 hydraulic pump and a
TECO Cast iron TEFC 3-phase squirrel cage induction motor. The winch lowers the recovery device
to a maximum depth of 1000 metres at 1.33 m/s. The recovery device – made from high tensile steel –
is actuated by a single, double action hydraulic return cylinder mounted to a control box, which
houses the power for the actuator - an electric hydraulic pump. The control box sits meters above the
‘grab’ mechanism with an umbilical winch connecting the control box to the surface to allow for
actuation and control of the grab.
Further optimisation and validation of the final overall system and each of its respective subsystems
will be described in the following section.
7
4 System Design
A preliminary analysis is carried out on the selected concept with calculations validating the
suitability of the design.
8
4.1 Winching System.
9
Figure 3 - 34mm Sheave
The rope chosen for the design, seen in Figure 4, is summarised below:
Table 3. Chosen rope type for the winching system
As such the DIEPA B75 rope is appropriate for the use in the system. For full calculations refer to
Appendix A.
Drum Design
Technical data of the custom-made drum from the preliminary design phase is summarised in Table 7
below.
10
Table 4: Winch technical data
As per the AS1418.1-2002 Standards, for a diameter rope and an M6 classed crane [2], the
minimum drum diameter was required to be:
4
The flange diameter of the drum is required to be larger than the outer working diameter by 2
diameters of the chosen rope [2]. This will prevent possibilities of the rope unravelling from the sides
of the winch drum. Therefore:
To attach the flange to the spooling section of the drum, a 4.5mm fillet weld is formed along the outer
edge of the cylinder. Refer to Appendix A.3 for detailed calculation of weld size.
The minimum drum thickness is found by considering the maximum bending and compressive
stresses occurring in the drum. A thickness of approximately 52mm is required for a drum
manufactured from the material summarised in Table 6. Refer to Appendix A.1 for supporting
formula and calculation of drum thickness.
Table 5. Drum material
A finite element analysis was carried out on the winching drum to determine the maximum equivalent
stress. A fixed support boundary condition was applied to the bolt holes of the drum and the opposite
bearing support. A load was applied to a line along the length of the drum simulating a 27-tonne
pulling load. The von-Mises equivalent stress in the drum can be seen in figure 5. The maximum
equivalent stress of 23MPa is well below the yield stress of the Grade 400 steel plate used for the
drum.
11
Figure 5 - Finite Element Analysis of Drum
Drum Stand
A finite element analysis was carried out on the drum stand to determine the maximum equivalent
stress and deflection when maximally loaded. A fixed support was applied to the 4 bolted connections
at the base, while the force of a 27-tonne line-pull at to the horizontal was applied to all tapped
holes on either side of the stand. A free body diagram of the loading conditions can be found in
Appendix A.4, It was found that a maximum stress of 133.79MPa occurs about the bolted connection
at the base, as seen in figure 5. Using the Grade 400 steel plate with a yield stress of , the
factor of safety on the drum stand is:
A maximum deflection of 0.1906mm occurs on the two sides of the drum stand, as seen in figure _,
which is well within operational conditions.
12
Figure 7 - Finite Element Analysis of Drum Stand Deformation
13
4.2 Power Train
4.2.1 Overview of Sub-System
The power train is broken down into two subassemblies, the winching gearbox which connects the
motor to the drum and the hydraulic power supply which powers the winch. The hydraulic power train
was chosen over an electric power train due to its high torque output and suitability in a wet and
corrosive environment.
For a load of :
For an M6 rated crane, a safety factor of is applied to the required output torque. Therefore,
the corrected output torque is:
14
The following gearbox from Bosch Rexroth was thus chosen [4]:
Table 6. Selected gearbox component
The maximum torque output of the chosen motor at is which is enough to reach
maximum output torque of the gearbox.
The maximum power delivered by the motor is calculated using:
At maximum working pressure, maximum input flow, and assuming a total efficiency of 0.9, the
output power is:
15
Displacement 250
Speed (max) 2700 rpm
Input flow (at max speed) 675 L/min
Torque @ 350 bar (at max input flow) 1393 Nm
Max angular acceleration 10000
Case volume 2.5 L
Mass 82 kg
To provide hydraulic power to the system, a hydraulic pump is used to transform mechanical energy
to fluid flow. The chosen pump is required to have a pressure rating greater than or equal to that of the
system, and supply power larger than the input required by the motor. Table 8 below summarises the
relevant pump properties:
Table 8: Pump technical data [6]
The maximum drive power required by the pump is 405kW, which can be supplied by the AC
induction motor selected.
Table 9: Pump technical data
A gear ratio of is needed to ensure the output torque remains within operating range of the
pump.
Line Speed Analysis
The average line speed of the winching system can be found using [3]:
Assuming a draw length of 1200m, the average time taken to raise a 27t load is:
16
4.3 Supporting Structure
The supporting structure of the system is split into 6 components. These components are the upper
frame, under frame, boom, slewing unit, gantry, and rail Wheels.
The final support structure concept, utilizes a housing structure reminiscent of a crawler crane,
mounted on an overhead gantry. For the verification of the support structure components the
assumptions in Table 10 were made.
Table 10. Assumed supporting structure dimensions
The length and width of the upper and under frames are based on calculations associated with the
equivalent bearing load and counter weight load.
For the support structure the material of choice used is ultra-high tensile steel. Due to the large
loading forces, as well as the high induced stresses in members a sufficiently strong material with a
high yield limit is required for the construction of the supporting structure.
All structural components are designed to the load limit of Amstrong Ultra 960QL, specialized Ultra
high tensile steel used in mobile and crawler crane units. The properties of 960Ql can be seen in the
table below:
Table 11. Material properties of Amstrong Ultra 960QL
17
Guy Wire
Sheave
Counter
Weight
Jib mount
These factored loads were used as the basis for the design verification, and analyse. The upper
carriage is split between two major assemblies, the Boom assembly and the carriage assembly. These
assemblies are discussed in detail below.
4.3.1.2 Lower Carriage
The lower carriage consists of an undertray which sits upon six shafts, with the two most extreme
shafts powered by individual TT Electric LAK 4250 B DC motors with the torque transmitted by a
60:1 gear train reduction. Rotational movement of each shaft is achieved through the use of SKF NCF
3020 CV cylindrical roller bearings – sealed with the HDS7 seal and lubricated with LGEM 2 grease.
The motor is secured atop the tray using custom bracketing made from steel and M24 bolts directly
into the undertray itself. Custom single flanged, cylindrical taper wheels have also been designed in
accordance with AS1418.1-2002 standards, allowing the tray to traverse the gantry across the ship.
Braking is achieved using two hydraulic buffers situated at either end of the tray, again secured with
M24 bolts and thread locking adhesive.
18
Figure 10 - View of Under Carriage Slew
4.3.1.3 Gantry
19
The boom itself is constructed from circular hollow section welded together to form a truss lattice.
The truce lattice is designed as a warren truss with each truss member joined together at 60 . A
warren truss provides good force distribution between truss members allowing for a better
deformation spread. The side view with the truss profile can be seen in the image below
Figure 12 - Boom
The boom was designed as a square structure, with a 1m2 cross sectional area. The square profile can
be seen in the image below.
A circular hollow cross-section of 89mm outer diameter and a 5mm wall thickness was selected for
the boom to minimise deflection to allowable limits as dictated by AS1418.1 standards. This has been
reviewed in more detail in the next section.
20
At the top of the boom a sheave connector is welded to the sides of the lattice structure. This
connector mounts the sheave and sheave shaft, allowing the winching system to work effectively.
Sheave connector
The sheave connector has a constant thickness of 50mm, and is designed to house the sheave pulley
for the winching cable. The holes are 100mm, and are designed to fit a custom cold drawn shaft. The
cold drawn shaft will be threaded on either end to allow a locking nut to be mounted. The locking nut
will be utilised to keep the shaft in place and reduce effective displacement of the shaft member.
As seen in the image above, there is a diameter difference between the shaft and the pulley sheaves.
This is to account for the mounting of a spherical roller bearing which has been discussed in the
section above.
21
Similar to the sheave connector. The jib connector is welded to the side of the boom, allowing for a
shaft to be mounted between the Boom to a vertical support. The jib connector can be seen in the
image below.
The pin is 100mm in diameter and like the sheave shaft is threaded on both ends to allow a locking
nut to hold the shaft in place. The shaft with the thread can be seen below.
The Boom mounts to the upper carriage as well as the winch drum, counterweight and guy wire
mount. The boom mounts to the carriage structure through the jib mount. The jib mount bolts to the
floor of the carriage structure and is held in place by 4 M24 bolts. The bolt holes on the connector and
connector geometry can be seen in the image below.
The bolts are 250mm long and go through the floor of the upper carriage to secure the jib mount down.
an analyse on the bolt stress has been done and is verified in the next section.
An 84 tonne counter weight has been used to stabilise the lifting force of the crawler crane. This
counter weight is of dimensions 2800mm x 1450mm and is made of solid cast iron giving it a close
approximated mass to 84 Tonne.
22
The counter weight is mounted to the rear of the upper carriage structure and is placed between two
slots and tightly held in place by the outer cage structure.
Counter weight
Guy wire
23
withstand large radial, axial and tilting loads. The slewing unit was chosen as it allows the crane to
rotate and cover an arc, rather than a single point. This was the most effective method in maximizing
the area of recovery.
From the Liebherr catalogue [7], a suitable bearing has been selected. The selected bearing is a 4-
point ball bearing unit with the following properties:
Table 13- Properties of Bearing KUDO01900-030VA15-900-000
The slewing bearing mounts to the bearing shaft with a specified H6 interference fit. The bearing is
driven by a DAT 400 slewing drive supplied by Liebheer. The DAT 400 is designed to provide
44Knm of torque and has a total of 13 teeth. Using the above slewing bearing this provides the crane
with a corresponding slewing torque of:
24
The slewing drive is mounted to the lower carriage with 24 M22 bolts, and is connected to the aircraft
carriers internal power supply.
At the wheel/bearing and undertray/bearing interface, the shaft is machined with a P6/h7 tolerance to
allow for an interference fit of the NCF 3020 CV bearing to the shaft. These bearings sit flush against
the larger diameters of the shaft to prevent longitudinal movement. Furthermore, there is a radial slot
machined at either end of the shaft to prevent longitudinal movement of the bearing at the wheel
interface.
For transmission of torque at the gear train interface, a key slot has been employed rather than a spline
due to minimisation of machining complexity and therefore cost. The key is inserted into the slot
when the gear is placed on the shaft, secured into place using a P6/h7 tolerance for standardisation
purposes.
As mentioned previously, all 24 bearing will be press-fit into their respective locations. A tolerancing
class of H7/p6 (wheel to bearing, undertray to bearing) and P6/h7 (bearing to shaft) is utilised to
ensure maximum contact with the outer race under loading, and hence prolonged bearing lifespan.
With reference to the bearing/wheel interface, shown in Figure 221, the bearing will be secured on the
inner-most side by sitting flush to a shoulder on the shaft and appropriate fillet. On the outermost side,
a circlip is attached to the shaft to prevent lateral movement of the bearing.
The bearing at the undertray interface is held in place with a shoulder on either side of the bearing,
preventing lateral movement and removing the need for a circlip.
Maintenance
Due to the seawater, and hence corrosive environment, bearings will be sealed with an SKF HDS7
‘Flex’ seal. The seal prevents ingress of water and solid contaminants through an “optimised non-
spring-loaded lip profile” (SKF,2018) that is designed to retain grease for lubrication and withstand
heavy-duty operations. Furthermore, SKF customers “reported that the HDS7 seal is easier to install
and provides longer service life than similar seal designs” (SKF, 2018) which is particularly important
in the unlikely event that a seal fails, as a crewman on the ship would be able to replace it.
Due to the high load and slow rotational nature of operation, the SKF LGEM 2 grease lubricant was
selected. The lubricant itself is mineral oil based and of high viscosity, rated for corrosion protection
(standard: ISO11007) operating in temperatures from to - ample constraints for
recovery operations in a high-salt environment.
25
Whilst oil based lubricants are typically used at sea, the combination of the HDS7 seal - which
prevents ingress of all liquids and solids - and the LGEM 2 grease lubrication provides appropriate
protection of the bearing for operation at sea. Relubrication should occur after 6000 hours of
operation by crewmen on the ship (Grease service life and relubrication intervals – SKF, 2018).
Shown in Figure 2322, the wheel will directly sit on the flange of the I beam due to its geometry and
is mounted upon a shaft via an SKF NCF 3020 CV bearing at the wheel centre bore, reflected about
the central longitudinal axis of the shaft. The shaft itself is located through mounting points built into
the lower carriage.
The motors themselves are located on top of the undertray, attached via simple steel brackets that are
bolted into the undercarriage surface itself, as can be seen in Figure 24 with a simplified CAD for the
motor. Note the slot in the undercarriage to account for the location of the gear train.
The brackets are bolted to the undertray with M24 bolts to maintain standardisation across the design,
with the strapping fitting snugly across the main frame of the motor to ensure no slippage or
movement at maximum acceleration.
26
Intermediate shafts are secured to the undertray using standard ASIS1050 CD steel with 100mm
diameter. Shafts are then bolted to the undertray using M24 bolts and standard steel clamped sections
to be welded to the shaft itself. All shafts have a standard 50mm centre distance keyway to allow for
torque transmission, and radial grooves for circlips to prevent any transverse movement along the
shaft.
The total deformation of the boom was found to be under 60mm, which complied with AS1418
standards in relation to cantilever beams.
Upper Carriage Analysis
Like the boom the upper carriage was analysed using finite element methods. For the upper carriage
analysis a factored hoisted load was applied as well as the weight of the counterweight at the rear. The
following results were produced from the FEA analysis of the upper carriage.
27
Figure 26 - FEA of Upper Carriage
The total deflection was found to be ~40mm, which is around 1/300 of the span of the upper carriage.
This corresponds to the upper limit of allowable deflection as per 1418.1 standards, however due to
the conservative nature of the force this was deemed to be viable.
The safety factor was found to be over 2, and as such verified the validity of the design.
Jib Mount Analysis
The jib mount was analysed to determine the validity of the resulting geometry. From a free body
analysis at the pin it was found that the pin was required to be a minimum diameter of 59mm.
However as the analysis was made with assumptions on loads and due to no need to maximise weight
savings the shaft pin diameter was increased to 100mm. This can be seen in appendix A.
From the pin analysis the bearing stress extorted on the stand was determined which yielded a safety
factor of:
A bolt calculation on the jib stand determined that the use of 4 M24 bolts was sufficient to adequately
hold the jib stand in place.
28
These calculations can be seen in detail in appendix A.
The counterweight has an applied 1.4 safety margin as per AS1418.1-2002 standards with detailed
calculations in found in Appendix A.5. During the calculation of the counter weight, three different
frame lengths were considered. These lengths were 8 m, 10 m and 12 m respectively. It was shown
that as the length increased the counterweight decreased correspondingly. As a general assumption a
100 t upper limit was imposed on the counter weight. To avoid the complexities of securing a high
counterweight, it was attempted to reduce the counterweight as much as possible.
From the calculations it was shown that the counterweight first reduced to under 100 t above an 8 m
length. A length of 12 m was selected for the final concept design to minimize the counterweight as
much as possible without increasing the frame length excessively.
Table 14. Counter weight at different lengths
29
The shaft material has been selected as ASIS1050 CD steel. ASIS1050 is a common cold drawn steel,
readily accessible and easy to source. In the interest to keep design costs low but maintain system
suitability and efficiency ASIS1050 was determined to be the most suitable option as it has a high
ultimate tensile limit but is readily available and inexpensive. The ultimate tensile strength of
ASIS1050 CD is:
From [4] the typical endurance limit for most high tensile steels is between 0.35 and 0.6 of the
ultimate tensile strength. Taking into consideration these two limits, the endurance limit of 1050 CD
was assumed to be 0.5, such that
However as mentioned in [5] and in [4] the endurance limit is highly sensitive to the surface condition,
residual stress state and the presence of other inclusions that induce stress concentrations. As such
correction factors have to be considered to determine a more reasonable fatigue endurance limit.
The factor ‘a’ for a machined or cold drawn part is given as 4.51 with the exponent, ‘b’ as -0.265.
This gives a surface factor Ka of:
As the current diameter is unknown the size correction factor K b has been assumed. The temperature
and loading correction factor has been assumed negligible and the reliability loading factor has been
determined and assuming a 90% reliable design. These correction factors have been listed in Table 15
below.
Table 15:Initial Correction Factors
As the miscellaneous correction factor is difficult to determine and tends to mask the effects of out
designed geometrical discontinuities such as keyways, the correction factor K f has also been assumed
negligible and taken as 1. This can be seen in Table 155 again.
From the correction factors a more accurate fatigue endurance limit can be calculated. As such S e
becomes:
Considering the layout of the shaft shown in Error! Reference source not found.8 below where
signifies a bearing location:
30
y
B1 B2 B3 B4
z x
C
B 340.73 kN.m D E
A Nm
100mm 1100mm 1000mm 100mm
Where is estimated to be
Hence,
Since the stress does not exceed the ultimate tensile strength of the material used.
31
FEA was further conducted on the wheel to verify assumptions, with result displayed in Figure 30 and
Figure 31. The stress at the contact patch was negligible, with the majority of stress concentrated
about the tapered flange with a maximum stress of approximately 29 MPa. In light of the ultimate
tensile strength of the steel used (500 MPa), this can be considered negligible. Similarly, total
deformation is considered negligible, totalling 0.03 mm at maximum loading.
4.3.3.3 Gantry
Section Properties
The gantry consists of custom sectioned I-beams welded onto grade 350 steel plates. A truss design is
made using square hollow sections that are supported at the joints by bolt connections. A summary of
the parts used is found below:
Table 16. Section Properties of Custom I-Beam
Property Value
Depth 0.40 m
Width 0.34 m
Flange Thickness 0.05 m
Web Thickness 0.03 m
Area 0.043 m²
Ixx 0.0011158 m4
32
Table 17. Section Properties of 200x200x16 SHS AS1163/C350LO(Orrcon)
Property Value
Size 200mm x 200mm
Thickness 16mm
Area 2553.9 mm2
Ixx 8029900 mm4
http://www.orrconsteel.com.au/products/tube-pipe/structural/square-hollow-section
Table 18. Properties of Grade 350 XLERATE Steel Plate (BlueScope)
Property Value
Size 3840mm x 4200mm
Thickness 20mm
Yield Stress 350 MPa
http://www.steel.com.au/products/uncoated-steel/xlerplate-steel/structural-grades-xs
Part Length
Custom I-beam 4x105m
Grade 350 XLERATE Steel Plate 2x105m
200x200x16 SHS AS1163/C350LO 290m
Finite Element Analysis of Gantry
A finite element analysis was carried out on the gantry using a factored load of -2703832.2N, which
includes the factored dead load and hoisting load of the crane. A fixed support was applied at 35m
intervals to represent the concrete blocks supporting the structure. A maximum deflection of 59mm
occurs when a 35m span is centrally loaded as seen in figure 31. The maximum magnitude direct
stress found in the truss structure is -215.78MPa as seen in figure _. Using the Grade 350 steel SHS,
the factor of safety is therefore:
33
Figure 32 - FEA Deflection of Gantry
Joint Analysis
A 60mm bolted plate is used to secure the truss members to the upper and lower deck of the structure.
Each plate consists of 6x Grade 12.9 M36 bolts that are inserted through the square hollow sections
and secured at the opposing side. The lower edge of the plate has an 18mm weld leg joining the plate
to the steel plates. Refer to Appendix A for detailed calculations of the bolt selection and weld
analysis.
34
Figure 35 - FEA of Axial Force Gantry
35
4.4 Artefact Recovery Device
Due to the unavailability of commercial solutions for underwater recovery devices, a custom design is
provided to be integrated into the supporting structure and manoeuvred vertically via the winching
system. However, certain subcomponents will utilise readily available products within the market to
reduce the complexity and costs of obtaining a custom made part.
The recovery device is a compromise between recovering the 12*5*5 artefact and standard ISO 1C
shipment container to ensure the recovery process does not damage the recovered asset.
36
4.4.1 Overview of Sub-System
The recovery device is powered by a single double action hydraulic return cylinder mounted to the
waterproof housing, with the waterproof housing being connected to the winch cable. The piston of
the hydraulic cylinder is connected to the holding jig, and thus moves the jig up and down while being
fixed to the housing. The effect of lengthening and shortening of the hydraulic cylinder controls the
opening and closing of the claws as the claws are directly connected with the holding jig.
The hydraulic cylinder is powered by an electric hydraulic pump, controlling the valve with a
solenoid. This hydraulic system is a closed loop system with an oil reservoir attached within close
proximity of the recovery device. This enables a reduction in pressure and head losses when powering
the hydraulic cylinder. The electric control will be supplied via a fibre optic cable attached to the
cable to the ship control which can then be controlled by the operator, seen similarly in Figure 7 in
section 4.2.5.
The hydraulic pump will be enclosed within a watertight box mounted on top of the upper block of
the recovery device. This is in order to keep components of the hydraulic pump, particularly the
electronic components dry, with only the hydraulic cylinder exposed to the surrounding water.
In terms of the claws, it will be custom made, with detachable webs and ‘L’ bended teeth at the end.
With limits to the dimensions in terms of width and height, the length is adjusted to a specified length
in order to minimise large bending moment forces caused by the weight of the contents to cause the
supporting structure to deform. The scoops are designed in such a way that there are detachable webs
as seen in the exploded view in Figure 35. When picking up loose artefacts, the webs are bolted on,
thus when the scoop is closed, it creates a closed container within the scoops, however when picking
up ISO 1C containers, the webs are detached and can thus clamp the container from either side with
the ‘L’ bend teeth lifting the container from the bottom. Furthermore, the scoops will be lined with
polystyrene sheets, due to their increased friction between the steel container and the scoops
underwater as compared with steel.
The double-acting hydraulic piston operated by its integrated pressurised oil system will provide the
necessary extension and retraction to provide the high clamping force and ultimately provide the
secure gripping force. Due to its constant usage under sea water, the clamp is expected to last the
equivalent life cycle of whole recovery system as outlined in the general requirements in AS1418.1-
2002. The long life cycle is possible through the use of marine grade galvanic coating as means of
protection from the sea elements which consists of a zinc based alloy composition [7]. It will be made
with the greatest coating layer of 15 as supplied by Massac EN. Similar to the support structure, it
will be made of Armstrong Ultra 960QL high tensile steel due to its employment in similar systems
such as cranes and crawlers.
A waterproof housing was designed to contain the hydraulics and the electronic components during
operation under the sea. A lid was designed such that the components within the housing can be easily
accessed for maintenance and servicing, where the lid will be bolted onto the housing. An analysis of
the bolts stress was undertaken and the detail can be seen in Appendix A. The waterproof housing will
be attached to the winch as explained before from the top through the eye bolt, and will have 4 steel
bars linking the housing with the claws. The claws will pivot around the attachment of these outer
arms and the claw, and the centre of the claw will be attached to the hydraulic cylinder which is
connected with the housing.
The camera system used in the artefact recovery device has four main components including a laser
sensor, under water GPS, cabling, and power source. The navigational system will allow for
appropriate positioning for recovery during operation, as well as allowing the client to see the
artefacts that can potentially be recovered. This helps the client to only select the artefacts that they
wish to collect, and thus do not waste time recovering worthless artefacts.
37
4.4.2 Integration with other components
The claws are connected with the detachable webs through the use of CL 12.9 M42 hex head bolts,
with 4 bolts attaching each web on either side of the claw. The claw is attached at two locations, with
the centre of the claws being attached to the holding jig via a steel shaft, where the holding jig is then
attached to the hydraulic cylinder. As explained before, this attachment is to allow the hydraulic
cylinder to control the opening and closing of the claws via the lengthening and shortening of the
cylinder. The camera for the navigation system is mounted upon the side of the holding jig as shown
in Figure 38, where its electronic components will be housed in the waterproof housing. The second
location in which the claws are connected are at the outer edges, where a steel bar connects the
outside of the claws to the waterproof housing. This is such that the claw can pivot around the
attachment with the steel arm as it is opened and closed. The hydraulic cylinder is mounted within the
waterproof housing where it is fixed. Within the waterproof housing, along with the cylinder, the
electric hydraulic pump powering the cylinder is located inside the housing. The housing has a lid
upon the top with which it is attached by 4 CL12.9 M42 hex head bolts. The lid allows for access to
within the housing for maintenance of hydraulic and electrical components. The lid has an eyebolt
where it connects with the winching system in order for the device to be able to be lowered and lifted
during operation. An additional winching system will be used for the electrical cabling required to
power the system as shown below.
38
Camera
Module
39
For more detail of the calculations refer to Appendix A.10.
A double-acting hydraulic return Enerpac RR10018 hydraulic cylinder was selected to provide the
necessary force, with its following specifications tabulated below,
Table 20: RR10018 Technical Specifications [9]
To produce a force of 308.7 kN, the pressure required to operate the cylinder can be calculated as
follows,
Thus it can be seen that the required operating pressure is only about 70.9% of the maximum
capable operating pressure of the selected cylinder resulting in a safety factor of about 1.41.
In order to power this hydraulic cylinder, an appropriate electric hydraulic pump was selected with the
following specifications,
Table 21: ZE6410SW Technical Specifications [10]
Thus the total volume required can be seen to be less than the selected pump reservoir
capacity, confirming the feasibility of the pump selection.
40
Furthermore, the opening and closing of the recovery device can be calculated according to the stroke
time of the hydraulic cylinder [11]. The calculated times are as follows where Appendix A.12 details
the calculations,
Thus total time for a full cycle of opening and closing of the cylinder,
Deflection
In considering the deflection that the recovery device will undergo, it was determined that the points
of maximum deflection occurring will be the section of the recovery device at the point of contact
with the container and the point of the hydraulic cylinder attachment to the recovery device as
highlighted below. Again, treating the container to have a point load reaction force,
Fp
Fbracket
A
Refer to Appendix 9 for detailed finite element analyses of the deflection results tabulated below,
Table 22- Deflection in ARD
41
The main specifications of the laser sensor is summarised;
Table 23 - Laser Sensor
42
Electrical
cable
Clear Nylon tubing
To relay information, long optic fibres will be utilised and the power source is connected via power
cables which are commercially available. It is of great importance for the cables and fibres to
withstand the constant bending caused by the winching system. Hence, the bending radius has been
analysed to develop a minimum winch radius before breakage of the optic fibre. Refer to appendix (A)
and winching section____
Diameter 2.5mm
Grade Outdoor use (coated with PVC)
43
Weight 71kg
Price $42.90 per 100m
Nylon Tubing
Will provide the necessary protection solely for the electrical cable
Table 27 - Nylon Tubing
Model Domin8r X
Total weight to haul 310.56 kg
Single layer Pull (weight/speed) 5540kg @ 0.115m/s
Fourth layer pull (weight/speed) 3125 kg @ 0.03m/s
Gear reduction ratio 218:1
Dimensions 525*160*195 mm
Inner drum diameter 0.3m
Price $349
44
5 Costing
5.1 Materials
ARD
Item Price
Enerpac RR10018 $8000
Enerpac ZE6410SW $15000
SL3 Laser Sensor including patent software $7100
GPS kit $6761
Wiring (1020m)
- Electrical cable $437.58
- Nylon tubing (water proofing) $1009.80
- Fibre optics (for relaying information) $3983.10
Winch $349
Polystyrene Sheet $120
Armstrong 960QL $3.30/kg $19305
20L Hydraulic Oil $150
12 x CL12.9 M42 x 4.5 x 200 Hex Head Bolts $820.20
ARD Total $63035.68
Support Structure
296m Hollow Square Section $152.95/m $45273.20
10.8 m2 Steel Sheets $112000
Custom I Beam $600/m $252000
Support Structure Total $409273.20
Winch System
1200m DIEPA B75 $10666.50
4 x CL12.9 M24 x 100 Cap Screw Bolts $20
Winch System Total $10686.50
Power Train
GFT 450 W4 6000 $10000
A2FE 250 Pump $2500
A4VSO 500 Motor $1000
TECO Cast iron TEFC 3-phase squirrel cage $3000
induction motor
Power Train Total $16500
Total $499495.38
45
5.2 Labour
ARD
Labour Price
Casting Cost $16688.99
- 2 x Scoops = $6186.16/pc
- 1 x Housing = $2337.31
- 1 x Housing Jig = $365.41
- 4 x Outer Arms = $344.56/pc
- 1 x Housing Lid = $235.71
Machining Cost $6609.21
- 2 x Scoop = $1710.14/pc
- 1 x Housing = $653.76
- 4 x Webs = $497.54/pc
- 1 x Housing Jig = $100.66
- 4 x Outer Arms = $94.89/pc
- 1 x Housing Lid = $64.79
Galvanic Painting $2685.96
- 2 x Scoops =$ 684.05/pc
- 1 x Housing = $261.89
- 4 x Webs = $178.54
- 1 x Housing Jig = $40.26
- 10 x Shafts = $12.40/pc
- 4 x Outer Arms = $37.96/pc
- 1 x Housing Lid = $25.91
Extrusion $687.06
- 70mm Round Bar 5.6m Length
ARD Total $26671.22
Winch System
Casting Cost $20834.50
- 1 x Drum = $9609.68
- 1 x Drum Stand = $11084.51
- 1 x Sheave = $140.31
Machining Cost $4851.27
- 1 x Drum = $2657.06
- 1 x Drum Stand = $2155.79
- 1 x Sheave = $38.42
Winch Total $25685.77
Total $52356.99
46
6 Conclusion
The UNSW School of Mechanical and Manufacturing Engineering seeks to venture into deep sea
artefact recovery and thus requires a suitable system to be designed to be used on the recently
acquired decommissioned aircraft carrier. In this proposal, Recovery Systems Inc. has presented a
finalised and validated artefact recovery system in line with AS1418.1-2002 standards for
implementation. Preliminary requirements were negotiated with the client and have been met with the
proposed solution. The recovery system features a double gantry support structure with a crane
housing and counterweight mounted upon a slewing drive. The slewing unit is mounted upon an
under carriage which traverses the central I-beams with custom made wheels to ensure versatility of
placement of the recovery device. A fixed length boom is also mounted onto the crane housing,
through which a DIEPA B75 cable acts as a winch with a custom-made steel drum for storage. The
winch is powered by a Bosh Rexroth gearbox, a fixed plug-in hydraulic motor, A4VSO 500 hydraulic
pump and a TECO Cast iron TEFC 3-phase squirrel cage induction motor. The winch lowers the
recovery device to a maximum depth of 1000 metres at 1.33 m/s. The recovery device – made from
high tensile steel – is actuated by a single, double action hydraulic return cylinder mounted to a
waterproof control box, which houses the power for the actuator - an electric hydraulic pump. The
control box sits meters above the ‘grab’ mechanism with an umbilical winch connecting the control
box to the surface to allow for actuation and control of the grab. The system has been optimised to
recover varying objects, with detachable webs in recovering ISO 1C containers, or can be configured
into an enclosed container for recovering loose artefacts, along with a camera navigation system in
order to suitable view and collect the artefacts the client wishes to recover.
The cost of the system has also been researched and broken down to display the material costs as well
as the labour involved in creating the proposed design.
The design has been validated against stress and deflection analysis, as well as using finite element
analysis to further display the feasibility of the design. Thus this design is shown to be not only
feasible but competitive, in satisfying both functional and customer requirements and thus is shown to
be the most appropriate solution available for UNSW to employ.
47
References
[2] Standards Australia, “AS1418.1-2002 Cranes, hoists and winches Part 1: General
Requirements,” 2002.
[4] Bosch Rexroth, “Winch drives MOBILEX GFT-W for mobile applications,” 2016.
[12] R. Group, “Things Worth Knowing about Hydraulic Cylinders,” February 2012. [Online].
Available: https://www.roemheld-
gruppe.de/fileadmin/user_upload/downloads/technische_informationen/Wissenswertes_Hydrau
likzylinder_en_0212.pdf. [Accessed 2018].
[13] R. G. Budynas and J. Nisbett, Shigley's Mechanical Engineering Design, McGrawhill, 2011.
48
Appendix A: Detailed Calculations
Appendix A.1: Winch Component Calculation
Rope design:
rope
Given , and :
49
7 151.7204 930.0962
8 158.0036 1088.1
9 164.2868 1252.387
Table A 1. Capacity of rope drum at different layers
The thickness of the drum is chosen to comply with AS1418.1-2002. Considering the FBD below:
50
Appendix A.2: Bearing Stress in Sheave
51
Appendix A.3: Winch Drum Flange Analysis
Considering the force on the drum by a 27-tonne line pull at the centre:
52
Secondary shear stress:
53
Appendix A.4: Winch Drum Stand Analysis
To determine
Assuming ,
The critically stressed bolt is therefore at position B. Since there are 2 bolts per side, each bolt will
support half the load.
54
Considering separation analysis at joint B with an applied external load:
90mm
100mm
Using .
Bolt stiffness:
Member stiffness:
Joint constant:
55
Total stress on the bolt:
Summary
https://www.bolt.com.au/m24-260mm-socket-head-cap-screws-zinc-plated-p-26864.html
The winch drum stand will be secured using 4x Grade 12.9 M24-3.220mm socket head cap screws
which is pretensioned using a standard 21.5mm hexagonal nut below the upper carriage. The threaded
section will have a length of:
56
Appendix A.5: Counter Weight Analysis
A B
C D
Assuming the entire system mass (including boom, jib and winch) has a center of mass at point C.
Giving the maximum weight of the Artefact will not exceed 25t, and allowing for a 5t leeway, due to
the mass of the artefact recovery device and the acceleration pull force. Force A is given by:
Assuming the boom only extends a maximum horizontal distance of AB = 6m (minimum length of
the artefact with leeway), and if the length of the frame (BD) is 12m. The counter weight force is:
Assuming that the minimum stabilizing moment is the moment generated by the counter weight, and
the maximum overturning moment is the moment generated by the hoisted load (Fa), then
However, as Fs is required to be no less than 1.4, the final counter weight mass is
57
Appendix A.6: Counter Moment Analysis
With no load being hoisted, the slewing drive bearing shaft must withstand the moment generated by
the counter weight.
From AS1418.1-2002, if the yield to strength ratio is greater than 0.7, the effective yield strength of a
material is given by:
Where:
From above the overturning safety margin is required to be 1.4 thus the maximum allowable bending
stress is:
58
For a hollow cylinder the second moment of inertia is:
As :
Thus:
59
Appendix A.7: Gantry Joint Analysis
The joints between truss members are held together as seen by the bolt holes in figure _, using Grade
12.9 M36 bolts.
Using the maximum magnitude axial force of , the shear force and stress exerted on
each bolt is equivalent to:
Considering the bolted plate to be fixed by a weld fillet on the sheet metal, the following forces act on
the weld line at point A:
The forces acting on the weld in the vertical and horizontal directions respectively are:
60
The total shear stress on the weld:
As there exist parallel loading on the weld, the weld leg size can be found using:
61
Appendix A.8: Rail Powertrain Analysis
The forces acting a powered wheel can be seen in the FBD below:
With the weight of the crane spread over 12 wheels, the reaction is:
Taking the sum of the forces in the x-direction over the whole undercarriage:
The rolling resistance is between a steel railway [7]. A maximum acceleration of 0.245
was chosen at it provides a compromise between a higher acceleration and lighter motor units,
thus the torque needed is:
The following motor from NORD Drivesystems was selected to satisfy the power requirements [8]:
Table E 1. Selected wheel drive system
Model SK 5282-180LH/4
Motor Power 22kW
Output torque 2191Nm
Transmission ration 15.38
62
Appendix A.9: Upper Carriage Analysis
Force analysis located at the upper boom
From equation 1:
The tension in the winching cable using the factored hoisted load is 545632.2 N, the force in the guy
wire is:
As there are 2 guy wires supporting the boom, each wire will support a load of 216754.537N.
The force acting on the boom is therefore
For the jib stand mounted to the upper carriage, the boom exerts a force at a central pin:
63
Considering the shear force at the pin:
64
Assuming the shear force is equally distributed:
Using a Grade 12.9 M24 bolt, the pretension on the bolt is:
65
The slewing drive uses 60xM20 bolts. The bolts experience a shear force in total,
therefore each bolt experiences .
Assuming each bolt takes an equal moment, then , where is per bolt and is the diameter of
the gear. Therefore:
66
Appendix A.10. Actuator Force Analysis
Fp
10
° B
L2
O
Recovery Device
Container Fr L1
Fn
Fbracket
L3
A
mg
In the case of the total amount of gripping force required purely from friction:
Assuming a load of 27000 kg,
Where m = 27000 kg, g = 9.81 m/s2, μ = 0.35 (assuming wet steel on polystyrene liner) [8]
Thus giving,
However it should be noted that as there are two sides to the claw, each claw will only need to
produce a force half of it, i.e.
However, the container will be held in combination by gripping and lifting from the brackets as seen
above, thus by applying Fn,applied = 115 kN, we can calculate the remaining frictional force,
Thus the frictional force that must be overcome to stop the container from slipping can be
calculated,
As each claw side of the ARD will have five brackets each, the load on each bracket can be
calculated,
67
To calculate the required force from the hydraulic cylinder, the moment is calculated around the hinge
O,
Assuming Fn occurs at the middle of the ISO 1C container with a height of 2.44m, we get
It should noted that this force is the amount required to supply sufficient force for one side of
the claw, thus the total force required from the cylinder will be double, i.e.
68
Appendix A.11: Oil Reservoir Volume Analysis
Assuming hydraulic oil is used, as it is pressurised, its volume decreases, thus the pump must provide
additional volume of oil in order to adequately account for this. This can be calculated in the
following,
Where the compressibility factor β = 70*10-6 1/bar for oil [12], and assuming a maximum ∆P
of 700 bar, thus
69
Appendix A.12: Stroke Time Analysis
The opening and closing of the recovery device can be calculated according to the stroke time of the
hydraulic cylinder [12]. The calculations are as follows,
Where dpiston = 13.03 cm, drod = 9.52 cm, stroke = 46 cm, Q = 2.73 L/min = 45.5 cm3/s,
Thus total time for a full cycle of opening and closing of the cylinder,
70
Appendix A.13: Deflection in Recovery Device
The following boundary conditions were placed in analysing the deflections for the scoop. Cylindrical
supports were placed at the hinge at which the scoop pivots upon, and was fixed in all directions
except the radial rotation. Forces were placed upon the bends due to the container sitting upon it as
well as at the connection of the scoop with the actuation jig. Deformation and stresses were seen to be
less than the allowable respective limits of 3mm deflection and 940 MPa yield stress.
71
72
For the determined shaft that would experience the greatest stresses being the shaft connecting the
scoop with the holding jig, boundary conditions selected were a force placed along the length of the
connection with the holding jig. Either end was fixed to act as reaction forces. Thus it can be seen
from the results that the deformation is less than the allowable 3mm, aswell as the maximum stress
experienced being less than the yield stress of the material 960QL steel.
73
For the lid where it is connected with the winch, it was determined that this also would be a place for
concern in light of the stresses and deflections experienced. The bolt locations at which the lid
connects with the house were considered as fixed supports, with the force due to the weight of the
payload and ARD being applied at the connection with the winch. As seen once again the deflection
and stresses are less than the allowable limit.
74
Appendix A.14: Housing Lid Analysis
322.258 kN
1100mm 1100mm
Fb Fb
Since there are 2 bolts on either end, each bolt will support half of the load.
Considering separation analysis at the bolt locations with an applied external load:
50mm
65mm
Using .
75
Bolt stiffness:
Member stiffness:
Joint constant:
76
Appendix A.16: Velocity of Under Carriage
Required velocity of the under carriage was defined to be the speed at which the crane travels an
entire long gantry (from one side of the ship to the other) within 30 minutes.
Hence:
77
Appendix A.17: Shaft Force Analysis
+V (kN)
185.57
-185.57
+ M (kN.m)
18.55 18.55
+ T (kN.m)
78
Appendix A.18: Shaft Material Properties and Correction Factors
Figure H - 1 First iteration estimates for stress concentration factor (Shigley's Mechanical Engineering Design Table 7-1)
Figure H- 1. Parameters for Marin Surface Modification Factor (Shigley's Mechanical Engineering Design Table 6-2)
79
Appendix A.19: Gantt Chart
80
Appendix B: Engineering Drawings
Appendix B.1: ARD
Appendix B.1.1: Left Web
81
Appendix B.1.2: Right Web
82
Appendix B.1.3: Scoop
83
Appendix B.1.4: Scoop Shafts
84
Appendix B.1.5: Holding Jig
85
Appendix B.1.6: Housing
86
Appendix B.1.7: Outer Arms
87
Appendix B.1.8: Arm Shafts
88
Appendix B 1.9: Housing Lid
89
Appendix B.2: Support Structure
Appendix B.2.1: Crane Wheel
90
Appendix B.2.2: Hydraulic Brake
91
Appendix B.2.3: Undertray Shaft
92
Appendix B.2.4: Overcarriage
93
Appendix B.3: Winching System
Appendix B.3.1: Winch Drum
94
Appendix B.3.2: Sheave
95
Appendix B.3.3: Drum Stand
96
Appendix B.3.4: Jib Stand
97