Daily Activity Program: Staking Inspection
Daily Activity Program: Staking Inspection
01 Staking Inspection
Conventional Crew-03
8:00 AM
1)T#116
Conventional Crew-01
02 Layout & Excavation 8:00 AM
2)T#41, 42
Conventional Crew-05
8:00 AM
3)T#87
Conventional Crew-02
1)T#72 3rd Leg, L# 3 8:00 AM
03 Steel Fixing
Conventional Crew-05
2)T#88 3rd & 4th Leg, L# 1, 3 8:00 AM
Conventional Crew-01
1)T#39 1st Leg L# 4 11:00 AM
Conventional Crew-02
04 Concrete
2)T#72 2nd Leg, L# 2 12:00 PM
Conventional Crew-03
3)T#113 1st & 2nd Leg L# 1, 3 9:00 AM
Conventional Crew-01
1)T#40 4th Leg L# 2 2:00 PM
Formwork Opening &
05
Curing
Conventional Crew-02 2:00 PM
2)T#72 1st Leg L# 2
06 Backfilling
1)Crew-01 T#16
-CPC L#1, 4, PILE 3, 4 2:00 PM
ROWs
FOUNDATION: T# 41, 44
PILING ROW: T# 20, 21
. .
CONTRACTOR’S CONSULTANT’S