Report date: 14-Jan-10

DCPP 4x135 MW Unit-1 Daily Commissioning Report Status updated for: 13-Jan-10

S.No. Status of commissioning activities Remarks


1 8 hrs trial run of HPF blower # 1A motor taken
2 8 hrs trial run of ID fan # 1A motor taken
3 8 hrs trial run of SA fan # 1B motor taken
4 Trial run of motors of scrapper of Clarifier scrapper taken
5
6
7
8

S.No. Planning for today Remarks


1 Trial run of ID fan # 1B motor
2 Trial run of Clarifier agitator & scrapper and flash mixer
3
4
5
6
7
8

S.No. Exceptions (Delays, if any) Remarks

Delayed as changeover from


1 DMCW line flushing up to Expansion tank Construction power to permanent power
is in progress. Clearance may be
available by 14-01-10
2
3
4
5
6
7
8

S.No. Critical concerns Remarks

1. Feed water line flushing to be


completed before commencement of dry
1 Refractory dry out out. Agency for pre boiler system
cleaning getting delayed.
2. Compressed air of 6kg/cm2 is required.
3. CCOE clearance for filling LDO in
tanks is required
2
3
4
5
6
7
8