The daily commissioning report for DCPP 4x135 MW Unit-1 provides status updates from January 13, 2010. On that date, 8-hour trial runs were completed for the HPF blower #1A motor, ID fan #1A motor, and SA fan #1B motor. A trial run was also taken for the motors of the clarifier scrapper. The planning for January 14 includes trial runs for the ID fan #1B motor and the clarifier agitator, scrapper, and flash mixer. There was a delay in flushing the DMCW line to the expansion tank due to the changeover from construction to permanent power, but clearance may be available by January 14. Critical
The daily commissioning report for DCPP 4x135 MW Unit-1 provides status updates from January 13, 2010. On that date, 8-hour trial runs were completed for the HPF blower #1A motor, ID fan #1A motor, and SA fan #1B motor. A trial run was also taken for the motors of the clarifier scrapper. The planning for January 14 includes trial runs for the ID fan #1B motor and the clarifier agitator, scrapper, and flash mixer. There was a delay in flushing the DMCW line to the expansion tank due to the changeover from construction to permanent power, but clearance may be available by January 14. Critical
The daily commissioning report for DCPP 4x135 MW Unit-1 provides status updates from January 13, 2010. On that date, 8-hour trial runs were completed for the HPF blower #1A motor, ID fan #1A motor, and SA fan #1B motor. A trial run was also taken for the motors of the clarifier scrapper. The planning for January 14 includes trial runs for the ID fan #1B motor and the clarifier agitator, scrapper, and flash mixer. There was a delay in flushing the DMCW line to the expansion tank due to the changeover from construction to permanent power, but clearance may be available by January 14. Critical
1 8 hrs trial run of HPF blower # 1A motor taken 2 8 hrs trial run of ID fan # 1A motor taken 3 8 hrs trial run of SA fan # 1B motor taken 4 Trial run of motors of scrapper of Clarifier scrapper taken 5 6 7 8
S.No. Planning for today Remarks
1 Trial run of ID fan # 1B motor 2 Trial run of Clarifier agitator & scrapper and flash mixer 3 4 5 6 7 8
S.No. Exceptions (Delays, if any) Remarks
Delayed as changeover from
1 DMCW line flushing up to Expansion tank Construction power to permanent power is in progress. Clearance may be available by 14-01-10 2 3 4 5 6 7 8
S.No. Critical concerns Remarks
1. Feed water line flushing to be
completed before commencement of dry 1 Refractory dry out out. Agency for pre boiler system cleaning getting delayed. 2. Compressed air of 6kg/cm2 is required. 3. CCOE clearance for filling LDO in tanks is required 2 3 4 5 6 7 8