Master Schedule WK
Master Schedule WK
cessors Resource Names 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
1 Proses Research 85 days Sun 1/1/23 Thu 4/27/23
2 Survey Lokasi 7 days Sun 1/1/23 Mon 1/9/23
3 Pembebasan Lahan 21 days Tue 1/10/23 Tue 2/7/23 2
4 Pengukuran Tanah 7 days Wed 2/8/23 Thu 2/16/23
5 Pembuatan Patokan Penggalian 14 days Fri 2/17/23 Wed 3/8/23 4
6 Pemeriksaan Patokan Pengukur 7 days Thu 3/9/23 Fri 3/17/23 5
7 Pembuatan Jalan Proyek 30 days Sat 3/18/23 Thu 4/27/23 6
8 Proses Development 150 daysFri 4/28/23 Thu 11/23/23
9 Overall Site Layout 2 days Fri 4/28/23 Mon 5/1/23
10 Tata Letak Pabrik 50 days Tue 5/2/23 Mon 7/10/23
11 Tata Letak Unit Utilitas 50 days Tue 7/11/23 Mon 9/18/23
12 Persetujuan Flowsheet 10 days Tue 9/19/23 Mon 10/2/23
13 Pembelian Alat-alat Utama 38 days Tue 10/3/23 Thu 11/23/23 12
14 Project Engineering 179 daysFri 11/24/23 Wed 7/31/24
15 Pengembangan Lokasi 14 days Fri 11/24/23 Wed 12/13/23
16 Design Pondasi 20 days Thu 12/14/23 Wed 1/10/24 15
17 Design Structural 25 days Thu 1/11/24 Wed 2/14/24 16
18 Design Mechanical System 40 days Thu 2/15/24 Wed 4/10/24 17
19 Design Instrumentasi 40 days Thu 4/11/24 Wed 6/5/24 18
20 Design Electric System 40 days Thu 6/6/24 Wed 7/31/24 19
21 Kontruksi 299 daysThu 8/1/24 Tue 9/23/25
22 Persiapan Pondasi 100 daysThu 8/1/24 Wed 12/18/24
23 Pondasi Gudang 25 days Thu 12/19/24 Wed 1/22/25
24 Pondasi Lainnya 25 days Thu 1/23/25 Wed 2/26/25 23
25 Gudang 25 days Thu 2/27/25 Wed 4/2/25 24
26 Struktural Steel 14 days Thu 4/3/25 Tue 4/22/25 25
27 Mechanical Equipment 25 days Wed 4/23/25 Tue 5/27/25 26
28 Perpipaan 30 days Wed 5/28/25 Tue 7/8/25 27
29 Listrik 25 days Wed 7/9/25 Tue 8/12/25 28
30 Instrumentasi 30 days Wed 8/13/25 Tue 9/23/25 29