ID Task Name Duration Start Finish Predecessors Resource Names 1st Half 2nd Half 1st Half 2nd

cessors Resource Names 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
1 Proses Research 85 days Sun 1/1/23 Thu 4/27/23
2 Survey Lokasi 7 days Sun 1/1/23 Mon 1/9/23
3 Pembebasan Lahan 21 days Tue 1/10/23 Tue 2/7/23 2
4 Pengukuran Tanah 7 days Wed 2/8/23 Thu 2/16/23
5 Pembuatan Patokan Penggalian 14 days Fri 2/17/23 Wed 3/8/23 4
6 Pemeriksaan Patokan Pengukur 7 days Thu 3/9/23 Fri 3/17/23 5
7 Pembuatan Jalan Proyek 30 days Sat 3/18/23 Thu 4/27/23 6
8 Proses Development 150 daysFri 4/28/23 Thu 11/23/23
9 Overall Site Layout 2 days Fri 4/28/23 Mon 5/1/23
10 Tata Letak Pabrik 50 days Tue 5/2/23 Mon 7/10/23
11 Tata Letak Unit Utilitas 50 days Tue 7/11/23 Mon 9/18/23
12 Persetujuan Flowsheet 10 days Tue 9/19/23 Mon 10/2/23
13 Pembelian Alat-alat Utama 38 days Tue 10/3/23 Thu 11/23/23 12
14 Project Engineering 179 daysFri 11/24/23 Wed 7/31/24
15 Pengembangan Lokasi 14 days Fri 11/24/23 Wed 12/13/23
16 Design Pondasi 20 days Thu 12/14/23 Wed 1/10/24 15
17 Design Structural 25 days Thu 1/11/24 Wed 2/14/24 16
18 Design Mechanical System 40 days Thu 2/15/24 Wed 4/10/24 17
19 Design Instrumentasi 40 days Thu 4/11/24 Wed 6/5/24 18
20 Design Electric System 40 days Thu 6/6/24 Wed 7/31/24 19
21 Kontruksi 299 daysThu 8/1/24 Tue 9/23/25
22 Persiapan Pondasi 100 daysThu 8/1/24 Wed 12/18/24
23 Pondasi Gudang 25 days Thu 12/19/24 Wed 1/22/25
24 Pondasi Lainnya 25 days Thu 1/23/25 Wed 2/26/25 23
25 Gudang 25 days Thu 2/27/25 Wed 4/2/25 24
26 Struktural Steel 14 days Thu 4/3/25 Tue 4/22/25 25
27 Mechanical Equipment 25 days Wed 4/23/25 Tue 5/27/25 26
28 Perpipaan 30 days Wed 5/28/25 Tue 7/8/25 27
29 Listrik 25 days Wed 7/9/25 Tue 8/12/25 28
30 Instrumentasi 30 days Wed 8/13/25 Tue 9/23/25 29

Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Milestone Manual Task External Tasks Progress


Master Schedule Group IX
Summary Duration-only External Milestone Manual Progress

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Path Predecessor Milestone Task