6 - Time Management

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

Time Management

Hammam Alkouz, PMP®


Hot Topics

• Network Diagram

• Milestone

• Critical Path

• Activity Estimation

2
Hammam Alkouz, PMP®
Monitoring &
Controlling Processes
Planning
Processes

Enter phase/ Initiating Closing Exit phase/


Start project Processes Processes End project

Executing
Processes

Process
Knowledge
Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Schedule Management
Define Activities
Sequence Activities Control
Time Estimate Activity Resources Schedule
Estimate Activity Duration
Develop Schedules
6.1 Plan Schedule Management
Plan schedule management is the process of establishing the policies,
procedures and documentation for planning, developing, managing,
execution and control the project schedule. It provides guidance on how the
schedule will be managed throughout the project.

4 Hammam Alkouz, PMP®


Schedule Management Plan
Schedule Management Plan, includes but not limited to:
 Project schedule model development
 Level of accuracy
 Units of measure
 Project schedule model maintenance
 Control thresholds
 Rules of performance measurement
 Reporting formats
 Process descriptions

5
Hammam Alkouz, PMP®
6.2 Define Activities
 The process of identifying the specific actions to be performed produce
the project deliverables.
 Activities provide a basis for estimating, scheduling, executing and
monitoring and controlling the project work.

6
Hammam Alkouz, PMP®
Define Activities (Tools & Techniques)
 Rolling Wave Planning: progressive elaboration planning where you do not to plan activities
until you start the project management process for that phase is in the project life cycle

 Activity List: The activity list is a comprehensive list including all schedule activities that are planned
to be performed on the project.

 Activity Attributes:
 Use for schedule development, selecting, ordering, sorting the planned schedule activities
 Used to identify e.g. responsible person, place, level of effort (LOE), apportioned effort (AE)

 Milestone: a significant point or event in the project.


 Not a work activity
 Checkpoint to help control the project
 Additional milestone can be add in Sequence Activities & Develop Schedule process
 The list can indicates the level of milestone (mandatory, optional, etc)
7
Hammam Alkouz, PMP®
Activity List

8
Hammam Alkouz, PMP®
Define Activity Attributes

9
Hammam Alkouz, PMP®
6.3 Sequence Activities
 Process of identifying and documenting relationship among
the project activities

10
Hammam Alkouz, PMP®
Precedence Diagramming Method (PDM)
 Precedence Diagramming Method (PDM) or Activity-on-Node (AON)
 Method used in Critical Path Methodology(CPM)
 No dummy activities
 Logical relationship:

• Finish-to-Start (FS)
• Finish-to-Finish (FF)
• Start-to-Start (SS)
• Start-to-Finish (SF)

11
Hammam Alkouz, PMP®
Applying Leads & Lags
• Use leads and lags to support realistic and achievable project schedule.
• Each activity is connected at least to one predecessor and one
successor except the start and the end.
A B C

predecessor Successor
 Leads.
 May be added to start an activity before the predecessor activity is complete.
 Lags
 Inserted waiting time between activities A A

B B

12
Hammam Alkouz, PMP®
Project Schedule Network Diagram
 A graphical representation of the dependencies among the
project schedule activities. A summary narrative can accompany
the diagram and describe the basic approach used to sequence
the activities.

13
Hammam Alkouz, PMP®
Dependency Determination
To define sequence among activity, these type of dependency are
used:
1. Mandatory (hard logic)
 Inherent in the nature of work being done or required by the contract
 E.g. You must design before you can develop
2. Discretionary (preferred, preferential, or soft logic)
 Define base on knowledge
 Can be changed if needed
 Important when how to shorten or re-sequence the project
3. External
 Based on the need t of the party outside the project

14
Hammam Alkouz, PMP®
6.4 Estimate Activity Resources
 Process of estimating the type and quantities of material, people,
equipment or supplies required to perform each activity.

15
Hammam Alkouz, PMP®
6.5 Estimate Activity Durations
 Process of approximating the number of work periods to
complete individual activities with estimated resources.
 Schedule shall be as believable and realistic as possible (do not allow padding)

16
Hammam Alkouz, PMP®
Estimate Activity Durations (Tools & Techniques)
 Analogous Estimating (Top down):
 use actual duration of previous activity (historical) that has similarity

 Parametric Estimating:
 use statistical relationship between historical data and other variables (e.g.
learning curve)
 The result can become heuristics (experience based technique/rule of thumb)

 Reserve analysis (buffer): includes contingency reserves


“A Buffer Isn’t Padding. Padding is extra time added to a schedule that you don’t really think you
need but that you add just to feel confident in the estimate. Padding is when I take a conventional
approach to building a Gantt chart, come up with three months, but tell my boss four months.”

17
Hammam Alkouz, PMP®
3-Points Estimate (PERT)
 Also called Program Evaluation and Review technique (PERT)
 Use for time and cost estimation
 Expected calculated from Most-likely, Optimistic, Pessimistic
 Range of estimate = EAD (Expected Activity Duration) +/- SD
(Standard Deviation)

Expected Standard Variance


Deviation

P  4Μ  Ο PΟ P  Ο2 
 
SD variance
6 6  6 

18
Hammam Alkouz, PMP®
6.6 Develop Schedule
 Process of analyzing activity sequences, durations, resource
requirements, and schedule constraints to create the project schedule.

19
Hammam Alkouz, PMP®
Network Diagram & Critical Path Method

EF = ES + D -1 ES = Early Start
LS = Latest Start
LS = LF – D +1 EF = Early Finish
Float (F) = LS – ES = LF – EF LF = Late Finish

20
Hammam Alkouz, PMP®
Critical Path
 Critical Path is the longest duration path. It Identify the shortest time needed
to complete a project
 There can be more than one critical path
 We don’t like critical path, it increase risk
 Don’t leave a project with a negative float, you would compress the schedule
 Near-critical path is the path that has close in duration to critical path

 Float (Slack)
 Total float: the amount of time an activity can be delayed without delaying the
project end date or intermediary milestone.
 Free float: the amount of time an activity can be delayed without delaying the
early start date of its successor(s).
 Project float: the amount of time an activity can be delayed without delaying the
externally imposed project completion date required by customer/management.

21
Hammam Alkouz, PMP®
Critical Chain Method
 Critical Chain Method focuses on resource allocation, optimization, and
leveling and on activity duration uncertainty on the Critical Path. CCM
focuses on eliminating project schedule delays due to uncertainties,
overestimation of task duration and wasted internal buffers.

1. Build a project network diagram using PDM


2. Identify critical path and enter the resource availability
3. Add duration buffers that are non-work activities to manage uncertainty.

 Add buffers within the critical path – these are known as project buffers
 Add feed buffers (if needed) in the non-critical path

22
Hammam Alkouz, PMP®
Resource Optimization Techniques
 Resource Leveling: Often cause original critical path to change and is
necessary when resources are over allocated. It is used when
resources are limited or time constrained and when specific schedule
dates need to be met.

 Resource Smoothing: Opposed


to Resource leveling, the critical
path is not changed and the
completion date may not be
delayed. So activities may be
delayed within their free and the
total float.

23
Hammam Alkouz, PMP®
Resource Optimization Techniques

24
Hammam Alkouz, PMP®
Modeling Techniques
 What-if Scenario Analysis: A process of evaluating scenarios in order
to predict their effect, positively or negatively, on project objective

 Monte Carlo (Simulation): Used when there is possibility that the


critical path will be different for a given set of project conditions.

 Using probability distribution for each activity or group of activities


 Using computer software
 Using three-point estimates and network diagram
 Help deal with “path convergence”
 Multiple paths converge into one or more activities (but adding risk)

25
Hammam Alkouz, PMP®
Schedule Compression
 Fast Tracking
 Performing critical path activities in parallel.
 Usually increase risk and requires more attention to communication.
 May need a rework.
 E.g. Design is half finished and start coding.

 Crashing
 Analyze cost and schedule trade-offs.
 Determine most compression for least cost.
 Crash the tasks that cost the least first, focusing on minimizing project cost.
 Always results in increased cost.

 Cut the Scope


 Cut the Quality
26
Hammam Alkouz, PMP®
Project Schedule
 Schedule can be shown with or without dependencies (logical relationship).

 Presented as
 Summary form e.g. Master Schedule, Milestone schedule
 Detailed form

 Format:
 Network diagram
 Milestone chart
 Bar chart (Gantt chart)

27
Hammam Alkouz, PMP®
Project Schedule

28
Hammam Alkouz, PMP®
Schedule Data
 Includes at least:
 Schedule milestone
 Schedule activities
 Activity attributes
 Assumptions & Constraints

 Additional information can be added, such as


 Resource histograms
 Cash-flow projections
 Order & delivery schedules
 Alternative schedules
29
Hammam Alkouz, PMP®
6.7 Control Schedule
 Process of The process of monitoring the status of project activities to
update project progress and manage changes to the schedule baseline
to achieve the plan.

30
Hammam Alkouz, PMP®
Q&A

31
Hammam Alkouz, PMP®

You might also like