Professional Documents
Culture Documents
6 - Time Management
6 - Time Management
6 - Time Management
• Network Diagram
• Milestone
• Critical Path
• Activity Estimation
2
Hammam Alkouz, PMP®
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process
Knowledge
Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Schedule Management
Define Activities
Sequence Activities Control
Time Estimate Activity Resources Schedule
Estimate Activity Duration
Develop Schedules
6.1 Plan Schedule Management
Plan schedule management is the process of establishing the policies,
procedures and documentation for planning, developing, managing,
execution and control the project schedule. It provides guidance on how the
schedule will be managed throughout the project.
5
Hammam Alkouz, PMP®
6.2 Define Activities
The process of identifying the specific actions to be performed produce
the project deliverables.
Activities provide a basis for estimating, scheduling, executing and
monitoring and controlling the project work.
6
Hammam Alkouz, PMP®
Define Activities (Tools & Techniques)
Rolling Wave Planning: progressive elaboration planning where you do not to plan activities
until you start the project management process for that phase is in the project life cycle
Activity List: The activity list is a comprehensive list including all schedule activities that are planned
to be performed on the project.
Activity Attributes:
Use for schedule development, selecting, ordering, sorting the planned schedule activities
Used to identify e.g. responsible person, place, level of effort (LOE), apportioned effort (AE)
8
Hammam Alkouz, PMP®
Define Activity Attributes
9
Hammam Alkouz, PMP®
6.3 Sequence Activities
Process of identifying and documenting relationship among
the project activities
10
Hammam Alkouz, PMP®
Precedence Diagramming Method (PDM)
Precedence Diagramming Method (PDM) or Activity-on-Node (AON)
Method used in Critical Path Methodology(CPM)
No dummy activities
Logical relationship:
• Finish-to-Start (FS)
• Finish-to-Finish (FF)
• Start-to-Start (SS)
• Start-to-Finish (SF)
11
Hammam Alkouz, PMP®
Applying Leads & Lags
• Use leads and lags to support realistic and achievable project schedule.
• Each activity is connected at least to one predecessor and one
successor except the start and the end.
A B C
predecessor Successor
Leads.
May be added to start an activity before the predecessor activity is complete.
Lags
Inserted waiting time between activities A A
B B
12
Hammam Alkouz, PMP®
Project Schedule Network Diagram
A graphical representation of the dependencies among the
project schedule activities. A summary narrative can accompany
the diagram and describe the basic approach used to sequence
the activities.
13
Hammam Alkouz, PMP®
Dependency Determination
To define sequence among activity, these type of dependency are
used:
1. Mandatory (hard logic)
Inherent in the nature of work being done or required by the contract
E.g. You must design before you can develop
2. Discretionary (preferred, preferential, or soft logic)
Define base on knowledge
Can be changed if needed
Important when how to shorten or re-sequence the project
3. External
Based on the need t of the party outside the project
14
Hammam Alkouz, PMP®
6.4 Estimate Activity Resources
Process of estimating the type and quantities of material, people,
equipment or supplies required to perform each activity.
15
Hammam Alkouz, PMP®
6.5 Estimate Activity Durations
Process of approximating the number of work periods to
complete individual activities with estimated resources.
Schedule shall be as believable and realistic as possible (do not allow padding)
16
Hammam Alkouz, PMP®
Estimate Activity Durations (Tools & Techniques)
Analogous Estimating (Top down):
use actual duration of previous activity (historical) that has similarity
Parametric Estimating:
use statistical relationship between historical data and other variables (e.g.
learning curve)
The result can become heuristics (experience based technique/rule of thumb)
17
Hammam Alkouz, PMP®
3-Points Estimate (PERT)
Also called Program Evaluation and Review technique (PERT)
Use for time and cost estimation
Expected calculated from Most-likely, Optimistic, Pessimistic
Range of estimate = EAD (Expected Activity Duration) +/- SD
(Standard Deviation)
P 4Μ Ο PΟ P Ο2
SD variance
6 6 6
18
Hammam Alkouz, PMP®
6.6 Develop Schedule
Process of analyzing activity sequences, durations, resource
requirements, and schedule constraints to create the project schedule.
19
Hammam Alkouz, PMP®
Network Diagram & Critical Path Method
EF = ES + D -1 ES = Early Start
LS = Latest Start
LS = LF – D +1 EF = Early Finish
Float (F) = LS – ES = LF – EF LF = Late Finish
20
Hammam Alkouz, PMP®
Critical Path
Critical Path is the longest duration path. It Identify the shortest time needed
to complete a project
There can be more than one critical path
We don’t like critical path, it increase risk
Don’t leave a project with a negative float, you would compress the schedule
Near-critical path is the path that has close in duration to critical path
Float (Slack)
Total float: the amount of time an activity can be delayed without delaying the
project end date or intermediary milestone.
Free float: the amount of time an activity can be delayed without delaying the
early start date of its successor(s).
Project float: the amount of time an activity can be delayed without delaying the
externally imposed project completion date required by customer/management.
21
Hammam Alkouz, PMP®
Critical Chain Method
Critical Chain Method focuses on resource allocation, optimization, and
leveling and on activity duration uncertainty on the Critical Path. CCM
focuses on eliminating project schedule delays due to uncertainties,
overestimation of task duration and wasted internal buffers.
Add buffers within the critical path – these are known as project buffers
Add feed buffers (if needed) in the non-critical path
22
Hammam Alkouz, PMP®
Resource Optimization Techniques
Resource Leveling: Often cause original critical path to change and is
necessary when resources are over allocated. It is used when
resources are limited or time constrained and when specific schedule
dates need to be met.
23
Hammam Alkouz, PMP®
Resource Optimization Techniques
24
Hammam Alkouz, PMP®
Modeling Techniques
What-if Scenario Analysis: A process of evaluating scenarios in order
to predict their effect, positively or negatively, on project objective
25
Hammam Alkouz, PMP®
Schedule Compression
Fast Tracking
Performing critical path activities in parallel.
Usually increase risk and requires more attention to communication.
May need a rework.
E.g. Design is half finished and start coding.
Crashing
Analyze cost and schedule trade-offs.
Determine most compression for least cost.
Crash the tasks that cost the least first, focusing on minimizing project cost.
Always results in increased cost.
Presented as
Summary form e.g. Master Schedule, Milestone schedule
Detailed form
Format:
Network diagram
Milestone chart
Bar chart (Gantt chart)
27
Hammam Alkouz, PMP®
Project Schedule
28
Hammam Alkouz, PMP®
Schedule Data
Includes at least:
Schedule milestone
Schedule activities
Activity attributes
Assumptions & Constraints
30
Hammam Alkouz, PMP®
Q&A
31
Hammam Alkouz, PMP®