Work Schedule
Example only : Offeror are requested to develop own work schedule

Works Schedule - in the form of a Gantt or Bar Chart

Aug Sep
No. Activity Dur.
Week I Week II Week III Week IV Week I Week II Week III Week IV

1 Preparation Works 3 days

2 Walling Works 5 days

Walling Treatment
3 Works 5 days

4 Electrical Works 3 days

5 Mechanical Works 3 days

6 IT Works 3 days

Built-In Custom
7 Furniture 21 days