Professional Documents
Culture Documents
CPM and Pert Analysis
CPM and Pert Analysis
CPM and Pert Analysis
ASSINGMENT
S.M.MURTAZA
ME-073
Sec: B
Batch: 2015-2016
S.M.MURTAZA
ME-073
NETWORK DIAGARAM:
GANT CHART:
S.M.MURTAZA
ME-073
PROJECT CRASHING
The probability of completion in 260 days was less than 75 %. So Crashing is required.
• Crashing Activity (A) by one day because it has less crashing cost and it lies on
CRITICAL PATH.
• Then checking the effect on the slack of different activities.
• After crashing (A) by one day there is no change in C.P as shown below.
• Also the slack of activities which are not on CP are greater. So now we can directly
crash (A) 10 times which is its limit.
S.M.MURTAZA
ME-073
GANT CHART
S.M.MURTAZA
ME-073
GANT CHART
S.M.MURTAZA
ME-073
CONCLUSION:
The total crash cost for crashing to 250 days is $15000, and now probability of completing the
project increases to 86.86%.
The total crash cost for crashing to 240 days is $34000, and now probability of completing the
project increases to 95.25%.