(Cirebon2) Material Delivery Schedule
(Cirebon2) Material Delivery Schedule
1 Test pile CSP. Dia. 600 x 100t Bottom 12 Mtr t = 100mm, Class C, K600 5 Point 5 EA Completed
CSP. Dia. 600 x 100t Middle 15 Mtr t = 100mm, Class C, K600 10 EA Completed
2 Piling Work (Onshore) CSP. Dia. 600 x 100t Bottom 12 Mtr t = 100mm, Class C, K600 243 Point 243 EA 243 20 20 20 30 30 30 30 30 20 13
Trestle Middle 6 Mtr t = 100mm, Class C, K600 12 EA 12 10 2
Middle 8 Mtr t = 100mm, Class C, K600 46 EA 46 20 20 6
3 SPP Test Pile Work SPP. Dia. 711 x 12t Bottom 12 Mtr Uncoated 5 Point 5 Ea Completed
Middle 15 Mtr Uncoated 10 Ea Completed
4 Piling Work (Offshore) SPP. Dia. 711 x 12t Bottom 15 Mtr Un-coated 509 Point 529 Ea 529 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 9
Trestle Midle 15 Mtr Un-coated 529 Ea 529 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 9
SPP. Dia. 711 x 14t Bottom 15 Mtr Un-coated 138 Point 127 Ea 127 10 10 10 10 10 10 10 10 10 10 10 10 7
5 Piling Work (Offshore) SPP. Dia. 812 x 14t Bottom 15 Mtr Un-coated 189 Point 189 Ea 189 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 9 5 5 5 5
Jetty Midle 15 Mtr Un-coated 189 Ea 189 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 9 5 5 5 5