RETAINING WALL WORK(75'-0"x6'-0")

Bill of Quantity

Sr
Particular Quantity Unit Rate Kyats Amount Kyats Total Kyats
No
(a) Material Cost
1 Cement 109.09 Bags 7500 818175.00
2 Sand 4.24 Sud 30000 127200.00
3 1/4"x3/4" Chipping 1.167 Sud 60000 70020.00
4 6"x9" Stone 14.53 Sud 45000 653850.00
5 Emulsion Paint 5.6 Gal 10000 56000.00
6 Roller 1 No 3000 3000.00
7 Brush(3") 1 No 1000 1000.00
8 Sand Paper 1 Sht 250 250.00
9 2" PVC Pipe 3 No 15000 45000.00
1774495.00 1774495.00

(b) Labour Cost


1 Mason 101.82 No 7000 712740.00
2 Worker 98.3 No 5000 491500.00
3 Painter 5.6 No 7000 39200.00
1243440.00 1243440.00

TOTAL 3017935.00