Micro Schedule - T1 Retrofitting

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

1 2 3 4

No. Work 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Jan Jan Jan Jan Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb Feb
1 Preparation Works
2 Dismantle Manhole Shell (M1) & Clean Out (C1)
3 Set Material & Equipment to Inside Tank
4 Area 1 & 2
- Dismantle Pipe Steam 2" & Support
- Gouging Welded Bottom Plate 10 mm
- Strip & Remove Mud & Dirt Soil
- Layering Mix Aggregate with Compacting
- Load Test 200 kg
- Pouring Slab Concrete K-300
- Layering Ashpalt + Sand
- Fit Up Existing Bottom Plate 10 mm
5 Area 3 & 4
- Dismantle Pipe Steam 2" & Support
- Gouging Welded Bottom Plate 10 mm
- Strip & Remove Mud & Dirt Soil
- Layering Mix Aggregate with Compacting
- Load Test 200 kg
- Pouring Slab Concrete K-300
- Layering Ashpalt + Sand
- Fit Up Existing Bottom Plate 10 mm
6 Weld Steam Pipe Support
7 Weld Joint Steam Pipe 2"
8 Remove All Material & Equipment to Outside Tank
9 Re - Install Man Hole Shell (M1) & Clean Out (C1)