HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 1 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LT/01/REV1
No.
METHOD STATEMENT
Line Test

Description
1.0 Line Test

1.1 Work Instruction Definition


 Measure the line impedance fulfills the client specification.

1.2 Test Equipment


 Insulation test set 5kV, 1 ph injection set (T3000), multimeter and HV
probe.

1.3 Reference Document


 Line conductor manufactures data sheet.

1.4 Safety Instruction (High Voltage Safety Precaution)

WARNING: induced voltage


! Earth the conductor before carryout the testing

1.5 Work Instruction Details:

1.5.1 Circuit configuration and phasing Check (Visual Check)

1.5.1.1 Facing towards the circuit at the incoming tower to


confirm the phasing of the Circuit (RYB) and confirm
the circuit configuration between circuit 1 and 2 (left or
right). Refer FIGURE 1.

1.5.1.2 Record the result and compare with drawing.

CIRCUIT NO ____ CIRCUIT NO _____

PHASE ____ PHASE ____

PHASE ____ PHASE ____

PHASE ____ PHASE ____

FIGURE 1
HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 2 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LT/01/REV1
No.
METHOD STATEMENT
Line Test

1.6 Induced voltage measurement check.

1.6.1 Ground the transmission conductor before connecting the test


Lead. Remove the ground wire at both line and measure the
voltage using the HV probe and multimeter.
1.6.2 Record the measurement for all the 3 phases.
1.6.3 Ground the transmission conductor at the end side for both line.
Measurement the voltage using the HV probe and multimeter.
1.6.4 Record the measurement for all the 3 phases.

1.7 Line phasing check.

1.7.1 Using the 5kV insulation test set, check the phasing of the
transmission line to ensure correct as per marking.
1.7.2 When inducted is voltage higher than 1 kV, the test can be
performed by grounding one point of the line under test. Connect
the yellow and blue to earth and underground the red phase (the
grounded phase has no voltage).
1.7.3 Repeat test no 11.5.3.2 for yellow and blue phasing check.
1.7.4 Record the result.

1.8 Insulation Resistance tests.

1.8.1 Using the 5 kV insulation test set, check the insulation of the
transmission line. Check for each phase to ground and phase-to-
phase conditions.
1.8.2 If induced voltage if higher than 1 kV in non-earthed condition, the
test cannot be performed. It will damage the test equipment. From
the results of the induced voltage measurement, it show the
conductor not shorted to ground.

1.9 Positive sequence Impedance Test (Z1).

1.9.1 Ground all three phases line at remote end. Check the induced
voltage in this condition. (Note : If the induced voltage is higher
than 100 V all the testing involve the impedance test cannot be
proceed)
1.9.2 Connect the surge/lighting arrester and injection test equipment
(T3000) as per FIGURE 2.
HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 3 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LT/01/REV1
No.
METHOD STATEMENT
Line Test

T 3000 ZL

D-10A/D-90V
ZL

COMMON ZL

FIGURE 2

1.9.3 Before start injection, test current must be suitable with line length in
km as shown in table below

Line Length (km) Current Injection (A)


10 UP to 16
20 Up to 8
50 Up to 4
100 Up to 2
200 Up to 1

1.9.4 Inject the voltage to circuit (phase to phase) slowly increase the
voltage output and verify the corresponding line impedance and
angle. Stop injection when the value is stable. (Note : All the results
automatically calculated by T3000 set)

1.9.5 Record the result.

2.0 Zero sequence Impedance Test (Z0).

2.1.1 Ground all three phases line at remote end. Check the induced
voltage in this condition. (Note : If the induced voltage is higher
than 100 V all the testing involve the impedance test cannot be
proceed).
HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 4 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LT/01/REV1
No.
METHOD STATEMENT
Line Test

2.1.2 Connect the surge/lighting arrester and injection test equipment


(T3000) as per FIGURE 3)

ZL
T3000

D-10A / D-90V ZL

COMMON ZL

FIGURE 3
LINE 1
ZL
T 3000
D-10A / D-90V
ZL
COMMON
ZL

10A 10V

ZL LINE 2

ZL

ZL
HG Power Transmission Sdn. Bhd.

Client : Tenaga Nasional Berhad Date : 01/10/2018


Contract Title 500kV Double Circuit Transmission Line from PMU Bentong
South to PMU Lenggeng (Point L to LGNG) and 275kV Double
: Circuit Transmission Line from PMU Lenggeng to PMU Mahkota
Page : 5 Of 3
Cheras (Point L to Lenggeng)
Doc.
Contract No : TNB 369/2018 : MS-LT/01/REV1
No.
METHOD STATEMENT
Line Test

2.1.3 Before start injection, test current must be suitable with line length in km
as shown in table below.

Line Length (km) Current Injection (A)


10 UP to 16
20 Up to 8
50 Up to 4
100 Up to 2
200 Up to 1