CRYOGENIC TANK / INSULATION

TENDERING PHILOSOPHY
Sr. No. Points to be clarified. Cryogenic Tank / Insulation Jai Comments
1 Single Vendor (EPC) Concept for Single vendor P.O. For design, engineering, EPC recommended
Tank construction & Insulation fabrication drawing, fabrication, material
jobs. procurement, all statutory approvals of
drawings as well as fabrication etc.
Insulation of bottom, shell and suspended roof EPC recommended
thermal design, material procurement &
application also to be done by Tank fabrication
vendor.
2 Civil jobs No civil job by tank vendor like foundation etc. Civil in NGC Scope. All civil information
details to be provided by vendor
3 Material procurement & supply Material procurement of major items like
plates etc. by whome (vendor or owner)? If by Vendor
owner(what all)
4 TPI (Third Party Inspection) TPI will be appointed by whom (vendor or Vendor, parties will be specified by
owner)? Should design review also be part of owner.
TPI scope including QAP? LAS to advise on design review & QAP
5 Construction power Who will provide construction power at site? DG sets by vendor
DG sets to be arranged by owner or vendor?
6 Site infrastructure Infrastructure at site, water supply by vendor Site infrastructure & water supply by
or owner? vendor
7 Prefabrication space/ yard Prefabrication yard or place at site will be A site within the land will be allocated to
provided by owner or vendor to arrange by vendor. Vendor manpower should not
himself? stay at site
8 Storage yard Material storage facilities Will be provided. Security in vendor
9 Bidding concept Bidding concept: scope

1) Tech bid- a) Owner(NGC), b) LAS Tech : NGC, LG & LAS (Soft & hard
2) Price bid- NGC copy)
Price : NGC (hard copy only) in sealed
cover
Address for bid submission? Krishnapatnam Address
10 Delivery schedule & start date Delivery schedule is 10 months: Nov 2019 to
Aug 2020.
Is it matching with project schedule? To be discussed
11 Supply by owner Free issue material list if any Instrumentation ??
Submersible pumps ??
12 Material supply origin Whether China origin material acceptable or To be discussed
not
13 Bidding Qualification 1) EMD, 2) Turnover, 3) Solvency, 4) Work Ok
qualification
14 Arbitration clause Arbitration clause & court jurisdiction? Owner Jurisdiction to be Chennai
to review or support draft.
Please refer Annexure. Wil revert after legal check
15 Proposed Payment schedule (i) 20% against fabrication, Design completion & TPI / LAS reiew /
(ii) 25% against erection, acceptance
(iii) 35% against welding, Order of materials
(iv) 10% against testing & calibration, Receipt of materials at Site
(v) 10% after completion/ submission of Fabrication, erection & welding -
handover documents including As-built progressive
drawings & bank guarantee for period stated (iv) and (v) are ok
above.
16 Bank gaurantee format Please refer Annexure. Wil revert after legal check

Purchase requisition can be made accordingly after freezing above points.