National Building Code PD 1096 148 Pagespdf
National Building Code PD 1096 148 Pagespdf
Fees
Administrative Sanction
Introduction
• Lessons learned from the implementatio
BP 344
Tragedies
Fees Imposition
Building Fees
Fines, Surcharges and Penalty
Application for Building Perm
• Building Permit – Section 301 / PD 1096 (New
IRR)
Section 301 – No person, firm or corporation, including any
agency or instrumentality of the government shall construct,
alter, repair, convert, use, occupy, move, demolish and add
any building/structure or any portion thereof or cause the
same to be done, without first obtaining a building permit
therefore from the Building Official assigned in the place
where the subject building/structure is located or to be done.
LOCATION OF CONSTRUCTION LOT NO._________ BLK NO ________ TCT NO ________ TAX DEC NO ________
STREET _______________ BARA NGAY _______________ CITY /MUNICIPALITY OF _______________________
SCOPE OF WORK
1 NEW CONSTRUCTION 4 RENOVATION ________________ RAISING ___________________________
ERECTION ______________ CONVERSION ________________ ACCESORY BUILDING STRUCTURE
22 ADDITION ______________ 3 REPAIR _____________________ 5 Demolition
OTHERS (specify) ______________
ALTERA TION ___________ MOVING _____________________ _____________________________
USE OF CHARAC TER OF OCCUPANC Y
GROUP A : RESIDENTIAL DWELLINGS GROUP F: INDUSTRIAL OTHERS (specify) ___________
GROUP B: RESIDENTIA L HOTEL APARTMENT GROUP G: INDUSTRIA L STORAGE AND HAZA RDOUS
GROUP C: EDUCATIONAL, RECREA TIONAL GROUP H: RECREATIONA L ASSEMBLY OCCUPANT LOAD LESS
GROUP D: INSTITUTI
ONAL GROUP :I RECREATIONALASSEMBLY OCCUPANT LOAD 1000
GROUP E: BUSINESS AND MERCA NTILE GROUP J: A GRICULTURA L A CCESSORY
OCCUPA NCY CLASSIFIED__________________________ TOTA L ESTIMATED COST P_______________________
NUMBER OF UNITS _______________________________ PROPOSED DATE OF CONSTRUCTION ___________
TOTAL FLOOR A REA __________________SQUARE METERS EXPECTED DA TE OF COMPLETION ______________
Application for Building Permit
• Treatment of Data/Information Entries
Box 1 – Detail of Application
Owner/Applicant
LAST NAM E FIRST NAM E MI TIN
“Corp” or“Inc”
“Proprietor”, “Prop” or- “Owner”
- - Corporation
Single Prop.
“Partners”, “Limited”, “Associates” -Partnership
“Cooperative” or “Coop” - - Cooperative
“If name of a person” - - Private Individuals
Application for Building Permit
• Treatment of Data/Information Entries
Box 1 – Detail of Application
Form of Ownership
LOCATION OF CONSTRUCTION LOT NO._________ BLK NO ________ TCT NO ________ TAX DEC NO ________
STREET _______________ BARA NGAY _______________ CITY /MUNICIPALITY OF _______________________
SCOPE OF WORK
1 NEW CONSTRUCTION 4 RENOVATION ________________ RAISING ___________________________
ERECTION ______________ CONVERSION ________________ ACCESORY BUILDING STRUCTURE
22 ADDITION ______________ 3 REPAIR _____________________ 5 Demolition
OTHERS (specify) ______________
ALTERA TION ___________ MOVING _____________________ _____________________________
USE OF CHARAC TER OF OCCUPANC Y
GROUP A : RESIDENTIAL DWELLINGS GROUP F: INDUSTRIAL OTHERS (specify) ___________
GROUP B: RESIDENTIA L HOTEL APARTMENT GROUP G: INDUSTRIA L STORAGE AND HAZA RDOUS
GROUP C: EDUCATIONAL, RECREA TIONAL GROUP H: RECREATIONA L ASSEMBLY OCCUPANT LOAD LESS
GROUP D: INSTITUTI
ONAL GROUP :I RECREATIONALASSEMBLY OCCUPANT LOAD 1000
GROUP E: BUSINESS AND MERCA NTILE GROUP J: A GRICULTURA L A CCESSORY
OCCUPA NCY CLASSIFIED__________________________ TOTA L ESTIMATED COST P_______________________
NUMBER OF UNITS _______________________________ PROPOSED DATE OF CONSTRUCTION ___________
TOTAL FLOOR A REA __________________SQUARE METERS EXPECTED DA TE OF COMPLETION ______________
Application for Building Permit
• Treatment of Data/Information Entries
Box 1 – Detail of Application
Number of Units
DIV. 2 1 2 3 3 1 5 4 1
(25)
NBC – IRR/2005 Assessment of Fees & other
Charges
ADMINISTRATION AND ENFORCEMENT
IRR VII – Classification of all Building by Use
Occupancy vs NCSO Code
A B C D E F G H I
10/15 16/19 (40 to 45) 20/29 30/35 ( o t h e r s) 71/
B
G
E H A A
t.
u
d si az sse sse
p
u
R l
c. I n ar
A
m m
a
n e
it
In
,l
st d
& ss b b
O n
d o
e
it ly ly
e t R / u u
d o tu st s , ,
i
M
U
e i O O
s H
/
e .,
cre n
o erc rial S L L
P R s
al o t < >
e tai an ra 1 1
R
o 0 0
n ilt g
e 0
0
0
0
e
DIV. 2 1 2 3 3 1 5 4 1
(25)
NBC – Example NCSO Type of Occupancies
ADMINISTRATION AND ENFORCEMENT
23 – Hotel/Motel
Inns, Pe nsion houses
NBC – Example NCSO Type of Occupancies
ADMINISTRATION AND ENFORCEMENT
Use or Type of Occupancy
• Commercial:
24 – Office Condominium/Business/Office
Transportation Office, Radio & TV
Broadcasting & Transmitt ing Studios
25 – Restaurants, Etc.
Cabarets, Day & Night Clubs, Disco
pads/houses, Ba r & Cocktai l Lounges, Beer
Gardens, Music Lounges, Night Club
26 – Shop
Beauty P arlor, Photo Developing Shop,
Engraving Shop, Lau ndry Shop, Painter
Sho
NBC – Other USE/Occuppancies
ADMINISTRATION AND ENFORCEMENT
BOX 3 – Applican t
BOX 4 – Lot Owner
A PPLICA NT WITH
MYCONSENT:LOTOWNER
A ddress Address
CTC
No. Date
Issued PlaceIssued CTC
No. DateIssued PlaceIssued
NBC – Other Definition / Items
ADMINISTRATION AND ENFORCEMENT
Total Estimated Cost –
Use: Table II.G.1 – Fixed Construction Cost
Proposed Datebe
Should ofin
Construction –
numeric figures; Ex. June 19,
2006, should written as 061906.
Expected Date of Completion – Should be later
than the proposed date of construction and
should also be written in numeric figures.
Total Floor Area – Should be reported in square
meter, and there should always be non-
zero entry for all types of new building
construction and additions to existing building
ASSESSEDFEES ASSESSEDBY AM OUNTDUE DATEPAID O.R.NUM BER NS
FILINGFEE
PROCESSINGFEE
LOCATIONAL /ZONING OF LAND USE
LINE AND GRADE (Geodetic)
FENCING
ARCHITECTURAL
CIVIL/STRUCTURAL
ELECTRICAL
MECHANICAL
SANITARY
PLUMBING
ELECTRONICS
INTERIOR
ONE HALF (1/2) OF FIRE SERVICE FUND(FSF)
TOTAL
Date Issued -----------------------
Blank
Blank
Blank
Blank
Blank
Blank
Location of Construction
021405
MMDDYY
Inter-disciplinary undertakin
CLIENT
to attain nation’s
towards a goal ordevelopm
objectiv
Discipline/Professionals
& Stakeholders
1. Building Technical
2. Building Official
3. Owner/Applicant
4. LGU
NBC – (New) IRR, similar entries on Ancillaries
JURISDICTION TO VARIOUS
ANCILLARY ON ACCESSORY
PERMITS
Ancillaries
Accessories
NBC– IRR/Organization of Forms; BP, Ancillary/Accessory
Ancillary/Accessory Perm
Per
ADMINISTRATION AND ENFORCEMENT
Organization of the Forms
Building
Bldg Permit, Form No. B-01 5 copies/
Permit
5 copies/
(Notarized) Architectural Permit,
Civil/Structural Form
Permit, No.
Form A-01
No. A-02 5 copies/
Electrical Permit, Form No. A-03 5 copies/
Ancillary Mechanical Permit, Form No. A-04 5 copies/
Sanitary Permit, Form No. A-05 5 copies/
Permits Plumbing Permit, Form No. A-06 5 copies/
(Not Notarized) Electronic Permit, Form No. A-07 5 copies/
Construction Phase
restriction of (law)
shall be done by anyregulation,
third partyand therefore
unless no change
violation of
regulation is/are evident/s.
Jurisdi ction & authority in Design & Construction
a) Owner – Right to improve
b) Designer – Profession / conceptualize/ expertise
c) Regulators – Government/control/ PD 1096/pol
d) Constructor – Deliver the goods / compliance.
NBC – IRR/2005 Pre Const/ Step 1
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Pre – Construction Phase/ Steps & Procedures in
Processing application for Building Permit
Step 1 – Receiving
• documents check for completeness including
clearances,
• if found incomplete or deficient, advise
applicant to complete/correct or rectify,
• requirements compliance, advise applicant
pay the non-refundable application fee.
• proceed/forward to Line & Grade Section.
NBC – IRR/2005 Pre Construct
Phases of Building Permit/Construction –
Evaluation –
– the process of assessing compliance of a
proposed project (construction) with
existing regulation or law/s promulgated
for the purpose of protecting the public
against excessive or lacking of
requirements of what is necessary.
N
OI Determination of violations
T
A
IC
PERMIT L
P
a) IRR 5, Section 2 : Adm & Enf.
NON- TO ISSUE P
A
ISSUANCE MAGNA CARTA /Disabled Pe
INCORPORATED
WHEN IN DESIGN &
NOT FACILITIES
Penalty:
INSTALLATION
CONSTITUTE
1st violation: P50T to 100 T or/w 6 Mo
NON-COMPLIANCE
VIOLATION BY
in prison up to 2 yrs or both.
-STAIRS
-OWNER -WALKWAYS 2nd violation: P100 to 200T or/w 2 Yrs
-CONTRACTOR -CORRIDORS
in prison up to 6 yrs or both.
-ARCHITECT -DOORS/ENTR
-ENGINEER -WASH/REST RM Abused: not less than 6 Mo in prison &
-BLDG OFF’L -LIFTS/ELEV imposed P5T to P50T or both.
-RAMPS, ETC.
BP 344 – D eter mination of violation/ BP 344 provisio
provision
N
OI Determination of violations
T
A
IC
PERMIT L
P
b) IRR Section 4.
NON- TO ISSUE P
A
ISSUANCE BP 344 /Disabled Per.
INCORPORATED
WHEN IN DESIGN &
NOT FACILITIES
Penalty:
INSTALLATION
CONSTITUTE
6 Mo. In prison and fine of P2T
NON-COMPLIANCE
VIOLATION BY
to P5T or both.
-STAIRS
-OWNER -WALKWAYS
-CONTRACTOR -CORRIDORS
-ARCHITECT -DOORS/ENTR
-ENGINEER -WASH/REST RM
-BLDG OFF’L -LIFTS/ELEV
-RAMPS, ETC.
BP 344 – Jurisdiction of Penalty
N
OI Jurisdiction of Penalty
T
A
IC
PERMIT L
P
a) Based on the New IRR. – the BO
NON- P
TO ISSUE A deny the application for Building
ISSUANCE
INCORPORATED Permit. The applicant can make appeal
WHEN IN DESIGN &
NOT FACILITIES
INSTALLATION b) In both cases, non-compliance can b
CONSTITUTE NON-COMPLIANCE filed in civil court for imposition of
VIOLATION BY -STAIRS penalty.
-OWNER -WALKWAYS
-CONTRACTOR -CORRIDORS Note: BO cannot impose
-ARCHITECT -DOORS/ENTR
imprisonment term to violator o
-ENGINEER -WASH/REST RM BP 344
-BLDG OFF’L -LIFTS/ELEV
-RAMPS, ETC.
PROCESSING APPLICATION FOR BLDG PERMITS
PAYMENT OF
FEES
LAND USE AND
ZONING
MUNICIPAL CIVIL/ 4
TREASURER STRUCTURAL
PLUMBING 5
13
REALEASE
10
SANITARY 6
VERIFICATION OF ARCHITECTURAL FINAL EVALUATION
LINE AND GRADE
ZONING & OTHER INTERIOR/ AND
(GEODETIC)
CLEARNCES ACCESSIBILITY RECOMMENDATION
ELECTRICAL 7
1 2 3
APPLICATION
ELECTRONICS &
T RUE COPY TCT COMMUNICATION
TAXDEC & RCPT
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN MECHANICAL 8
(A/S, S/P, E & M)
GOV’T & EXEMP
OTHERS 9
REQUIRED (SPECIFY, REPAIR)
CLEARANCES
NBC- IRR/Administration&Enforcement
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
1 2 3
APPLICATION
Line & Grade:
T RUE COPY TCT - Set L&G per T CT
TAXDEC & RCPT - Easements & Access
- Determine pay items
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
- Sect 804/ Courts & Yards, min ho rizontal distance not l ess than
BO Evaluation of Compliance
1 & 2 sty bldg., 1.5m on cluster bldg.
1.5m 1.5m
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
B
u
1 2 3 il
d
in
APPLICATION g
p
r
o Courts
T RUE COPY TCT p
e
TAXDEC & RCPT r
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
Building proper
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
BO Evaluation of Compliance
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
BO Evaluation of Compliance
BO Evaluation of Compliance
- Sect 805/ Ceiling Heights
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
BUILDING
SECTION
– School rooms :
• Volume- - - - - - - 3.00cu.m.
• Floor area/person - - 1.00 sq. m
– Workshops, Factories, and Offices:
• Volume- - - - - - - 12.00cu.m.
• Floor area/person - - - 1.00 sq. m.
– Habitable rooms:
• Volume- - - - - - - 14.00cu.m.
• Floor area/person - - - 1.00 sq. m.
- Sect 808/ Window Opening s for any room without artificial venti
BO Evaluation of Compliance
stem shall b e
NBC- IRR/Administration&Enforcement
ARCHITECTURAL
INTERIOR/
ACCESSIBILITY
NBC- IRR/Administration&Enforcement
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
CIVIL/ 4
STRUCTURAL
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
CIVIL/ 4
STRUCTURAL
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
Boring and Load Test (in accordance with NSCP) for the following;
1 2 3
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
Foundation Investigation:
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE Foundation Investigation required when using Table 304-1;
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
a) Assum ption limitation
1 2 3 - Continuous Footing w/
APPLICATION - Isol ated Footing with load > 250
T RUE COPY TCT b) Higher values set by Tab 304-1 on soil bearing
TAXDEC & RCPT in refe rence to min depth
PD 1096
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
7
forbelow, increase of300
each additional 20%mm
is allowed
of
width and/or depth to a maximum
value of three times the designated t(min) = 250mm
value. Dp(min) = 600mm
NBC - IRR/ Administration & Enforcement
91
Structural Evaluation Sheet
(Note: Reference is also made to Section 416 – Precast Concrete where test and
acceptance is also required by the Code)
APPLICATION 4. Sect 302 PD 1096- Foundation Investigation c) RSB shall be between (0.01- 0,08) of gross s
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN
(A/S, S/P, E & M)
GOV’T & EXEMP
REQUIRED
CLEARANCES
NBC- IRR/Administration&Enforcement
Spiral Colum
250 mm
n
300 mm
NSCP on Concrete:
Limiting Dimension of Column:
Equivalent circular column – As an exception to the general
procedure of utilizing
be permissible thea full
to design grosscolumn
circular area ofand
the column
to build section,
it with aitsq
octagonal, or other shaped section of the least lateral dimensio
such case, the allowable load, the gross area considered, an
required percentage of reinforcement shall be taken as those of
circular column.
16 mm Ф RSB
(minimum size)
MUNICIPAL CIVIL/ 4
TREASURER STRUCTURAL
PLUMBING 5
Could be less processing time
or more complicated for large stru
SANITARY 6
VERIFICATION OF ARCHITECTURAL
LINE AND GRADE
ZONING & OTHER INTERIOR/
(GEODETIC)
CLEARNCES ACCESSIBILITY
ELECTRICAL 7
1 2 3
APPLICATION
ELECTRONICS &
T RUE COPY TCT COMMUNICATION
TAXDEC & RCPT
(LEASE
SETS OFCNTRCT)
PLANS
& SPECIFICATN MECHANICAL 8
(A/S, S/P, E & M)
GOV’T & EXEMP
OTHERS 9
REQUIRED (SPECIFY, REPAIR)
CLEARANCES
NBC- IRR/Administration&Enforcement
CIVIL/ 4
• Final Evaluation by the Chief Proc essing Unit STRUCTURAL
ELECTRONICS &
COMMUNICATION
MECHANICAL 8
OTHERS 9
(SPECIFY, REPAIR)
NBC- IRR/Administration&Enforcement
13 MUNICIPAL PLUMBING 5
TREASURER
REALEASE 10
SANITARY 6
RECEIVINGV FINAL EVALUATION
LINE AND GRADE ARCHITECTURAL BUILD
ERIFICATION OF
(GEODETIC)
INTERIOR/ AND
CLEARNCES ACCESSIBILITY
RECOMMENDATION
ELECTRICAL 7
1 2 3 • Signs/issues Building
Permit
APPLICATI and accompanying
ELECTRONICS &
ON Ancillary/Accessory Permits
T RUE COPY TCT COMMUNICATION
TAXDEC & RCPT
1. refer one set of plans/ upon presentation of
(LE ASE
OF CNTRCT) Official Receipts and Fire
SETS PLANS specs to the BFP c/o
& SP ECIFICATN City/Mun. Fire Marshall, Safety Check issued by
MECHANICAL 8
(A/S, S/P, E & M) to act in 5 days. The BFP & Forward all
GO V’T & EXEMP
processed/signed document
OTHERS 9 for Recording and
REQUIRED
(SPECIFY, REPAIR) Releasing Section.
CLEARANCES
NBC - IRR/ Administration &
Enforcement Administrative & Enforc
NBC – (NR)IRR BP Processing Flow
CHIEF, PROCESSING CHIEF, PROCESSING
MUNICIPAL DIVISION DIVISION
TREASURER (Recommendation) (Recommendation)
ARCHITECTURAL
REALEASE
CIVIL/
STRUCTURAL
VERIFICATION OF
LINE AND GRADE ASSESSMENT BUILDIN
ZONING & OTHER
(GEODETIC) OF FEES
CLEARNCES
PLUMBING
APPLICATION
(LEASE
SETS OFCNTRCT)
PLANS DEPUTY
& SPECIFICATN ELECTRICAL
(A/S, S/P, E & M) DEPUTY
GOV’T & EXEMP
DEPUTY
PAYMENT OF
FEES
LAND USE AND
ZONING
MUNICIPAL CIVIL/
TREASURER STRUCTURAL
PLUMBING
REALEASE
SANITARY
VERIFICATION OF ARCHITECTURAL FINAL EVALUATION
LINE AND GRADE
ZONING & OTHER INTERIOR/ AND
(GEODETIC)
CLEARNCES ACCESSIBILITY RECOMMENDATION
ELECTRICAL
APPLICATIO
N ELECTRONICS &
TR UE COPY T CT COMMUNICATION
TAXDEC & RCPT
(LEASE
SETS OF CNTRCT)
PLANS
& SPECIFICATN MECHANICAL
(A/S, S/P, E & M)
GOV’T & EXEMP
OTHERS
REQUIRED (SPECIFY, REPAIR)
CLEARANCES
ARCHITECTURAL
REALEASE
CIVIL/
STRUCTURAL
VERIFICATION OF
LINE AND GRADE ASSESSMENT BUILDIN
ZONING & OTHER
(GEODETIC) OF FEES
CLEARNCES
PLUMBING
APPLICATIO
N SANITARY
TR UE COPY T CT
TAXDEC & RCPT
(LEASE
SETS OF CNTRCT)
PLANS DEPUTY
& SPECIFICATN ELECTRICAL
(A/S, S/P, E & M) DEPUTY
GOV’T & EXEMP
DEPUTY
Flow more4
11 7
6
2
5
4
3
Flow more5
Flow more7
NBC – (New) IRR Process Concept, Diagram
Institute Strategic
measure to meet Code
requirement by both
designer & evaluator.
NBC – IRR/2005 Pre Construct
Phase, Definitio
ADMINISTRATION AND ENFORCEMENT
Phases of Building Permit/Construction –
Definitions Relevant to Evaluation/processing
Storey – bet. succ. floor surfaces or floor/roof
Level, (or Split) – (refer to elevations)
Roof Deck – (required to have parapet vs flr. lev
Penthouse – simply a floor level/area > 6 sqm.
VIOLATIONS -
A. Initiation of action usually arises from a complaint and/or findings of
violation involving the following;
Activities/ Type Fine, upon
Compliance
Violations Violation determination
1. Erecting, constructing,
altering, repairing, moving,
converting, installing or Sect. 301 Grave P 10,000.00
demolishing a private or Violation
private building/structure
without building and/or
demolition permit.
126
Administration & Enforcem
NBC – (Rev) IRR
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/ Type Fine, upon
Violations Compliance Violation determination
127
NBC – (Rev) IRR
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/ Type Fine, upon
Compliance
Violations Violation determinati
3. Unauthorized change,
modification or alteration
during construction in the Grave P 10,000.00
Sect. 304
duly submitted plans and Violation
specifications on which the
building permit is based.
128
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/ Type
Violations Compliance Violation
129
NBC – (Rev) IRR
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/ Type Fine, upon
Violations Compliance Violation determinatio
130
NBC – (Rev) IRR
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/ Type Fine, upon
Violations Compliance Violation determinati
6. Use or occupancy of a
building/structure without
Certificate of
Occupancy/Use even if Less Grave P 8,000.00
constructed under a valid Sect. 309
Violation
building permit.
131
Administration & Enforcem
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
132
NBC – (Rev) IRR
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Note: Mandatory
133
Administration & Enforcem
VIOLATIONS -
A. Initiation of action usually arises from a complaint involving the
following;
Activities/
Compliance Type Violation
Violations
134
NBC – (Rev) IRR
VIOLATIONS -
135
Administration & Enforcem
NBC – IRR/2005 Assessment of Fees & other
Charges
ADMINISTRATION AND ENFORCEMENT
1. Basis of Assessment
• Type of Occupancy or Use of the Building
• Cost of Construction
• Floor Area, and
• Height.
NBC – IRR/2005 Assessment of Fees & other
Charges
ADMINISTRATION AND ENFORCEMENT
ASSESSMENT OF FEES & OTHER CHARGES
2. Cost of Construction uniform application
regardless of the following;
• Type of construction, and
• Cost of construction
• Doesconstruction/
not depend ofbill
submitted material
of materials of
submitted
by designer, which in former days;
- Rich field of graft and corruption
- Source of “cashunduan” of what should b
adopted, usually favoring the applicant
causing disadvantage to the governm
for allowing collecting reduced fees.
- Repair, Cert of Occupancy & Fire Fund use
cost of construction
ORGANI ZATION AN D ENFORCEMEN T: Reports Gener ation
NBC – (NR)IRR Organization & Enforcement – report generation Administration & Enforce
NBC – IRR/2005 Assessment of Fees & other Charges
Features:
• Payment shall be per calendar month,
• Compliance with of
requirement theIRR
safety
XI.and protective
Adm & Enf (Safety Net)
NBC – IRR/2005 Assessment of Fees & other Charges
ADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Ground P reparation and Excavation Permit
Features:
Excavations > 50.00 cu m and 2m in depth
Required: GP/EP
Solution: (Ref. Sect 304(4) – Processing BP
Sect 9(b)(i)(a to f) – Sched. of Fees
Form: NBC Form No. 8- 02 w/ cond.
Features:
Excavations > 50.00 cu m and 2m in depth
Required: GP/EP
Limit of Permit:
Max Volume – 100.00 cu m.
&Depth– 3.00m.
Duration – 30 days (or superseded by
the issuance of the
principal Building Permit)
NBC – IRR/2005 Assessment of Fees & other Charges
ADMINISTRATION AND ENFORCEMENT
Computation of Building Permit Fees (Hypothetical)
Repairs Differentiated fro m Renovation /Altera tion
Definitions:
Repair – dismantling/replacing dilapidated/
deteriorated part/s of existing building
with same or equivalent material/s.
Fee – Ref. Sect 9(i), Schedule of Fees.
Cemeteries,
constructionMausoleum, columbarium,
– Ref. Sect 8 (p). tombs, etc
Certi ficate o f Use: Group J, Div. 3 & Ancillaries –
bank/record vaults, swimming pools, towers, silos,
smoke stacks/chimney/ovens/kilns/furnaces/tanks, etc
Fees Silos, IRR II, Sect 8g