Professional Documents
Culture Documents
SRT - TXT - EnergyEfficientPum inJetMachine (250 KG) - SRT - TXT - EEP - 09 PDF
SRT - TXT - EnergyEfficientPum inJetMachine (250 KG) - SRT - TXT - EEP - 09 PDF
ON
ENERGY EFFICIENT PUMP FOR JET DYEING
MACHINE (250 KG)
(SURAT TEXTILE CLUSTER)
Acknowledgement
We have received very encouraging feedback for the BEE SME Program in various SME
Clusters. Therefore, it was decided to bring out the DPR for the benefits of SMEs. We sincerely
thank the officials of BEE, Executing Agencies and ISTSL for all the support and cooperation
extended for preparation of the DPR. We gracefully acknowledge the diligent efforts and
commitments of all those who have contributed in preparation of the DPR.
Energy Efficient Pump For jet Machine (250 kg)
Contents
List of Annexure vii
Executive summary ix
1 INTRODUCTION.......................................................................................................... 1
List of Annexure
List of Tables
List of Figures
vii
Energy Efficient Pump For jet Machine (250 kg)
List of Abbreviations
FD Forced Draft
ID Induced Draft
EE Energy Efficient
viii
Energy Efficient Pump For jet Machine (250 kg)
EXECUTIVE SUMMARY
Zenith Energy Services Pvt. Ltd is executing BEE-SME program in Surat textile cluster,
supported by Bureau of Energy Efficiency (BEE) with an overall objective of improving
the energy efficiency in cluster units.
Surat textile cluster is one of the largest textile clusters in India; accordingly this cluster
was chosen for energy efficiency improvements by implementing energy efficient
measures/technologies, so as to facilitate maximum replication in other textile clusters
in India.
The main energy forms used in the cluster units are electricity and fuel such as wood,
coal, natural gas and other biomass product. Mostly used in boilers, thermopac, Jet
dying, stenter, loop machine, scouring, bleaching, Jiggers, Jumbo, hydro extractor,
small pumps and lighting.
Installation of Energy Efficient Pump with Jet dying machine or Jigger or Jumbo will
reduces electricity consumption & production cost and also reduces the
environmentally harmful green house gases emission.
Project implementation i.e. installation of energy efficient pump (250 kg) for jet machine
will lead to reduction in electricity consumption by 56,280 kWh per annum however;
this intervention will not have any effect on the existing consumption pattern of fossil
fuel.
Total investment, debt equity ratio for financing the project, monetary savings, Internal
rate of return (IRR), Net present value (NPV),Debt service coverage ratio (DSCR),
Return on investment (ROI) etc. for implementing energy efficient pump is furnished in
Table below:
ix
Energy Efficient Pump For jet Machine (250 kg)
The energy use technology studies would provide information on technology status,
best operating practices, gaps in skills and knowledge on energy conservation
opportunities, energy saving potential and new energy efficient technologies, etc for
each of the sub sector in SMEs.
In most of the cases SME entrepreneurs are dependent on the locally available
technologies, service providers for various reasons. To address this issue BEE has
also undertaken capacity building of local service providers and entrepreneurs/
Managers of SMEs on energy efficiency improvement in their units as well as clusters.
The local service providers will be trained in order to be able to provide the local
services in setting up energy efficiency projects in the clusters
The objective of this activity is to facilitate the uptake of energy efficiency measures
through innovative financing mechanisms without creating market distortion.
x
Energy Efficient Pump For jet Machine (250 kg)
1 INTRODUCTION
The products manufactured in Surat Textile Cluster are synthetic sarees and dress
materials and the products are renowned in the country and abroad. The main raw
material for the cluster units is grey cloth and is procured from local weaving units and
agents. The cost of energy (electrical and thermal energy) as percentage of
manufacturing cost varies between 12 and 15%.
Majority of the cluster units are of integrated type, where the raw material “grey cloth”
is processed in-house to the final product like sarees and dress materials. Most of the
units of the cluster are working on Job basis, where the textile agents will provide
design and grey cloth and the unit’s process as per design provided by the clients. The
energy cost is next to the raw materials cost.
The main process operation for dyeing and printing process of synthetic sarees and
dress materials adopted in cluster units are as follows:
Fabric pre-treatment
The main purpose of the fabric pre-treatment process is to remove oil, grease and
other materials and to whiten the grey cloth though bleaching. The various process
adopted in pre-treatment are scouring, bleaching and shrinking process.
Dyeing
Dyeing is the process of imparting colors to the material through a dye (color). In which
a dye is applied to the substrate in a uniform manner to obtain an even shade with a
performance and fastness appropriate to its final use. This process is mainly performed
in Jet Dyeing Machines and Jigger machines
Dyeing of fabric is carried out in jet dyeing machines. The temperature of the solution
is raised to 50°C. Concentrated dyestuff solution is prepared separately and is added
to the liquor. After the addition of dyes, the temperature is raised to 130°C and
maintained for about 60 minutes.
After whitening/dyeing, the fabric is unloaded from the machine and taken to the
folding and rolling machines for improving the width of cloth, which gets shrunk during
the washing and dyeing process.
1
Energy Efficient Pump For jet Machine (250 kg)
Printing
In Surat cluster three types printing methods are used. Most of the units are use flat
bed printing, rotary printing and some units follows hand printing. Hand printing is the
old method to print the fabric. The flat bed printing has provision for printing 10 to 14
colors simultaneously. The color print paste prepared is fed onto the screens from
which it is transferred to the fabric fed in. The fabric after print paste transfer is passed
through a drying chamber at 145°C. The dried and printed fabric is taken for further
processing.
After printing, the drying process is performed in loop machine, where the temperature
is maintained between 130°C to 170°C for better colour setting. After passing through
the loop machines, the printed fabric is washed in a series of normal water and hot
water washing in the presence of chemicals for colour setting. After completion of the
washing process, the printed and washed fabric is subjected to heat setting process in
Stenter and then pressing and finishing treatments.
2
Energy Efficient Pump For jet Machine (250 kg)
General Printing
Gray (Raw Material) Grey
(Raw Material)
Scouring (Soflina)
Scouring (Soflina)
Printing
Printing
Hydro Extraction
Hydro Extraction
Pressing
Pressing
Packing/Dispatch Packing/Dispatch
3
Energy Efficient Pump For jet Machine (250 kg)
The main energy forms used in a typical unit in the cluster are electricity, coal/lignite
and natural gas. Electricity is used for driving the prime movers of pumps, fans, stenter
fans, ID and FD fans, conveyers, loop machines drives, lighting etc. Imported coal and
lignite are used as fuel in boilers for steam generation and whereas natural gas is used
as fuel in generators for electricity generation, stenters, printing and loop machines.
The energy consumption of a typical unit in the cluster using local make pumps and
having about 7 Jet machines is furnished in Table 1.1 below:
The average production in a year in a typical unit is 123 lakh meters of final product.
There are about 4200 circulation pumps connected to the jet machines in entire cluster
units and these pumps are of local make and are inefficient. As per the detailed studies
undertaken in various units of the cluster, the efficiency of the pumps is found to be in
the range of 25 to 35% only, where as the KSB pumps have efficiencies above 75%.
The low efficiency of the installed pumps is due to inferior design of the pumps.
The project activity is the installation of new energy efficient pumps for jet machines by
replacing the existing pumps. The pumps are used for circulation of water/cloth during
pre-treatment and dyeing process.
4
Energy Efficient Pump For jet Machine (250 kg)
24 hours in a day.
The power consumption of various jet machines water circulation pump of three cluster
units is furnished in Table 1.2 below
Power
Jet Machines Efficiency of
S. No Name of the unit consumption
Capacity (kg) pump (%)
(kWh/day)
1 Beetex India Limited 250 140 47.5
Jayshaleen Dye & Ptg
2 250 148 44.7
Mills Pvt Ltd
Rohit Dyeing &
3 250 142 46.9
Finishing works
The major technical barriers that prevented the implementation of the energy efficient
pump in the cluster are:
The lack of awareness of the losses and monetary benefit of energy efficient pumps
Not applicable
Information on the energy efficient technologies not available among cluster unit
owners, though the suppliers are available locally of energy efficient pumps, the
information was not disseminated among cluster units.
5
Energy Efficient Pump For jet Machine (250 kg)
The project activity is replacement of jet machine conventional pumps with new energy
efficient pumps. The new pumps will have overall efficiency more than 75%. The
energy efficient pumps will have critically designed impellers, volute, eye and casing.
The impeller is made of Stainless Steel material and are resistant to corrosion and
scale formation.
In Surat Textile Cluster units, the pumps installed for jet machines have efficiencies in
the range of 25% to 35% only due to inferior design of pumps and mismatch selection.
Considering the above facts and for reducing electricity consumption of Jet machine
pumps, it is suggested to install energy efficient pumps of KSB make. The details of
power consumption of various pumps installed for jet machines and efficiency levels
are provided in Annexure 1.
The efficiency of the present pumps installed is of low efficiency (25 to 35%) and
efficiency of the energy efficient pumps will be of 75%. Replacing the conventional
pumps with new energy efficient pumps will reduce power consumption and reduces
production cost.
The pump selected will have same flow and pressure and can be installed to the
present Jet machine.
The new energy efficient pumps are superior to the existing pumps for the following
features:
• Will have constant flow and pressure throughout the life of the pump
6
Energy Efficient Pump For jet Machine (250 kg)
The KSB pump make dealers are available in Surat and the details of the suppliers are
provided in Annexure 6.
The service providers are locally available and contact details of service providers are
given in Annexure 6.
The process down time is considered only one day, as it requires only assembling.
The proposed pump will give the same output w.r.t existing pumps. The details of the
pump selected for 250 kg capacity jet machines is provided below:
7
Energy Efficient Pump For jet Machine (250 kg)
The power savings due to installation of new energy efficient pumps for Jet machines
is 1.34 kWh and for 5 Jet machines is 56,280 kWh per annum.
The product quality may improve, as the pump will give required flow and pressure,
where as in present pumps; the pump parameters are not assured.
Not applicable
8
Energy Efficient Pump For jet Machine (250 kg)
The project activity identified will utilize state-of-the-art technologies to ensure energy
efficiency and energy conservation of non renewable fuels and the project activity
reduce the breakdowns and leakages hence improves working environment.
The equipment selected for the implementation is new and energy efficient. The
equipment implemented will create awareness among the workforce and improves the
skill of the workers.
The project activity will reduce effluent generation, as with new pumps, the leakages
may reduce.
The major GHG emission reduction source is CO2. The technology will reduce grid
electricity consumption and emission reductions are estimated as 47 tonne of CO2 per
annum due to implementation of the project activity.
The equipment reduces the coal consumption and also reduces SOx emissions.
9
Energy Efficient Pump For jet Machine (250 kg)
The total cost for 5 pumps is estimated at ` 4.53 lakh, which includes motor, pump and
base coupling.
The total cost of implementation of the energy efficient boiler is estimated at ` 4.90
lakh. The above cost includes cost of equipment / machinery, cost of fabrication
(and/or) commissioning charges and the details are furnished below
The entrepreneur’s contribution is 25% of total project cost, which works out at ` 1.22
lakh.
The term loan is 70% of the total project, which is ` 3.67 lakh.
The interest rate is considered at 10% which is SIDBI’s rate of interest for energy
efficient projects. The loan tenure is 4 years excluding initial moratorium period is 3
months from the date of first disbursement of loan.
Considering the above discussed assumptions, the net cash accruals starting with `
2.10 lakh in the first year operation gradually increases to ` 6.65 lakh at the end of
fourth year.
10
Energy Efficient Pump For jet Machine (250 kg)
The total project cost of the proposed technology is ` 4.90 lakh and monetary savings
due to reduction in electricity consumption is ` 3.15 lakh and the simple payback
period works out to be 18 months.
The Net present value of the investment at 10.00% interest rate works out to be ` 4.23
lakh.
The after tax Internal Rate of Return of the project works out to be 43.45%. Thus the
project is financially viable.
The average return on investment of the project activity works out at 36.25% for an
investment of ` 4.90 lakh. The average debt service coverage ration works out at 2.58.
A sensitivity analysis has been worked out to ascertain how the project financials
would behave in different situations like there is an increase in electricity savings or
decrease in electricity savings. For the purpose of sensitive analysis, two scenarios are
considered are.
In each scenario, other inputs are assumed as constant. The financial indicators in
each of the above situation are indicated along with standard indicators are shown in
Table 4.2 below:
11
Energy Efficient Pump For jet Machine (250 kg)
The project is highly sensitive to electricity savings, the debt service coverage ratio
works out to be 2.33 times in worst scenario, which indicates the strength of the
project.
The project is expected to be completed in 1 week from the date of financial closure.
The detailed schedule of project implementation is furnished in Annexure 6.
12
Energy Efficient Pump For jet Machine (250 kg)
Annexure
13
Energy Efficient Pump For jet Machine (250 kg)
14
Energy Efficient Pump For jet Machine (250 kg)
The jet machines are the most commonly found equipment in the cluster units and
considerable quantities of hot water or colour water is required for the dyeing process
and this water is supplied by the water pump which consumes lot of electricity. This
study was carried out in 75 industries, and all the units are using conventional pump for
supply of water with high electricity consumption.
The Installation of energy efficient pump will reduce the electricity consumption and
also reduces the green house gas emission.
The various factors influence the selection of the energy efficient pump. The following
were considered:
- Space availability
- Cost economics
15
Energy Efficient Pump For jet Machine (250 kg)
Assumption
Name of the Technology Jet Machine Pumps
Rated Capacity 250 Kg
Flow and head 50 cum/hr and 30 m H
No. of pumps to be replaced 5
Details Unit Value Basis
Installed Capacity Kcal 10
No of working days Days 350
No of Shifts per day Shifts 3
Capacity Utilization Factor %
Proposed Investment
Plant & Machinery ` (in lakh) 4.53
Erection & Commissioning ` (in lakh) 0.25
Investment without IDC ` (in lakh) 4.78
Interest During Implementation ` (in lakh) 0.12
Total Investment ` (in lakh) 4.90
Financing pattern
Own Funds (Equity) ` (in lakh) 1.22 Feasibility Study
Loan Funds (Term Loan) ` (in lakh) 3.67 Feasibility Study
Loan Tenure years 4 Assumed
Moratorium Period Months 3 Assumed
Repayment Period Months 51 Assumed
Interest Rate % 10.00% SIDBI Lending rate
Estimation of Costs
O & M Costs % on Plant & Equip 4.00% Feasibility Study
Annual Escalation % 5.00% Feasibility Study
Estimation of Revenue
Power Saving KWh 56280
Cost `/KWh 5.6
St. line Depn. %age 5.28 Indian Companies Act
IT Depreciation %age 80.00 Income Tax Rules
Income Tax %age 33.99 Income Tax
Estimation of Interest on Term Loan (` in lakh)
Years Opening Balance Repayment Closing Balance Interest
1 3.67 0.54 3.13 0.32
2 3.13 0.72 2.41 0.28
3 2.41 0.96 1.45 0.20
4 1.45 1.20 0.25 0.09
5 0.25 0.25 0.00 0.00
3.67
WDV Depreciation
Particulars / years 1 2 3 4 5
Plant and Machinery
Cost 4.90 0.98 0.20 0.04 0.01
Depreciation 3.92 0.78 0.16 0.03 0.01
WDV 0.98 0.20 0.04 0.01 0.00
16
Energy Efficient Pump For jet Machine (250 kg)
Projected Profitability
Particulars / Years 1 2 3 4 5
Revenue through Savings
Fuel savings 3.15 3.15 3.15 3.15 3.15
Total Revenue (A) 3.15 3.15 3.15 3.15 3.15
Expenses
O & M Expenses 0.20 0.21 0.22 0.23 0.24
Total Expenses (B) 0.20 0.21 0.22 0.23 0.24
PBDIT (A)-(B) 2.96 2.95 2.94 2.92 2.91
Interest 0.32 0.28 0.20 0.09 0.00
PBDT 2.64 2.67 2.74 2.83 2.91
Depreciation 0.26 0.26 0.26 0.26 0.26
PBT 2.38 2.41 2.48 2.57 2.65
Income tax - 0.64 0.88 0.95 0.99
Profit after tax (PAT) 2.38 1.77 1.60 1.62 1.66
Computation of Tax
` (In lakh)
Particulars / Years 1 2 3 4 5
Profit before tax 2.38 2.41 2.48 2.57 2.65
Add: Book depreciation 0.26 0.26 0.26 0.26 0.26
Less: WDV depreciation 3.92 0.78 0.16 0.03 0.01
Taxable profit (1.28) 1.88 2.58 2.80 2.90
Income Tax - 0.64 0.88 0.95 0.99
` (In lakh)
Particulars / Years 1 2 3 4 5
Liabilities
Share Capital (D) 1.22 1.22 1.22 1.22 1.22
Reserves & Surplus (E) 2.38 4.14 5.74 7.37 9.03
Term Loans (F) 3.13 2.41 1.45 0.25 0.00
Total Liabilities D)+(E)+(F) 6.74 7.78 8.42 8.85 10.26
Assets
Gross Fixed Assets 4.90 4.90 4.90 4.90 4.90
Less: Accm. Depreciation 0.26 0.52 0.78 1.03 1.29
Net Fixed Assets 4.64 4.38 4.12 3.86 3.61
Cash & Bank Balance 2.10 3.40 4.30 4.98 6.65
Total Assets 6.74 7.78 8.42 8.85 10.26
Net Worth 3.60 5.37 6.97 8.59 10.26
Dept equity ratio 2.56 1.97 1.19 0.21 0.00
17
Energy Efficient Pump For jet Machine (250 kg)
` (In lakh)
Particulars / Years 0 1 2 3 4 5
Sources
Share Capital 1.22 - - - - -
Term Loan 3.67
Profit After tax 2.38 1.77 1.60 1.62 1.66
Depreciation 0.26 0.26 0.26 0.26 0.26
Total Sources 4.90 2.64 2.03 1.86 1.88 1.92
Application
Capital Expenditure 4.90
Repayment of Loan - 0.54 0.72 0.96 1.20 0.25
Total Application 4.90 0.54 0.72 0.96 1.20 0.25
Net Surplus - 2.10 1.31 0.90 0.68 1.67
Add: Opening Balance - - 2.10 3.40 4.30 4.98
Closing Balance - 2.10 3.40 4.30 4.98 6.65
NPV 3.78
18
Energy Efficient Pump For jet Machine (250 kg)
Return on Investment
` (In lakh)
Particulars / Years 1 2 3 4 5 Total
Net Profit Before Taxes 2.38 2.41 2.48 2.57 2.65 12.48
Net Worth 3.60 5.37 6.97 8.59 10.26 34.79
35.89%
` (In lakh)
Particulars / Years 1 2 3 4 5 Total
Cash Inflow
Profit after Tax 2.38 1.77 1.60 1.62 1.66 9.03
Depreciation 0.26 0.26 0.26 0.26 0.26 1.29
Interest on Term Loan 0.32 0.28 0.20 0.09 0.00 0.90
Total (M) 2.96 2.31 2.06 1.97 1.93 11.22
Debt
Interest on Term Loan 0.32 0.28 0.20 0.09 0.00 0.90
Repayment of Term Loan 0.54 0.72 0.96 1.20 0.25 3.67
Total (N) 0.86 1.00 1.16 1.29 0.25 4.57
Average DSCR (M/N) 2.46
19
Energy Efficient Pump For jet Machine (250 kg)
weeks
S. No. Activities
0-0.5 0.5-1 1-1.5 1.5-2
1 Placement of Orders for Equipment
2 Supply of Pump’s
20
Energy Efficient Pump For jet Machine (250 kg)
21
Energy Efficient Pump For jet Machine (250 kg)
22
Energy Efficient Pump For jet Machine (250 kg)
23
Energy Efficient Pump For jet Machine (250 kg)
24
Standard application form for financial assistance to existing units
(upto and including Rs. 50 lakh)
I Applicant details
1 Name of Unit
2 Address for correspondence
3 Constitution
4 SSI Registration. No.
5 Date of Incorporation
6 Date of Commencement of Operations
7 Activity / Industry
II Promoters/Directors
Bio-data of all the promoters/directors of the unit (Preferably make separate sheet for each
promoter/director)
Promoter/Director
Name
Full Address( incl Tel no./ mobile no)
Age
Passport No.
Father's / husband's name
Qualification
Experience
Functional responsibility in the unit
Relationship with Chief Promoter
Shareholding in the unit
Net worth
Pl. furnish details of any other shareholder having more than 5% in the unit.
Sl. No. Product Installed capacity Present capacity utilisation End use of product Export orientation
p.a.
Yes/ No
Page 1 of 7
Application form for
Loans upto and including Rs. 50 lakh
Facilities enjoyed :
Nature of facility Amount (Rs. lakh) Rate of Nature of Security and value
(bankwise) interest
Sanctioned Outstanding as on ___ ___
Fund based
Basedkfjdffkldkfjdfkjdfkjdfkdjfkdjf
-Term Loan
-Working capital
Non Fund Based
1 Civil Works -
2 Plant & Machinery (incl. installation) * 4.53
-Indigenous
-Imported
3 Professional charges -
4 Erection & commisioning charge 0.25
5 Preliminary & pre-operative expenses [Loan syndication fee etc.] 0.12
&
Page 2 of 7
Application form for
Loans upto and including Rs. 50 lakh
6 Taxes(CST)
7 Contigency -
TOTAL 4.90
* Details of Plant and machinery/ Misc. fixed assets at Annexure II and III
Indicate details of expenditure already incurred, if any and how the expenditure was financed ?
6.3. Means of Finance
(Rs. Lakh)
S. No. No. Details Total
1 Additional share capital / Internal accruals 1.23
2 Interest free Unsecured Loans -
3 Term Loan proposed from SIDBI / Banks inclusive of subsidy #### 3.67
Total 4.90
# ### In terms of existing guidelines of Ministry of MSME , GoI the subsidy amount is received on implementation of the project
Say within 3 months therefore the amount of subsidy is included in the term laon amount as bridge loan and funded by the bank
and
On receipt of the subsidy from the GoI it is adjusted towards the loan amount.
6.4 Whether additional Working Capital required for the unit. If yes, amount and arrangements proposed may
be indicated:
6.5 Technology
S. No. Item
1 Any Technical collaboration? If yes, details
2 Details of main technical professionals employed
3 Any quality certification obtained ? If yes enclose certificate.
1 Raw material
(Details, arrangement, sources and
distance)
2 Power Connected Load
Utilised load
Page 3 of 7
Application form for
Loans upto and including Rs. 50 lakh
6.9 Others
Items
Please indicate the various licenses / consents for the project / unit already obtained from the
respective authorities
Please indicate licenses / consents for the project / unit that are yet to be obtained.
Category as per pollution control dept. If polluting, pollution control measures taken
Whether the project is entitled for any govt. subsidy, tax exemptions. Details thereof
Repayment period (in months) sought including repayment holiday requested, if any,
Details of Collateral security offered and value (basis).
List of guarantors for the proposed loan
Enclose documents as indicated in the check list at Annexure V.
6.10 Strengths / Weaknesses of the borrower (such as market standing, product/ service differentiation,
technical expertise, infrastructure facilities etc.)
Strengths
Weaknesses
DECLARATION
I/We certify that all information furnished by me/ us above and in the appendix/ annexures/ statements and other
papers enclosed is true; I/we have no borrowing arrangements for the unit with any bank / FI except as indicated in
the application; that there are no overdues / statutory dues/government enquiry/proceedings/prosecution against
the unit/associate concerns/ promoters/directors except as indicated in the application; that no legal action has
been/ is being taken against the unit/associate concerns/promoters/directors; that I/ we shall furnish all other
information that may be required by SIDBI in connection with my/our application and I/ We have no objection to
your furnishing the information submitted by me/ us to any agency as you may deem fit in connection with
consideration of the assistance. We have no objection to SIDBI/ its representatives making suitable enquiries while
considering the application.
Place : Signature
Date Name & Designation
Page 4 of 7
Application form for
Loans upto and including Rs. 50 lakh
Annexure I
Details of Associate Concerns
Name , Address & products Existing Name & Address of existing Banker Facilities Enjoyed Share holding of the
manufactured since (s) main promoter(s) of
applicant unit
Annexure II
Name of Name of manufacturer, Lead time Invoice Purpose /use Basis of Remark
machinery, contact person, for delivery price (for of machine selection of s reg.
(model / e-mail address of indigenous supplier after
specification) telephone no. machinery machinery) / sale
CIF price service
(for etc.
imported )
(Rs. lakh)
Energy Deraz Engineers 1 Weeks 0.50 Water Crediability
Efficient 6-3-1177/90, Deraz house, circulation of the
Pumps For BS Maktha, Begumpet in Jet Technolgy
Jet Machine India-500016 Dyeing Provider
E-mail: deraz@deraz.in machine
Mobile:+91 9948353601
Telefax:+040 23412165
Furnish competitive quotations, catalogues / invoice for each machinery proposed to be acquired
In case of second hand /fabricated machinery, indicate the need / reasons for acquiring such machinery. Also enclose
Chartered Engineer's certificate regarding residual value and life in respect of second hand machinery.
Annexure III
Details of Misc. Assets / equipment Proposed
Page 5 of 7
Annexure IV
Profitability projections for the Unit/ Company as a whole*
S.No. Item Actuals for Y1 Y2 Y3 Y4 Y5 TOTAL
previous year
Page 6 of 7
Annexure V
CHECK LIST of documents to be
submitted along with the application
*****
Page 7 of 7
Bureau of Energy Efficiency (BEE)
(Ministry of Power, Government of India)
4th Floor, Sewa Bhawan, R. K. Puram, New Delhi – 110066
Ph.: +91 – 11 – 26179699 (5 Lines), Fax: +91 – 11 – 26178352
Websites: www.bee-india.nic.in, www.energymanagertraining.com
Zenith Energy Services Pvt. Ltd India SME Technology Services Ltd
10-5-6/B, My Home Plaza, Masab DFC Building, Plot No.37-38,
Tank HYDERABAD, AP 500 028 D-Block, Pankha Road,
Phone: 040 23376630, 31, Institutional Area, Janakpuri, New Delhi-110058
Fax No.040 23322517 Tel: +91-11-28525534, Fax: +91-11-28525535
Website: www.zenithenergy.com Website: www.techsmall.com